Fee Review-notes | 4/3/2002 | 4/3/2002 | 3/21/2003 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 8/2/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9288 issued 8-2-02 to Zion's Bank.
|
Code Occupancy Approval | 8/1/2002 | 8/1/2002 | 8/1/2002 | P | DONE |
Carol Montgomery
|
|
|
|
BLD-Final | 7/25/2002 | 7/26/2002 | 7/26/2002 | P | PASS |
Jim Sly
|
|
|
###-#### OK for Perm Occ. 7/26/2002 2:06:43 PM
|
Permanent Occupancy | | 7/26/2002 | 7/26/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/24/2002 | 7/25/2002 | 7/25/2002 | P | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled 7/25/2002 4:24:07 PM
|
BLD-Framing/Rough-in | 7/9/2002 | 7/10/2002 | 7/10/2002 | A | PART |
Dave Hannah
|
|
|
JACK ###-#### CELING GRID pods ok crew can start dropping in pannels but need to leave out areas so elec and mec can inspect 7/10/2002 10:03:27 AM
|
BLD-Framing/Rough-in | 6/14/2002 | 6/17/2002 | 6/17/2002 | A | PART |
Dave Hannah
|
|
|
JACK ###-#### shear ok int framing ok to cover 6/17/2002 11:14:00 AM
|
BLD-Framing/Rough-in | 6/7/2002 | 6/7/2002 | 6/7/2002 | P | PART |
Dave Hannah
|
|
|
r/i- keele ###-#### ext framing ok still need fire blocking areas that have osb sheeting and at vert to horz 6/7/2002 3:16:01 PM
|
BLD-Framing/Rough-in | 5/28/2002 | 5/28/2002 | 5/28/2002 | P | FAIL |
Dave Hannah
|
|
|
shane ###-#### this inspection was for ext walls on the east north and west sides only still needs to finish bolting base to foundation and fire blocking on furred out walls 5/28/2002 2:19:22 PM
|
Routing - PLAN CHECK | 5/1/2002 | | 5/3/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/3/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 5/3/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/3/2002 | | |
|
|
|
|
Telephone call | | | 5/3/2002 | | DONE |
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 5/3/2002 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/9/2002 | | 5/3/2002 | | PASS |
Carl Westfall
|
|
|
5/3/2002 09:37:25 CJW - activity updated through activity BLDA022 from case BLD02-00757.
|
Plan resubmittals received | | | 5/2/2002 | | DONE |
|
|
|
Received two copies of revised sheets SD-1R and S2.1. One copy of structural building analysis. Routed to Carl W. kmm
|
Routing - FIRE | 4/26/2002 | 5/1/2002 | 5/1/2002 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 5/1/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/24/2002 | | 4/26/2002 | | |
|
|
|
Failed first UBC review. UBC plan review started April 24, 2002 and finished April 26, 2002. A response was required from the architect. See the conditions list. A plan review report was sent to the architect.
|
Routing - PLANNING | 4/11/2002 | | 4/24/2002 | | PASS |
|
|
|
Approved for Design Review per DRH02-8. Approved for planning per CUP01-00177 and CVA01-00040.
|
Routing - PUBLIC WORKS | 4/9/2002 | | 4/11/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/4/2002 | | DONE |
|
|
|
Requesting demo.
|
Recd Pcfee & Taken To Pln CK | | | 4/3/2002 | | DONE |
|
|
|
|