BLD-Final | 3/25/2003 | 3/26/2003 | 3/26/2003 | A | PASS |
Carl Dependahl
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Annette Moore...ok for c/o, card to contractor. 3/26/2003 10:34:21 AM
|
Permanent Occupancy | | 3/26/2003 | 3/26/2003 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 3/26/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9605 issued 3-26-03 to Chrisman Dental.
|
BLD-Final | 1/16/2003 | 1/16/2003 | 1/16/2003 | P | PART |
Carl Dependahl
|
|
|
temp occ; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung...ok for t/o... 1/16/2003 4:19:39 PM
|
FIRE-Final Inspection | 1/3/2003 | 1/6/2003 | 1/6/2003 | A | PASS |
Rick Jackson
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
PubWorks Occupancy Approval | 12/13/2002 | 12/13/2002 | 12/13/2002 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 12/13/02. M.Strasser
|
BLD-Framing/Rough-in | 12/5/2002 | 12/6/2002 | 12/6/2002 | A | PART |
Carl Dependahl
|
|
|
ceiling insp -rick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie...grid extensions at existing office area...add spreader bars 12/6/2002 10:53:48 AM
|
BLD-Framing/Rough-in | 12/5/2002 | 12/6/2002 | 12/6/2002 | P | PART |
Carl Dependahl
|
|
|
ceiling insp -rick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie...ok, chk for spreaders at final ...existing office area. 12/6/2002 2:54:17 PM
|
BLD-Framing/Rough-in | 11/14/2002 | 11/15/2002 | 11/15/2002 | A | PART |
Tony Young
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
west main floor framing ok pending trades, and fire blocking ceiling line 11/15/2002 11:11:29 AM
|
BLD-Framing/Rough-in | 10/24/2002 | 10/24/2002 | 10/24/2002 | P | PART |
Carl Dependahl
|
|
|
ceiling; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung...bsmt ok, add firestops at pipes... 10/24/02 6:19:50 PM
|
BLD-Framing/Rough-in | 10/21/2002 | 10/22/2002 | 10/22/2002 | A | PART |
Carl Dependahl
|
|
|
###-####...ok to insulate & place hat channel at bsmt mech rm for 1hr lid....will chk screws for oc spacing when gyp installed. 10/22/02 9:29:00 AM
|
BLD-Framing/Rough-in | 10/16/2002 | 10/17/2002 | 10/17/2002 | P | PART |
Carl Dependahl
|
|
|
ceiling; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung... grid ok 10/17/02 3:45:32 PM
|
BLD-Framing/Rough-in | 10/8/2002 | 10/8/2002 | 10/8/2002 | P | PART |
Carl Dependahl
|
|
|
###-#### soffit ok...below 1hr lid, need hvac ok for ducts 10/9/02 10:04:54 AM
|
BLD-Conference | 10/8/2002 | 10/8/2002 | 10/8/2002 | A | PASS |
Carl Dependahl
|
|
|
re add'l soffit frame, need hvac insp for ducts inside.
|
BLD-Framing/Rough-in | 9/27/2002 | 9/27/2002 | 9/27/2002 | P | PART |
Carl Dependahl
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung... soffit ok pending truss eng's ok; complete fireblocks, chk at grid insp. 9/29/2002 3:40:49 PM
|
BLD-Framing/Rough-in | 9/19/2002 | 9/20/2002 | 9/20/2002 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/19/2002 at 11:32:03. Contact: ###-####. ok to cover still needs insp at mech room 9/20/2002 12:46:21 PM
|
BLD-Energy code compliance | 9/19/2002 | 9/20/2002 | 9/20/2002 | P | PASS |
Tom Arcoraci
|
|
|
rick ###-#### cell
|
BLD-Framing/Rough-in | 9/17/2002 | 9/18/2002 | 9/18/2002 | A | FAIL |
Carl Dependahl
|
|
|
rick cell ###-####
|
BLD-Framing/Rough-in | 9/18/2002 | 9/18/2002 | 9/18/2002 | P | FAIL |
Carl Dependahl
|
|
|
c/n, need truss calcs & for soffit..ok to insul 9/18/2002 6:42:27 PM
|
BLD-Framing/Rough-in | 9/16/2002 | 9/17/2002 | 9/17/2002 | A | CANC |
Dave Hannah
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie--cancel per rick
|
BLD-Framing/Rough-in | 9/16/2002 | 9/17/2002 | 9/17/2002 | A | CANC |
Dave Hannah
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Conference | 9/5/2002 | 9/6/2002 | 9/6/2002 | A | PART |
Carl Dependahl
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung, re r-3 in bsmt, need emer egress, 1hr lid... 9/6/2002 9:33:32 AM
|
BLD-Framing/Rough-in | 9/6/2002 | 9/6/2002 | 9/6/2002 | P | FAIL |
Carl Dependahl
|
|
|
For Carl, see history, C/N issued: provide & firestop 1HR LID/ OCC. SEPARATION 9/6/2002 5:58:24 PM
|
BLD-Footing | 8/21/2002 | 8/21/2002 | 8/21/2002 | P | PART |
Dave Hannah
|
|
|
Phone #: ###-#### front colm pads ok to pour 8/21/2002 3:02:40 PM
|
BLD-Footing | 8/19/2002 | 8/19/2002 | 8/19/2002 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 08/19/2002 at 07:42:58. Contact: ###-####. Pop out section (south of building)rebar exceeds plans). Footing and foundation formed together. 8/19/2002 3:36:46 PM
|
BLD-Footing | 8/19/2002 | 8/19/2002 | 8/19/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/19/2002 at 07:42:58. Contact: ###-####. ext pop-out at front ok. 8/19/2002 4:27:13 PM
|
BLD-Conference | 8/19/2002 | 8/19/2002 | 8/19/2002 | P | PASS |
Carl Dependahl
|
|
|
w/ bldr & HVAC re occ. sep, framing, etc.
|
BLD-Foundation | 7/30/2002 | 7/31/2002 | 7/31/2002 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/30/2002 at 08:54:40. Contact: ###-####.pending s. i. report 7/31/2002 2:27:30 PM
|
BLD-Conference | 7/31/2002 | 7/31/2002 | 7/31/2002 | P | PASS |
Tony Young
|
|
|
w/ contractor,,, rick, about s. i. requirements,, will have from here on out
|
BLD-Footing | 7/24/2002 | 7/25/2002 | 7/25/2002 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 07/24/2002 at 12:52:50. Contact: ###-####.
|
BLD-Foundation | 7/10/2002 | 7/11/2002 | 7/11/2002 | A | PART |
Tony Young
|
|
|
RICK ###-####
|
BLD-Footing | 7/9/2002 | 7/10/2002 | 7/10/2002 | A | PART |
Carl Dependahl
|
|
|
RICK ###-####
|
BLD-Foundation | 7/9/2002 | 7/10/2002 | 7/10/2002 | A | PART |
Carl Dependahl
|
|
|
RICK ###-####
|
BLD-Foundation | 7/2/2002 | 7/3/2002 | 7/3/2002 | A | PART |
Tony Young
|
|
|
found- rick ###-####
wip on forming only, rebar looked at by 301 7/3/2002 12:18:26 PM
|
BLD-Footing | 7/1/2002 | 7/2/2002 | 7/2/2002 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/01/2002 at 13:19:52. Contact: ###-####.ft and wall for first support locations ok to place rebar ok splice is hammered into the soil to be checked on next set up for progrection. 7/2/2002 2:02:54 PM
|
Issue PAID IN FULL permit | | | 6/25/2002 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 5/17/2002 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/17/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/17/2002 | | DONE |
|
|
|
|
Telephone call | | | 5/17/2002 | | DONE |
|
|
|
permit ready
|
Routing - PLAN CHECK | 5/10/2002 | | 5/16/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2002 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 4/9/2002 | | 5/16/2002 | | PASS |
Mike Otto
|
|
|
5/16/2002 10:59:39 MLO - activity updated through activity BLDA022 from case BLD02-00798.
|
Plan resubmittals received | | | 5/10/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheetsA2.0, A2.1, A4.0, A4.1, A8.0, S0.2, S1.2, S2.1, M2.0, M2.1, Structural Calculations, and cover letter. Routed to Mike Otto.
|
Plan Review Completed(1st rev) | | | 5/7/2002 | | FAIL |
|
|
|
|
Routing - FIRE | 5/2/2002 | | 5/7/2002 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 5/2/2002 | | DONE |
|
|
|
UBC corrections
|
Routing - PLAN CHECK | 4/25/2002 | | 5/2/2002 | | FAIL |
|
|
|
corrections faxed and mailed to architect
|
Routing - PLUMBING | 4/24/2002 | | 4/25/2002 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 4/23/2002 | | 4/24/2002 | | PASS |
|
|
|
approved
|
Routing - PLANNING | 4/12/2002 | | 4/22/2002 | | PASS |
|
|
|
Ok by TAC. Sent to MGS 4/19. Approved for Design Review per DRH01-87 (MGS).
|
Routing - PUBLIC WORKS | 4/9/2002 | | 4/12/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/9/2002 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 4/9/2002 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 4/9/2002 | | |
|
|
|
|
First Notice | 4/8/2002 | 4/8/2002 | 4/8/2002 | | DONE |
|
|
|
|
Application received | | | 4/8/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/8/2002 | | DONE |
|
|
|
|