BLD-Final | 7/9/2002 | 7/10/2002 | 7/10/2002 | A | PASS |
Jim Storey
|
|
|
final ok 7/10/2002 9:01:37 AM
|
DOC - Permit Finaled | 7/10/2002 | 7/10/2002 | 7/10/2002 | A | PASS |
Jim Storey
|
|
|
Finaled by inspector at 7/10/2002 9:01:40 AM
|
BLD-Final | 7/8/2002 | 7/9/2002 | 7/9/2002 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 17:38:24. Contact: ###-####. out of time. 7/9/2002 5:32:20 PM
|
BLD-Energy code compliance | 5/21/2002 | 5/21/2002 | 5/21/2002 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/21/2002 at 06:52:39. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/17/2002 | 5/20/2002 | 5/20/2002 | A | FAIL |
Jim Storey
|
|
|
1. justify truss itp conctor at bearing point 3# truss b.
2. seal bldg per bcic.
3. provide leadger atchment to exsting gable at roof rafter.
4. single top plate at bearing wall provide stud under roof loading.
|
BLD-Footing | 4/25/2002 | 4/25/2002 | 4/25/2002 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 04/25/2002 at 06:49:25. Contact: ###-####.
|
BLD-Foundation | 4/25/2002 | 4/25/2002 | 4/25/2002 | A | PASS |
Alan Hauser
|
|
|
4/25/2002 9:46:47 AM
|
Issue PAID IN FULL permit | | | 4/17/2002 | | DONE |
|
|
|
|
Application received | | | 4/9/2002 | | |
|
|
|
|
Plan assigned to (PEP) | 4/9/2002 | | 4/9/2002 | | PASS |
Perry Paine
|
|
|
4/9/2002 07:16:44 PEP - activity updated through activity BLDA022 from case BLD02-00800.
|
Inspector's copy Bld permit | | | 4/9/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/9/2002 | | DONE |
|
|
|
|
Telephone call | | | 4/9/2002 | | DONE |
|
|
|
|