BLD-Final | 5/17/2005 | 5/17/2005 | 5/17/2005 | P | PASS |
Dave Hannah
|
|
|
please call 30 min prior to inspection///michael; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
DOC - Permit Finaled | 5/17/2005 | 5/17/2005 | 5/17/2005 | P | PASS |
Dave Hannah
|
|
|
please call 30 min prior to inspection///michael; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Final | 8/11/2004 | 8/13/2004 | 8/13/2004 | A | NR |
Dave Hannah
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie needs to post address and install drive way and fine grade around house int not finished but life saftey items complete ok to move in to house 8/13/2004 10:43:27 AM
|
PostCard Mailed | | | 8/4/2004 | | SENT |
|
|
|
PostCard has been mailed requesting inspection.
|
BLD - Request for Extension | 12/18/2003 | 12/18/2003 | 12/18/2003 | P | PASS |
Dave Hannah
|
|
|
###-#### Michael
|
BLD-Framing/Rough-in | 7/3/2003 | 7/7/2003 | 7/7/2003 | A | PASS |
Dave Hannah
|
|
|
michael; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 6/30/2003 | 7/1/2003 | 7/1/2003 | A | PART |
Dave Hannah
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Annette Moore talked with engineer and contractor will get letter signing off all changes and steel beams connections 7/1/2003 10:35:16 AM
|
BLD-Framing/Rough-in | 6/26/2003 | 6/26/2003 | 6/26/2003 | P | PASS |
Dave Hannah
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok to insulate 6/27/2003 8:14:58 AM
|
BLD-Framing/Rough-in | 6/20/2003 | 6/23/2003 | 6/23/2003 | A | PART |
Dave Hannah
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Annette Moore fire blocking and straps 6/23/2003 12:12:48 PM
|
BLD-Conference | 4/15/2003 | 4/15/2003 | 4/15/2003 | P | DONE |
Dave Hannah
|
|
|
mike ; Phone #: ###-#### Internet Inspection Request from: Annette Moore smoke detector system for house ok to install 4/15/2003 3:03:11 PM
|
BLD-Framing/Rough-in | 3/5/2003 | 3/6/2003 | 3/6/2003 | A | PART |
Dave Hannah
|
|
|
shear mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie this finishes the shear around the ext the ext is ok to cover 3/6/2003 10:51:17 AM
|
BLD-Conference | 2/26/2003 | 2/27/2003 | 2/27/2003 | A | DONE |
Dave Hannah
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Darla Downs soffits east side of house main level engineer will get me a letter beams and connecctions 2/27/2003 10:50:09 AM
|
BLD-Framing/Rough-in | 10/30/2002 | 10/31/2002 | 10/31/2002 | A | PART |
Dave Hannah
|
|
|
DAN ###-#### looked at shear panels east wall south half ok to cover ext but still needs to finsis hold downs on int side of wall 10/31/2002 11:00:39 AM
|
BLD-Conference | 10/29/2002 | 10/29/2002 | 10/29/2002 | P | NR |
Jim Storey
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylierainning to slick to walk on roof. 10/29/2002 3:18:37 PM
|
BLD-Conference | 10/15/2002 | 10/15/2002 | 10/15/2002 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
upper roof nailing and screwing ok, 10/15/2002 3:15:13 PM
|
BLD-Framing/Rough-in | 10/2/2002 | 10/3/2002 | 10/3/2002 | A | PART |
Tony Young
|
|
|
roof sheeting; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
south sections of roof sheeting,, conf. on other parts of frame,,, need eng. back-up 10/3/2002 12:35:47 PM
|
BLD-Framing/Rough-in | 8/26/2002 | 8/26/2002 | 8/26/2002 | P | PART |
Tony Young
|
|
|
mike; Phone #: ###-####
parts of shear ok under block areas 8/26/2002 3:42:34 PM
|
BLD-Framing/Rough-in | 8/19/2002 | 8/19/2002 | 8/19/2002 | P | PART |
Steven Webb
|
|
|
SHEAR WALL; Phone #: ###-#### Shear--North and northeast sides only--ground floor, ok to cover. 8/19/2002 4:27:50 PM
|
BLD-Footing | 7/9/2002 | 7/9/2002 | 7/9/2002 | P | PART |
Russ Owen
|
|
|
###-#### Plans idicate a (2) bars for 2 foot wall horizontal this is a 3 foot wall , need ok for 2 horizontal in a 3 foot wall talked with contractor at job site, and he called architect will get letter. Subject to ok pour at own risk. 7/9/2002 3:50:08 PM
|
BLD-Footing | 6/21/2002 | 6/24/2002 | 6/24/2002 | P | PART |
Tom Arcoraci
|
|
|
###-#### wip fts 6/24/2002 2:48:24 PM
|
BLD-Footing | 6/21/2002 | 6/21/2002 | 6/21/2002 | P | CANC |
Steven Webb
|
|
|
todd ###-#### Cancelled by contractor 6/21/2002 3:33:05 PM
|
BLD-Foundation | 6/6/2002 | 6/6/2002 | 6/6/2002 | P | PART |
Tony Young
|
|
|
todd ###-#### found wall
wip on mech room walls (wall typ. "P") 6/6/2002 2:40:06 PM
|
BLD-Footing | 6/4/2002 | 6/5/2002 | 6/5/2002 | A | PART |
Dave Hannah
|
|
|
###-#### TODD basement ftgs 6/5/2002 11:37:31 AM
|
BLD-Footing | 6/3/2002 | 6/4/2002 | 6/4/2002 | P | NR |
Dave Hannah
|
|
|
MICHEL ###-####
|
BLD-Foundation | 6/3/2002 | 6/4/2002 | 6/4/2002 | P | CANC |
Tony Young
|
|
|
MICHAEL ###-####
|
BLD-Foundation | 5/31/2002 | 6/3/2002 | 6/3/2002 | P | CANC |
Steven Webb
|
|
|
MIKE ###-#### AND FOUNDATION Cancelled by contractor 6/3/2002 2:17:02 PM
|
Issue PAID IN FULL permit | | | 5/17/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/16/2002 | | |
|
|
|
|
Plan Review Report | | | 5/16/2002 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/16/2002 | | DONE |
|
|
|
|
Telephone call | | | 5/16/2002 | | DONE |
|
|
|
CALLED LEFT MESSAGE PLANS READY 5-16-02///DLD
|
Routing - PLAN CHECK | 4/19/2002 | | 5/16/2002 | | DONE |
|
|
|
|
Pending Assignment by DJO | 4/12/2002 | | 5/16/2002 | | DONE |
Dan Overy
|
|
|
|
Print permit w/o conditions | | | 5/7/2002 | | |
|
|
|
|
Plan Reviewer's activity | | | 5/2/2002 | | PEND |
|
|
|
5/2/02 13:10 I called and left a message with Riley to call me regarding the engineering. Riley called me back and said Lee (EIT) will get with me later today. I left a message on Scott Snyder and Mike Smith's phones letting them know that I have engineering questions and plans are on hold till I talk to the engineer.
|
Routing - PUBLIC WORKS | 4/17/2002 | | 4/19/2002 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/12/2002 | | 4/18/2002 | | PASS |
|
|
|
Needs to show that this property has legal frontage to E Warm Springs Ave AEM.
Called applicant on address issue 4/17/02 told him he needs speak to Dave Miller on fire requirements and also change site plans to reflect where their easement is. Okay with plans AEM. Address on E Warm Springs Ave is okay.
|
Routing - PLANNING Land Div | 4/15/2002 | 4/15/2002 | 4/17/2002 | | PASS |
|
|
|
Approved as per 1941 deed and easement agreement to Warm Springs Avenue.
|
Routing - PLANNING | 4/12/2002 | | 4/15/2002 | | PASS |
|
|
|
Routed to Dave Abo for land division review
|
Application received | | | 4/12/2002 | | |
|
|
|
|