Fee Review-notes | 4/18/2002 | 4/18/2002 | 6/24/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/15/2002 | 5/15/2002 | 5/15/2002 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 5/15/2002 1:36:18 PM
|
Permanent Occupancy | | 5/15/2002 | 5/15/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 5/15/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9136 issued 5-15-02 to Simplot Partners.
|
FIRE-Final Inspection | 5/13/2002 | 5/14/2002 | 5/14/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide approved door hardware on the exterior office doors or remove hardware 5/14/2002 10:53:39 AM
|
BLD-Final | 5/13/2002 | 5/14/2002 | 5/14/2002 | P | FAIL |
Russ Owen
|
|
|
bob- ###-#### call 1st before insp---fn occ--. Needs fire/life/safety inspection, Which has a c/n for door hardware, Note door hardware is not shown on this plan, and must have been shown on original plan and this is not on site at this time, Note door hardware is typically checked an occupancy inspection, not vanila finish. There is 1 door in the ware house that has key locking hardware also 2 doors out of office to sidewalk. 5/14/2002 6:08:25 PM
|
Issue PAID IN FULL permit | | | 5/13/2002 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 4/19/2002 | | 5/10/2002 | | PASS |
|
|
|
5/10/2002 08:32:02 RMH - activity updated through activity BLDA022 from case BLD02-00917.
|
Plan assigned to (R_H) | 4/24/2002 | | 5/10/2002 | | PASS |
|
|
|
5/10/2002 08:32:02 RMH - activity updated through activity BLDA022 from case BLD02-00917.
|
Routing - PLAN CHECK | 5/9/2002 | | 5/10/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/10/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/10/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/10/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/10/2002 | | |
|
|
|
|
Telephone call | | | 5/10/2002 | | DONE |
|
|
|
CALLED LEFT MESSAGE WITH PAT PERMIT READY 5-10-02 ///DLD
|
Routing - FIRE | 5/4/2002 | | 5/9/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/24/2002 | | 5/3/2002 | | FAIL |
Ron Hill
|
|
|
|
Plan Reviewer's activity | | | 5/3/2002 | | FAIL |
|
|
|
Faxed requirements to the Architect Mike Falash on 5/03/02, & routed plans to the fire department.
|
Case Summary (BLD) | | | 5/3/2002 | | DONE |
|
|
|
|
Routing - FIRE | 4/23/2002 | | 4/24/2002 | | NR |
|
|
|
Verified the haz mat summary done by Megan Davis and returned plans to Ron for Bldg review before we can do the UFC Fire review.
|
Routing - PLANNING | 4/22/2002 | | 4/23/2002 | | PASS |
|
|
|
Approved.
|
Routing - PUBLIC WORKS | 4/19/2002 | | 4/22/2002 | | PASS |
|
|
|
Environmental Division.
|
Plans ACCEPTED BY PLAN TECH | | | 4/19/2002 | | DONE |
|
|
|
|
Application received | | | 4/18/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/18/2002 | | DONE |
|
|
|
|