Case Summary (BLD) | | | 5/7/2012 | | |
|
|
|
|
Second Notice BLD | 5/25/2006 | 5/25/2006 | 5/25/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 4/4/2006 | 4/4/2006 | 5/25/2006 | | DONE |
Jim Sly
|
|
|
|
BLD-Final | 4/4/2006 | 4/4/2006 | 4/4/2006 | A | PASS |
Jim Sly
|
|
|
C/C by Cathy W.
|
DOC - Permit Finaled | 4/4/2006 | 4/4/2006 | 4/4/2006 | P | PASS |
Jim Sly
|
|
|
C/C by Cathy W
|
Letter of compliance | | | 10/18/2002 | | DONE |
|
|
|
Letter of Compliance #22748issued 10-18-02.
|
FIRE-Final Inspection | 10/8/2002 | 10/8/2002 | 10/8/2002 | P | PASS |
Troy Cobbley
|
|
|
fire alarm, fire sprinkler and life safety finaled
|
BLD-Final | 8/23/2002 | 8/23/2002 | 8/23/2002 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/23/2002 at 11:19:06. Contact: ###-####. C/N Need all req. signatures for Perm Occ. status within 90 days of this notice. OK for Temp.
8/23/2002 12:24:02 PM 8/23/2002 12:24:30 PM
|
Temporary occupancy | | | 8/23/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4852 issued 8-23-02 to Lowell Scott Middle School.
|
BLD-Framing/Rough-in | 8/21/2002 | 8/21/2002 | 8/21/2002 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/21/2002 at 08:20:13. Contact: ###-####. 2hr walls appear OK. 8/21/2002 3:14:30 PM
|
FIRE-Final Inspection | 8/21/2002 | 8/21/2002 | 8/21/2002 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given for the fire alarm and the life safety per Steve Minnis's with the Boise Fire Dept. permission until the approved fire alarm plans and any modifications are made 8/23/2002 11:18:40 AM
|
BLD-Framing/Rough-in | 8/12/2002 | 8/13/2002 | 8/13/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/12/2002 at 17:01:39. Contact: ###-####. OKd 2hr at storage room near Multi purpouse WP 7060 8/13/2002 12:22:34 PM
|
BLD-Framing/Rough-in | 8/8/2002 | 8/8/2002 | 8/8/2002 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/08/2002 at 09:51:18. Contact: ###-####. Multi purpouse, band/chior and 2hr walls adjacent......OK. 8/9/2002 11:06:36 AM
|
BLD-Framing/Rough-in | 8/6/2002 | 8/7/2002 | 8/7/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/06/2002 at 15:52:24. Contact: ###-####. OK rooms 3 c 8/7/2002 1:10:14 PM
|
BLD-Framing/Rough-in | 8/5/2002 | 8/5/2002 | 8/5/2002 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/05/2002 at 07:21:03. Contact: ###-####. O K...Misc grid 2hr walls. 8/5/2002 4:00:42 PM 8/5/2002 4:01:23 PM
|
BLD-Framing/Rough-in | 7/31/2002 | 8/1/2002 | 8/1/2002 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/31/2002 at 15:48:18. Contact: ###-####. C/N....Varify 2hr rating on infill on 2hr.Occ. sep wall W.multi rm, Data for no reduced rating at exist electr panel, Firestop at fire barrier wall E. gym. 8/1/2002 12:20:31 PM 8/1/2002 12:38:18 PM
|
BLD-Framing/Rough-in | 7/24/2002 | 7/25/2002 | 7/25/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/24/2002 at 14:22:36. Contact: ###-####.
|
FIRE-Sprinkler Rough-in | 7/24/2002 | 7/24/2002 | 7/24/2002 | P | PART |
Troy Cobbley
|
|
|
area 3C ok to cover. sprinkler head locations will still need to be verified 7/24/2002 1:35:36 PM
|
BLD-Framing/Rough-in | 7/19/2002 | 7/22/2002 | 7/22/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/19/2002 at 14:58:36. Contact: ###-####. Pre insp area B. 7/22/2002 11:20:25 PM
|
BLD-Framing/Rough-in | 7/15/2002 | 7/16/2002 | 7/16/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/15/2002 at 13:18:09. Contact: ###-####.rear area of non rated construction only, north side ok pending other trades. 7/16/2002 11:18:22 AM
|
BLD-Conference | 7/1/2002 | 7/2/2002 | 7/2/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/01/2002 at 16:28:49. Contact: ###-####. Discussed need for UL listed tested assemblies for all varied penitrations and beam/joist pockets for firestopping at 2hr walls. 7/4/2002 1:14:40 AM
|
BLD-Conference | 6/20/2002 | 6/21/2002 | 6/21/2002 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 06/20/2002 at 16:15:33. Contact: ###-####. Contr. would like to phase project.....Need OK from all other inspectors.....Need map and log of project for insp verifications. 6/21/2002 11:04:08 AM
|
Issue PAID IN FULL permit | | | 5/31/2002 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 4/22/2002 | | 5/20/2002 | | PASS |
Mike Otto
|
|
|
5/20/2002 09:07:04 MLO - activity updated through activity BLDA022 from case BLD02-00937.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/20/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/20/2002 | | DONE |
|
|
|
|
Telephone call | | | 5/20/2002 | | DONE |
|
|
|
CALLED ED LEFT MESSAGE PERMIT READY 5-20-02///DLD
|
Routing - FIRE | 5/17/2002 | | 5/17/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 5/13/2002 | | 5/17/2002 | | PASS |
|
|
|
|
Plan resubmittals received | | | 5/15/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A0.02, A1.01, A2.01, A2.02, A2.03, A7.03, A8.01, with response letter, structural calculations, and letter from United Water. Routed to Mike Otto.
|
Routing - FIRE | 5/8/2002 | | 5/13/2002 | | FAIL |
|
|
|
|
Plan Review Completed(1st rev) | | | 5/9/2002 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 4/26/2002 | | 5/8/2002 | | FAIL |
|
|
|
corrections sent to architect
|
Plan resubmittals requested | | | 5/8/2002 | | FAIL |
|
|
|
UBC corrections
|
Routing - PLUMBING | 4/24/2002 | | 4/26/2002 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/22/2002 | | 4/24/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 4/24/2002 | | 4/24/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/22/2002 | | DONE |
|
|
|
|
First Notice | 4/19/2002 | 4/19/2002 | 4/19/2002 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/19/2002 | | DONE |
|
|
|
|
Application received | | | 4/19/2002 | | |
|
|
|
|