Permanent Occupancy | | 12/2/2004 | 12/2/2004 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/3/2002 | 12/4/2002 | 12/4/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety and fire sprinklers finaled 12/4/2002 10:43:23 AM
|
BLD-Final | 12/3/2002 | 12/4/2002 | 12/4/2002 | A | CANC |
Tony Young
|
|
|
late pm ###-####
|
BLD-Final | 12/4/2002 | 12/4/2002 | 12/4/2002 | P | PASS |
Tony Young
|
|
|
late pm
ok for perm. occupancy 12/4/2002 3:24:11 PM
|
Permanent occupancy UNPAID FEE | | | 12/4/2002 | | DONE |
|
|
|
Issued to Laundry Mutt #9463 aml
|
FIRE-Final Inspection | 12/3/2002 | 12/3/2002 | 12/3/2002 | P | FAIL |
Troy Cobbley
|
|
|
sprinklers are now correct but the duct smoke detector needs to have the correct type of wire installed 12/3/2002 2:48:02 PM
|
BLD-Final | 12/3/2002 | 12/3/2002 | 12/3/2002 | P | PART |
Tony Young
|
|
|
call first to meet there ###-####
ok for temp occ. pending fire/lifesafety sign-off 12/3/2002 2:41:09 PM
|
FIRE-Final Inspection | 11/27/2002 | 11/29/2002 | 11/29/2002 | A | FAIL |
Troy Cobbley
|
|
|
sprinkler pendants appear to exceed the design spacing of the overhead system which they cannot due per note #6 on the fire review comments, provide a canopy for the sprinkler head missing one, provide key and cover on the knox key box and provide a test for the duct detector 11/29/2002 9:42:30 AM
|
BLD-Framing/Rough-in | 11/8/2002 | 11/8/2002 | 11/8/2002 | P | PART |
Tony Young
|
|
|
ceiling grid -bruce--lock box on front door is 1290; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
ok pending trades and check south end wires at final for tightness and wires on air defussers 11/12/2002 8:38:01 AM
|
BLD-Framing/Rough-in | 10/22/2002 | 10/25/2002 | 10/25/2002 | A | FAIL |
Tony Young
|
|
|
ceiling grid\\lock box 1290; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
c/n posted 10/25/2002 10:10:57 AM
|
BLD-Framing/Rough-in | 9/26/2002 | 9/26/2002 | 9/26/2002 | P | PASS |
Jim Sly
|
|
|
bruce--lock box on front door- 1092; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Issue PAID IN FULL permit | | | 7/29/2002 | | DONE |
|
|
|
|
Telephone call | | | 7/26/2002 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (JCB) | 4/25/2002 | | 5/23/2002 | | PASS |
Jason Blais
|
|
|
5/23/2002 10:46:06 JCB - activity updated through activity BLDA022 from case BLD02-00955.
|
Routing - PLAN CHECK | 5/13/2002 | | 5/23/2002 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/23/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 5/23/2002 | | |
|
|
|
|
Print Occupancy Form | | | 5/23/2002 | | DONE |
|
|
|
|
Telephone call | | | 5/23/2002 | | DONE |
|
|
|
CALLED BRUCE PERMIT READY 5-23-02 ///DLD
|
Routing - PLUMBING | 5/22/2002 | 5/22/2002 | 5/22/2002 | | PASS |
|
|
|
1 1/4" branch line to serve 10 tubs, wc, lav cw, all fixtures to be trapped and vented per 2000 upc.
|
Plan resubmittals received | | | 5/22/2002 | | DONE |
|
|
|
Received two sets of Sheets "2" via Bill Vandergrift with Plumbing's plan review. Routed to Jason Blais.
|
Telephone call | | | 5/20/2002 | | DONE |
|
|
|
Called contractor, Bruce Borup, concerning new Plumbing Plans required to be submitted. He said they would be coming in the next day or two.
|
Routing - FIRE | 5/9/2002 | | 5/13/2002 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 5/13/2002 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 5/7/2002 | | 5/9/2002 | | PEND |
|
|
|
Plan review report sent and faxed to contractor. No response required. Plumbing Division has issues needing to be resolved. Plans to route to Fire Dept. for review. Then will need to be routed to Plumbing again when resubmittals received.
|
Routing - PLUMBING | 5/2/2002 | | 5/7/2002 | | FAIL |
|
|
|
please provide a plumbing plan showing a water system serving the 48 fixture units, premise protection if required, thermol expantion protection, cross connection protection to the tubs, also include venting for the waste system.
|
Routing - PUBLIC WORKS | 4/25/2002 | | 5/2/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/23/2002 | | DONE |
|
|
|
|
First Notice | 4/22/2002 | 4/22/2002 | 4/22/2002 | | DONE |
|
|
|
|
Application received | | | 4/22/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/22/2002 | | DONE |
|
|
|
|