Permit Information
Permit NumberBLD02-00978
StatusFinaled
Name AMERICAN ECOLOGY
Site Address 300 E MALLARD DR Unit: (3RD FLR)
Project NameLAKEPOINTE CENTRE 1
Customer Number 
ePlanReviewNo
Description
(AMERICAN ECOLOGY - LAKEPOINTE CENTRE - 3RD FLR) This building is fire sprinklered to substitute for 1-hr fire-resistive construction. To expand an existing office tenant space on the 3rd floor to 7,210 square feet. Work is to include interior nonbearing walls, suspended ceilings, doors, windows, and finishes all per approved drawings and plan review conditions on file. The location of fire sprinkler heads shall comply with NFPA 13-1999 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes4/24/20024/24/20028/10/2004 DONE
First Notice 9/18/20039/18/2003 DONE
BLD-Aging Inspection8/15/20038/15/20038/15/2003 PASS
DetailsJim Storey
final ok 8/15/2003 8:17:19 AM
DOC - Permit Finaled8/15/20038/15/20038/15/2003APASS
DetailsJim Storey
Finaled by inspector at 8/15/2003 8:17:21 AM
Permanent occupancy  6/18/2003 DONE
Perm. Occ. Cert. #9694 issued 6-18-03 to American Ecology in the Lakepoint Centre Bldg. #1.
Permanent Occupancy 6/12/20036/12/2003 DONE
Details
BLD-Final6/11/20036/12/20036/12/2003APASS
DetailsJim Storey
pat; Phone #: ###-#### Internet Inspection Request from: Barbara Moore final ok 6/12/2003 3:30:47 PM
BLD-Final6/10/20036/11/20036/11/2003AFAIL
DetailsJim Storey
pat; Phone #: ###-#### Internet Inspection Request from: Annette Moore smoke seal west door at receptionest. 6/11/2003 9:44:22 AM
BLD-Aging Inspection6/10/20036/10/20036/10/2003 FAIL
DetailsJim Storey
called jack to obtain final. 6/10/2003 2:57:27 PM
BLD-Aging Inspection4/10/20034/10/20034/10/2003 PART
DetailsJim Storey
east 1/2 sheer ok/ c/n to arch. 4/10/2003 2:23:31 PM
BLD-Final6/28/20027/1/20027/1/2002PFAIL
DetailsJim Storey
###-#### ###-####previous c/n not done. 7/1/2002 1:05:56 PM
FIRE-Final Inspection6/28/20027/1/20027/1/2002APASS
DetailsRick Jackson
JACK ###-#### card not there; final okay 7/1/2002 8:45:15 AM
BLD-Final6/27/20026/28/20026/28/2002AFAIL
DetailsJim Storey
1. (Main exit hardware) In B, F, M and S Occupancies, key-locking hardware may be used on the main exit where the main exit consists of a single door or pair of doors where there is a readily visible, durable sign on or adjacent to the door stating, "THIS DOOR MUST REMAIN UNLOCKED DURING BUSINESS HOURS". The sign shall be in letters not less than 1 inch high on a contrasting background. When unlocked, the single door or both leaves of a pair of doors must be free to swing without operation of any latching device. (1997 UBC 1003.3.1.8 Exception #1) When determining which door is the main exit door, consider the door that must be unlocked in order to conduct business. In other words, if the main exit door was locked, customers could not enter and business could not take place. Keeping the main exit door unlocked during business hours is therefore self regulating.

2. smoke seals and closers on all rated door openings.

3. gyp on coridor at recption rm. storage rm to tunnal gyp const.
FIRE-Final Inspection6/28/20026/28/20026/28/2002AFAIL
DetailsRick Jackson
Added by Inspector: 409 On 6/28/2002 9:53:17 AM extinguishers; pull station obstructed by door
FIRE-Sprinkler Rough-in6/21/20026/21/20026/21/2002PPASS
DetailsRick Jackson
Added by Inspector: 409 On 6/21/2002 3:43:34 PM okay to cover
BLD-Framing/Rough-in5/30/20025/31/20025/31/2002APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 05/30/2002 at 14:36:38. Contact: ###-####.c/n on site maintanestair and corridor / top suport walls / lable saftey glazing. 5/31/2002 10:17:42 AM
Issue PAID IN FULL permit  5/15/2002 DONE
Routing - PLAN CHECK5/13/2002 5/14/2002 PASS
PLANS/APPL TAKEN TO FRONT DESK  5/14/2002 PASS
Inspection Record Card- Bld  5/14/2002  
Print Occupancy Form  5/14/2002  
Telephone call  5/14/2002 DONE
left mess that permit is ready
Plan assigned to (CJW)4/26/2002 5/14/2002 PASS
DetailsCarl Westfall
5/14/2002 08:40:17 CJW - activity updated through activity BLDA022 from case BLD02-00978.
Plan Review Completed(1st rev)  5/13/2002 PASS
Routing - FIRE5/8/2002 5/13/2002 PASS
Routing - PLAN CHECK4/29/2002 5/8/2002 PASS
UBC plan review started May 7, 2002 and finished the next day. The drawings were approved with conditions. See the conditions list.
Routing - PUBLIC WORKS4/26/2002 4/29/2002 PASS
Plans ACCEPTED BY PLAN TECH  4/24/2002  
Application received  4/24/2002  
Recd Pcfee & Taken To Pln CK  4/24/2002 DONE