IHOP * To construct a 4,985 sq. ft. one story, Type VN restaurant on a developed pad. Other work will include grading, paving, landscaping and lighting and as shown on the approved plans and attachments. DRH01-00155 CUP73-00093 .
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/1/200211/1/200211/1/2002PPASS
DetailsRuss Owen
JOE ###-#### ok perm oc. 11/1/2002 1:34:10 PM
Permanent Occupancy 11/1/200211/1/2002 DONE
Details
Permanent occupancy UNPAID FEE  11/1/2002 DONE
Perm. Occ. Cert. #9426 issued 11-1-02 to IHOP #9899.
BLD-Final10/31/200210/31/200210/31/2002PCANC
DetailsRuss Owen
###-####
(F) Reprint permit  10/28/2002 DONE
(F) Reprint permit  10/28/2002 DONE
(F) Reprint permit  10/28/2002 DONE
BLD-Final10/15/200210/16/200210/16/2002APART
DetailsRuss Owen
###-#### Ok temp oc c/n posted and needs all other req signatures. 10/16/2002 12:38:33 PM
FIRE-Final Inspection10/16/200210/16/200210/16/2002PPASS
DetailsTroy Cobbley
fire life/safety finaled 10/16/2002 8:58:22 AM
Code Occupancy Approval10/17/200210/16/200210/16/2002APASS
DetailsScott M.Brown
ALL CONDITIONS MET SO SIGNED FINAL OCCUPANCY 10/17/2002 9:20:15 AM
Temporary occupancy  10/16/2002 DONE
Temp. Occ. Cert. #4875 issued 10-16-02 to IHOP.
PubWorks Occupancy Approval10/15/200210/15/200210/15/2002 DONE
Drainage project complete, signed permanent occupancy 10/15/02. R.Rokovitz
BLD-Final10/14/200210/15/200210/15/2002PNR
DetailsSteven Webb
###-#### Need all sign-offs prior to final inspection. 10/15/2002 3:00:35 PM
FIRE-Final Inspection10/14/200210/15/200210/15/2002PFAIL
DetailsTroy Cobbley
Barrell on the fire hydrant needs to be turned so the 4" outlet points over the curb (south) all other items are ok 10/15/2002 2:26:55 PM
FIRE-Alarm Testing10/10/200210/11/200210/11/2002PPASS
DetailsTroy Cobbley
Inspection was for the kitchen hood system. The hood operated properly with all caps blowing off, power, gas and make up air shutting off 10/11/2002 3:06:01 PM
BLD-Other10/3/200210/3/200210/3/2002ACANC
DetailsRuss Owen
Scheduled by a contractor via Hello! on 10/03/2002 at 07:05:45. Contact: ###-####.
BLD-Other10/3/200210/3/200210/3/2002PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/03/2002 at 08:21:07. Contact: ###-####. grid ok 10/3/2002 3:28:18 PM
BLD-Other10/2/200210/2/200210/2/2002PNR
DetailsRuss Owen
Scheduled by a contractor via Hello! on 10/02/2002 at 07:52:23. Contact: ###-####. needs electrical and mechanical and also work needs to be complete. I should have not been called out at this time I have spoke with contractor at a prior inspection about calling inspections when work is complteted. As we have a 2 times a day which we will be AM and PM . there is no need to call for an inspection unless work is complete. 10/2/2002 2:06:52 PM
BLD-Framing/Rough-in9/5/20029/5/20029/5/2002PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 09/05/2002 at 08:02:19. Contact: ###-####. Just need to repair draftstop at penetrations. Contractor notified. also complete below beam at rest room other items ok./5/2002 2:24:19 PM 9/5/2002 2:24:40 PM
BLD-Framing/Rough-in9/3/20029/4/20029/4/2002ACANC
DetailsRuss Owen
Scheduled by a contractor via Hello! on 09/03/2002 at 12:07:48. Contact: ###-####.did this 9/3. 9/4/2002 9:45:02 AM
BLD-Wall cover8/29/20029/3/20029/3/2002PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 08/29/2002 at 08:41:08. Contact: ###-####. need draft stops and roof starps added below ceiling contractor on site will recall all of which are prior c/ns. 9/3/2002 4:29:00 PM
BLD-Energy code compliance8/29/20028/29/20028/29/2002PFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 08/29/2002 at 08:40:14. Contact: ###-####.c/n posted same corrections. 8/29/2002 4:46:58 PM
BLD-Other8/27/20028/27/20028/27/2002PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 08/27/2002 at 09:20:57. Contact: ###-####.dumpster. Also talked with framer and advised to wait for the engineers revisions before performing any repairs. 8/27/2002 1:50:30 PM
BLD-Framing/Rough-in8/23/20028/26/20028/26/2002AFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 08/23/2002 at 14:20:07. Contact: ###-####.c/n posted. 8/26/2002 3:01:19 PM
BLD-Energy code compliance8/23/20028/26/20028/26/2002ANR
DetailsRuss Owen
Scheduled by a contractor via Hello! on 08/23/2002 at 14:20:50. Contact: ###-####.
BLD-Wall cover8/23/20028/26/20028/26/2002AFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 08/23/2002 at 14:21:29. Contact: ###-####.
BLD-Framing/Rough-in8/21/20028/22/20028/22/2002ACANC
DetailsDave Hannah
Scheduled by a contractor via Hello! on 08/21/2002 at 15:11:20. Contact: ###-####. out of time am resch for pm 8/22/2002 12:47:05 PM
BLD-Framing/Rough-in8/22/20028/22/20028/22/2002PPART
DetailsDave Hannah
shear ok to cover ext walls ok to insulate ext walls need to fix diagonal bracing roof to wall per engineering 8/22/2002 2:26:56 PM
BLD-Framing/Rough-in8/20/20028/21/20028/21/2002APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 08/20/2002 at 15:23:56. Contact: ###-####. Ok to cover roof only interior and exterior have not been inspected, Note: contractor has asked me if ok to insulate and I have told him no as it is not ready and They have never called for interior framing or exterior shear inspection roof area only. 8/21/2002 3:28:24 PM
BLD-Foundation8/17/20028/19/20028/19/2002PPASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 08/17/2002 at 09:37:25. Contact: ###-####.trash enclosure. 8/19/2002 3:31:34 PM
BLD-Framing/Rough-in8/19/20028/19/20028/19/2002PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 08/19/2002 at 09:09:36. Contact: ###-####.partial on roof needs south parpet completed. 8/19/2002 4:09:53 PM
BLD-Framing/Rough-in8/14/20028/15/20028/15/2002PFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 08/14/2002 at 11:05:22. Contact: ###-####.verbal c/n with contractor on site will recall. 8/15/2002 4:37:54 PM
BLD-Concrete7/24/20027/25/20027/25/2002PCANC
DetailsRuss Owen
Scheduled by a contractor via Hello! on 07/24/2002 at 16:22:56. Contact: ###-####.
BLD-Footing7/16/20027/17/20027/17/2002APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 07/16/2002 at 13:34:02. Contact: ###-####.ok first pour of 2, new detail from engineer. 7/17/2002 11:13:27 AM
BLD-Footing7/12/20027/15/20027/15/2002PFAIL
DetailsRuss Owen
JACK- ###-#### FTContractor on site footing and general, I told them to contact the engineer as footing cold joint would not be as per plan. Need a new detail. They said they would call me back to confirm. Do not pour at this time. 7/15/2002 5:39:56 PM
(F) Reprint permit  6/26/2002  
Issue PAID IN FULL permit  6/25/2002 DONE
Plan assigned to (MLO)4/30/2002 6/14/2002 PASS
DetailsMike Otto
6/14/2002 08:41:57 MLO - activity updated through activity BLDA022 from case BLD02-01028.
Routing Off Site - STRUCTURAL6/12/2002 6/14/2002 PASS
Contacted PDQ to take resubmitted plans and structural calcs. of 6/11/02 to outside engineering. KMM
PLANS/APPL TAKEN TO FRONT DESK  6/14/2002 DONE
Print Occupancy Form  6/14/2002 DONE
Inspection Record Card- Bld  6/14/2002 DONE
Telephone call  6/14/2002 DONE
SPOKE WITH LINDA BERGSTRAND PERMIT READY AND FEES DUE, REQUIRES ACHD
Routing - PLAN CHECK6/11/2002 6/11/2002 PASS
Plan resubmittals received  6/10/2002 DONE
Received (1) separate set of resubmittal sheets S-1, S-2, S-3, S-4, S-5, (2) sets of structural calculations, (2) sets of resubmittal sheets CS-1, C.1, C.2, C.3, SD-1, L-1, L-2, A-1, A-2, A-3, A-4, A-5, A-7, A-8, A-10, A-11, A-12, A-15, A-16, S-1, S-2, S-3, S-4, S-5, M-1, M-2, M-5, M-6, P-2, P-4, E-2, EQ-1, EQ-4, with cover letter. Routed to Mike Otto.
Routing - FIRE5/24/20035/29/20025/31/2002 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  5/31/2002 DONE
Routing Off Site - STRUCTURAL5/1/2002 5/24/2002 FAIL
contacted pdq to take plans to outside eng. kmm
Plan resubmittals requested  5/24/2002 DONE
UBC and structural review comments
Routing - PLAN CHECK5/17/2002 5/24/2002 FAIL
corrections mailed and faxed to architect
Routing - PLUMBING5/8/2002 5/17/2002 PASS
no indirect waste receptors will be allowed with in a cabinet, cross connection protection may be required on the supply to beverags mechs at the service counter, additional cross connection protection may be required.
Routing - PLANNING5/7/2002 5/8/2002 PASS
Approved per DRH01-155.
Routing - PUBLIC WORKS5/1/2002 5/6/2002 PASS
Routing - PLANNING Land Div5/1/2002 5/1/2002 PASS
ROS #2901
Plans ACCEPTED BY PLAN TECH  5/1/2002 DONE
First Notice4/30/20024/30/20024/30/2002 DONE
has owner supplied equipment --big sinks(6), icemaker--called and left mesg for edd
Plan routing begun/NEW & ADDTN  4/30/2002 DONE
Application received  4/30/2002  
Recd Pcfee & Taken To Pln CK  4/30/2002 DONE