BLD-Final | 11/1/2002 | 11/1/2002 | 11/1/2002 | P | PASS |
Russ Owen
|
|
|
JOE ###-#### ok perm oc. 11/1/2002 1:34:10 PM
|
Permanent Occupancy | | 11/1/2002 | 11/1/2002 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 11/1/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9426 issued 11-1-02 to IHOP #9899.
|
BLD-Final | 10/31/2002 | 10/31/2002 | 10/31/2002 | P | CANC |
Russ Owen
|
|
|
###-####
|
(F) Reprint permit | | | 10/28/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/28/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/28/2002 | | DONE |
|
|
|
|
BLD-Final | 10/15/2002 | 10/16/2002 | 10/16/2002 | A | PART |
Russ Owen
|
|
|
###-#### Ok temp oc c/n posted and needs all other req signatures. 10/16/2002 12:38:33 PM
|
FIRE-Final Inspection | 10/16/2002 | 10/16/2002 | 10/16/2002 | P | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled 10/16/2002 8:58:22 AM
|
Code Occupancy Approval | 10/17/2002 | 10/16/2002 | 10/16/2002 | A | PASS |
Scott M.Brown
|
|
|
ALL CONDITIONS MET SO SIGNED FINAL OCCUPANCY 10/17/2002 9:20:15 AM
|
Temporary occupancy | | | 10/16/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4875 issued 10-16-02 to IHOP.
|
PubWorks Occupancy Approval | 10/15/2002 | 10/15/2002 | 10/15/2002 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 10/15/02. R.Rokovitz
|
BLD-Final | 10/14/2002 | 10/15/2002 | 10/15/2002 | P | NR |
Steven Webb
|
|
|
###-#### Need all sign-offs prior to final inspection. 10/15/2002 3:00:35 PM
|
FIRE-Final Inspection | 10/14/2002 | 10/15/2002 | 10/15/2002 | P | FAIL |
Troy Cobbley
|
|
|
Barrell on the fire hydrant needs to be turned so the 4" outlet points over the curb (south) all other items are ok 10/15/2002 2:26:55 PM
|
FIRE-Alarm Testing | 10/10/2002 | 10/11/2002 | 10/11/2002 | P | PASS |
Troy Cobbley
|
|
|
Inspection was for the kitchen hood system. The hood operated properly with all caps blowing off, power, gas and make up air shutting off 10/11/2002 3:06:01 PM
|
BLD-Other | 10/3/2002 | 10/3/2002 | 10/3/2002 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/03/2002 at 07:05:45. Contact: ###-####.
|
BLD-Other | 10/3/2002 | 10/3/2002 | 10/3/2002 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/03/2002 at 08:21:07. Contact: ###-####. grid ok 10/3/2002 3:28:18 PM
|
BLD-Other | 10/2/2002 | 10/2/2002 | 10/2/2002 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/02/2002 at 07:52:23. Contact: ###-####. needs electrical and mechanical and also work needs to be complete. I should have not been called out at this time I have spoke with contractor at a prior inspection about calling inspections when work is complteted. As we have a 2 times a day which we will be AM and PM . there is no need to call for an inspection unless work is complete. 10/2/2002 2:06:52 PM
|
BLD-Framing/Rough-in | 9/5/2002 | 9/5/2002 | 9/5/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/05/2002 at 08:02:19. Contact: ###-####. Just need to repair draftstop at penetrations. Contractor notified. also complete below beam at rest room other items ok./5/2002 2:24:19 PM 9/5/2002 2:24:40 PM
|
BLD-Framing/Rough-in | 9/3/2002 | 9/4/2002 | 9/4/2002 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/03/2002 at 12:07:48. Contact: ###-####.did this 9/3. 9/4/2002 9:45:02 AM
|
BLD-Wall cover | 8/29/2002 | 9/3/2002 | 9/3/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/29/2002 at 08:41:08. Contact: ###-####. need draft stops and roof starps added below ceiling contractor on site will recall all of which are prior c/ns. 9/3/2002 4:29:00 PM
|
BLD-Energy code compliance | 8/29/2002 | 8/29/2002 | 8/29/2002 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/29/2002 at 08:40:14. Contact: ###-####.c/n posted same corrections. 8/29/2002 4:46:58 PM
|
BLD-Other | 8/27/2002 | 8/27/2002 | 8/27/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/27/2002 at 09:20:57. Contact: ###-####.dumpster. Also talked with framer and advised to wait for the engineers revisions before performing any repairs. 8/27/2002 1:50:30 PM
|
BLD-Framing/Rough-in | 8/23/2002 | 8/26/2002 | 8/26/2002 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/23/2002 at 14:20:07. Contact: ###-####.c/n posted. 8/26/2002 3:01:19 PM
|
BLD-Energy code compliance | 8/23/2002 | 8/26/2002 | 8/26/2002 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/23/2002 at 14:20:50. Contact: ###-####.
|
BLD-Wall cover | 8/23/2002 | 8/26/2002 | 8/26/2002 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/23/2002 at 14:21:29. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/21/2002 | 8/22/2002 | 8/22/2002 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 08/21/2002 at 15:11:20. Contact: ###-####. out of time am resch for pm 8/22/2002 12:47:05 PM
|
BLD-Framing/Rough-in | 8/22/2002 | 8/22/2002 | 8/22/2002 | P | PART |
Dave Hannah
|
|
|
shear ok to cover ext walls ok to insulate ext walls need to fix diagonal bracing roof to wall per engineering 8/22/2002 2:26:56 PM
|
BLD-Framing/Rough-in | 8/20/2002 | 8/21/2002 | 8/21/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/20/2002 at 15:23:56. Contact: ###-####. Ok to cover roof only interior and exterior have not been inspected, Note: contractor has asked me if ok to insulate and I have told him no as it is not ready and They have never called for interior framing or exterior shear inspection roof area only. 8/21/2002 3:28:24 PM
|
BLD-Foundation | 8/17/2002 | 8/19/2002 | 8/19/2002 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/17/2002 at 09:37:25. Contact: ###-####.trash enclosure. 8/19/2002 3:31:34 PM
|
BLD-Framing/Rough-in | 8/19/2002 | 8/19/2002 | 8/19/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/19/2002 at 09:09:36. Contact: ###-####.partial on roof needs south parpet completed. 8/19/2002 4:09:53 PM
|
BLD-Framing/Rough-in | 8/14/2002 | 8/15/2002 | 8/15/2002 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/14/2002 at 11:05:22. Contact: ###-####.verbal c/n with contractor on site will recall. 8/15/2002 4:37:54 PM
|
BLD-Concrete | 7/24/2002 | 7/25/2002 | 7/25/2002 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/24/2002 at 16:22:56. Contact: ###-####.
|
BLD-Footing | 7/16/2002 | 7/17/2002 | 7/17/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/16/2002 at 13:34:02. Contact: ###-####.ok first pour of 2, new detail from engineer. 7/17/2002 11:13:27 AM
|
BLD-Footing | 7/12/2002 | 7/15/2002 | 7/15/2002 | P | FAIL |
Russ Owen
|
|
|
JACK- ###-#### FTContractor on site footing and general, I told them to contact the engineer as footing cold joint would not be as per plan. Need a new detail. They said they would call me back to confirm. Do not pour at this time. 7/15/2002 5:39:56 PM
|
(F) Reprint permit | | | 6/26/2002 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/25/2002 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 4/30/2002 | | 6/14/2002 | | PASS |
Mike Otto
|
|
|
6/14/2002 08:41:57 MLO - activity updated through activity BLDA022 from case BLD02-01028.
|
Routing Off Site - STRUCTURAL | 6/12/2002 | | 6/14/2002 | | PASS |
|
|
|
Contacted PDQ to take resubmitted plans and structural calcs. of 6/11/02 to outside engineering. KMM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/14/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/14/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/14/2002 | | DONE |
|
|
|
|
Telephone call | | | 6/14/2002 | | DONE |
|
|
|
SPOKE WITH LINDA BERGSTRAND PERMIT READY AND FEES DUE, REQUIRES ACHD
|
Routing - PLAN CHECK | 6/11/2002 | | 6/11/2002 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/10/2002 | | DONE |
|
|
|
Received (1) separate set of resubmittal sheets S-1, S-2, S-3, S-4, S-5, (2) sets of structural calculations, (2) sets of resubmittal sheets CS-1, C.1, C.2, C.3, SD-1, L-1, L-2, A-1, A-2, A-3, A-4, A-5, A-7, A-8, A-10, A-11, A-12, A-15, A-16, S-1, S-2, S-3, S-4, S-5, M-1, M-2, M-5, M-6, P-2, P-4, E-2, EQ-1, EQ-4, with cover letter. Routed to Mike Otto.
|
Routing - FIRE | 5/24/2003 | 5/29/2002 | 5/31/2002 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 5/31/2002 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/1/2002 | | 5/24/2002 | | FAIL |
|
|
|
contacted pdq to take plans to outside eng. kmm
|
Plan resubmittals requested | | | 5/24/2002 | | DONE |
|
|
|
UBC and structural review comments
|
Routing - PLAN CHECK | 5/17/2002 | | 5/24/2002 | | FAIL |
|
|
|
corrections mailed and faxed to architect
|
Routing - PLUMBING | 5/8/2002 | | 5/17/2002 | | PASS |
|
|
|
no indirect waste receptors will be allowed with in a cabinet, cross connection protection may be required on the supply to beverags mechs at the service counter, additional cross connection protection may be required.
|
Routing - PLANNING | 5/7/2002 | | 5/8/2002 | | PASS |
|
|
|
Approved per DRH01-155.
|
Routing - PUBLIC WORKS | 5/1/2002 | | 5/6/2002 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 5/1/2002 | | 5/1/2002 | | PASS |
|
|
|
ROS #2901
|
Plans ACCEPTED BY PLAN TECH | | | 5/1/2002 | | DONE |
|
|
|
|
First Notice | 4/30/2002 | 4/30/2002 | 4/30/2002 | | DONE |
|
|
|
has owner supplied equipment --big sinks(6), icemaker--called and left mesg for edd
|
Plan routing begun/NEW & ADDTN | | | 4/30/2002 | | DONE |
|
|
|
|
Application received | | | 4/30/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/30/2002 | | DONE |
|
|
|
|