Permit Information
Permit NumberBLD02-01036
StatusFinaled
Name JAYO CONSTRUCTION
Site Address 13287 W HEATHERBROOK DR
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a three bedroom, two bathroom 2060 sq. ft. two story single family dwelling (1751 sq. ft. first floor/309 sq. ft. second floor) with a attached 744 sq. ft. three car garage and a 93 sq. ft. covered front porch. Per approved plans, engineering and requirement list. PC#245 (SAM)
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/1/200210/2/200210/2/2002PPASS
DetailsJim Sly
shane =-gar code 5296; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie C/C issued. 10/2/2002 2:11:34 PM
DOC - Permit Finaled10/2/200210/2/200210/2/2002PPASS
DetailsJim Sly
Finaled by inspector at 10/2/2002 2:11:53 PM
BLD-Framing/Rough-in8/12/20028/12/20028/12/2002PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 08/12/2002 at 10:49:08. Contact: ###-####.
BLD-Framing/Rough-in8/7/20028/8/20028/8/2002APASS
DetailsJim Sly
###-####
BLD-Framing/Rough-in8/8/20028/8/20028/8/2002PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 08/08/2002 at 10:04:00. Contact: ###-####.
BLD-Framing/Rough-in8/6/20028/7/20028/7/2002AFAIL
DetailsJim Sly
Scheduled by a contractor via Hello! on 08/06/2002 at 16:43:24. Contact: ###-####.
BLD-Framing/Rough-in8/5/20028/6/20028/6/2002PFAIL
DetailsJim Sly
Scheduled by a contractor via Hello! on 08/05/2002 at 15:05:18. Contact: ###-####. corr not completed. 8/6/2002 12:08:49 PM
BLD-Framing/Rough-in8/2/20028/5/20028/5/2002AFAIL
DetailsJim Sly
###-#### shane C/N..... 8/5/2002 12:03:29 PM
BLD-Framing/Rough-in7/16/20027/17/20027/17/2002APART
DetailsJim Sly
SHANE; Phone #: ###-#### Shear OK. 7/18/2002 2:28:48 AM
BLD-Framing/Rough-in7/11/20027/12/20027/12/2002ANR
DetailsRuss Owen
shear nail- shane ###-####
BLD-Foundation6/17/20026/18/20026/18/2002APASS
DetailsJim Sly
###-####
BLD-Footing6/14/20026/17/20026/17/2002APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 06/14/2002 at 11:55:35. Contact: ###-####.
Issue PAID IN FULL permit  6/11/2002 DONE
Telephone call  6/6/2002 DONE
left mess that permit is ready
Pending Assignment by DJO5/1/2002 5/16/2002 DONE
DetailsDan Overy
5/16/2002 10:28:48 SAM - activity updated through activity BLDA183 from case BLD02-01036.
Routing - PLAN CHECK5/7/2002 5/16/2002 DONE
Plan assigned to (SAM)5/16/2002 5/16/2002 PASS
DetailsSteve Munroe
5/16/2002 16:05:51 SAM - activity updated through activity BLDA022 from case BLD02-01036.
Print Pending Permit.LaserJet4  5/16/2002  
Plan Review Report  5/16/2002  
PLANS/APPL TAKEN TO FRONT DESK  5/16/2002 DONE
Inspection Record Card- Bld  5/16/2002 DONE
Telephone call  5/16/2002 DONE
Routing - PUBLIC WORKS5/3/2002 5/6/2002 PASS
Application received  5/1/2002  
Routing - PLANNING5/3/20025/3/2002  PASS
Routing - PLANNING5/1/2002   FAIL
Spoke with Office/ left Msg. for Shane/Legal not actual lot/site plan flip