Fee Review-notes | 5/2/2002 | 5/2/2002 | 8/10/2004 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/7/2004 | | DONE |
|
|
|
Perm. Occ. Cert. #9918 issued 1-7-04 to Aspen Springs Apartments.
|
BLD-Final | 1/6/2004 | 1/6/2004 | 1/6/2004 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/6/2004 at 9:39:45 AM. Contact: ###-####. OK for Perm Occ. :) 1/6/2004 2:10:13 PM
|
BLD-Final | 12/30/2003 | 12/30/2003 | 12/30/2003 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/30/2003 at 10:56:44 AM. Contact: ###-####.
|
BLD-Final | 12/22/2003 | 12/22/2003 | 12/22/2003 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/22/2003 at 9:51:23 AM. Contact: ###-####.
|
BLD-Final | 12/12/2003 | 12/15/2003 | 12/15/2003 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/12/2003 at 3:58:26 PM. Contact: ###-####.
|
Code Occupancy Approval | | | 12/15/2003 | | PASS |
|
|
|
FINAL SIGNED OFF
|
FIRE-Final Inspection | 12/8/2003 | 12/8/2003 | 12/8/2003 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/8/2003 at 10:34:10 AM. Contact: ###-####.
|
BLD-Energy code compliance | 9/19/2003 | 9/19/2003 | 9/19/2003 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/19/2003 at 11:27:19 AM. Contact: ###-####. 9/19/2003 1:04:20 PM
|
BLD-Energy code compliance | 9/18/2003 | 9/18/2003 | 9/18/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/18/2003 at 8:37:38 AM. Contact: ###-####. 9/18/2003 3:43:44 PM Check 3rd flr for firestop. 9/18/2003 3:44:30 PM
|
BLD-Framing/Rough-in | 9/15/2003 | 9/15/2003 | 9/15/2003 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/15/2003 at 9:12:14 AM. Contact: ###-####. Firestopping 9/15/2003 4:31:01 PM
|
BLD-Framing/Rough-in | 8/19/2003 | 8/20/2003 | 8/20/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/19/2003 at 6:48:37 PM. Contact: ###-####. ok to side. 8/26/2003 10:00:22 AM
|
BLD-Framing/Rough-in | 8/13/2003 | 8/13/2003 | 8/13/2003 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/13/2003 at 7:45:56 AM. Contact: ###-####.shear . 8/15/2003 1:04:49 PM
|
BLD-Framing/Rough-in | 8/12/2003 | 8/12/2003 | 8/12/2003 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/12/2003 at 7:56:25 AM. Contact: ###-####.out of time. 8/12/2003 5:41:17 PM
|
BLD-Framing/Rough-in | 6/17/2003 | 6/18/2003 | 6/18/2003 | A | PART |
Russ Owen
|
|
|
VINCENT--NAILING INSP; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Went out to verify that drywall will be located behind eectrical panels. 6/18/2003 12:13:07 PM
|
Inspection Record Card- Bld | | | 4/16/2003 | | |
|
|
|
|
Print Occupancy Form | | | 4/16/2003 | | |
|
|
|
|
Case Summary (BLD) | | | 3/31/2003 | | |
|
|
|
|
BLD-Foundation | 3/21/2003 | 3/24/2003 | 3/24/2003 | P | PASS |
Russ Owen
|
|
|
###-####
|
BLD-Footing | 3/17/2003 | 3/18/2003 | 3/18/2003 | A | PART |
Russ Owen
|
|
|
VINCENT; Phone #: ###-#### Internet Inspection Request from: Darla Downs. subject to compaction report, contractor said will be done. 3/18/2003 12:22:18 PM
|
BLD-Aging Inspection | 3/13/2003 | 3/13/2003 | 3/13/2003 | | CANC |
Russ Owen
|
|
|
|
Issue PAID IN FULL permit | | | 12/10/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/22/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/22/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/14/2002 | | 11/15/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/2002 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/15/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/15/2002 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 5/6/2002 | | 11/15/2002 | | PASS |
Mike Phillips
|
|
|
11/15/2002 11:05:58 M_P - activity updated through activity BLDA022 from case BLD02-01062.
|
Routing - PLAN CHECK | 11/12/2002 | | 11/14/2002 | | |
|
|
|
|
Routing - FIRE | 11/14/2002 | | 11/14/2002 | | PASS |
Bill Alexander
|
|
|
|
Routing - FIRE | 11/6/2002 | | 11/8/2002 | | FAIL |
Bill Alexander
|
|
|
Hydrant locations have problems with obstructions (carports, parking) and need updated due to FD access modifications. Water supply is questionable due to the location of certificate. Fire loop is found to be 4" and minimum allowed is 6".
|
Routing - PLAN CHECK | 10/23/2002 | | 11/6/2002 | | |
|
|
|
Routing to fire.
|
Plan resubmittals received | | | 10/31/2002 | | DONE |
|
|
|
Received three sets of resubmittal sheets CS1, A02, A03, A04, A05, A06, A08, A10, A33, with cover letter. Routed to Mike Phillips.
|
Plan resubmittals received | | | 10/25/2002 | | DONE |
|
|
|
Received two copies of revised sheets C2.0, C2.1, C2.2, C3.1 and C3.2. Routed to Mike P. kmm
|
Routing - FIRE | 10/17/2002 | | 10/22/2002 | | FAIL |
Bill Alexander
|
|
|
Lack response to items #2, #3 and #5 review dated 06/6/2002 and now 10/22/2002.
|
Routing - PLAN CHECK | 10/3/2002 | | 10/17/2002 | | PEND |
|
|
|
10/17/02 * Waiting for others to approve prior to issuing permit.
|
Routing - PUBLIC WORKS | 10/4/2002 | | 10/15/2002 | | PASS |
|
|
|
Approved as change with fire department requirements.
|
Routing - PLANNING | 9/27/2002 | | 10/3/2002 | | PASS |
|
|
|
Approved per DRH02-5 and as noted on plans.
|
Routing - PLANNING Land Div | 9/25/2002 | | 9/27/2002 | | PASS |
|
|
|
Approved. ROS 2842. Parcel is 13.1 acres in size. Parcels over 5 acres are exempt from subdivision requirements.
|
Plan resubmittals received | | | 9/24/2002 | | DONE |
|
|
|
Received three copies of revised struct. calcs., sheets A03, A04, A05, A06, A08, A10, A12, A20, A21, A22, A23, A24, A25, A26, A27, P-1, M02, E02, L01. and five copies of revised sheets C-1.0, C-2.0, C-2.1, C-2.2, C-3.0, C-3.1, C-3.2, C-4.0, C-4.1, C-4.2, C-4.3, C-5.0, C-5.1, C-5.2, C-6.0. Had client put into plans. kmm
|
Routing Off Site - STRUCTURAL | 7/23/2002 | | 7/30/2002 | | PASS |
|
|
|
contacted pdq to take revised plans of 7.23.02 to outside eng.
|
Plan resubmittals received | | | 7/25/2002 | | DONE |
|
|
|
Received comment letter by fax. Routed to Mike Phillips.
|
Routing - PLAN CHECK | 7/8/2002 | | 7/25/2002 | | |
|
|
|
|
Plan resubmittals received | | | 7/23/2002 | | DONE |
|
|
|
Received three copies of revised sheets A15, A16, A17, A18, A19, A20, A21, A22, A23, A24, A25, A26, A27, A28, A29, A30, A32, A34, M01, M02, M03, response letter and revised tructural calculations. Routed two copies to Mike P, and one copy to outside eng. kmm
|
Routing Off Site - STRUCTURAL | 6/27/2002 | | 7/11/2002 | | FAIL |
|
|
|
Contacted pdq to take revised plans of 6/27/02 to outside eng. kmm
Second review failed faxed comments to architect.
|
Plan resubmittals received | | | 7/8/2002 | | DONE |
|
|
|
Received two copies of resubmittal Sheet No. 1. Routed to Mike Phillips.
|
Routing - PLUMBING | 7/8/2002 | | 7/8/2002 | | PASS |
|
|
|
VENT ALL FIXTURES, COLD WATER BRANCH SERVING 2 BATH UNITS MUST BE 1".
|
Routing - PLAN CHECK | 6/26/2002 | | 7/8/2002 | | FAIL |
|
|
|
7/1/02 * Second review failed. Sent comments to architect requesting additional information for further review.
|
Plan resubmittals received | | | 6/27/2002 | | DONE |
|
|
|
Received three copies of structural calcs, sheets SO1, CS1, A01, A02, A03, A04, A05, A06, A08, A09, A10, A11, A15, A14, A17, A18, A21, A22, A25, A26, A31, A32, A33, A34, A35, A36, M01, M02, M03. Routed two copies to Mike P and one copy to outside eng. kmm
|
Routing - PUBLIC WORKS | 6/20/2002 | 6/18/2002 | 6/26/2002 | | PASS |
|
|
|
Send to PW
|
Routing - PLAN CHECK | 6/17/2002 | | 6/20/2002 | | |
|
|
|
|
Routing - PUBLIC WORKS | 6/10/2002 | | 6/17/2002 | | FAIL |
|
|
|
Requires drainage plan revisions. Per Brian Murphy
|
Routing - PLAN CHECK | 6/6/2002 | | 6/10/2002 | | |
|
|
|
|
Routing - FIRE | 6/3/2002 | 6/6/2002 | 6/6/2002 | | FAIL |
Bill Alexander
|
|
|
Reference attached and faxed notes 06/06/2002.
|
Plan Review Completed(1st rev) | | | 6/6/2002 | | DONE |
|
|
|
|
Routing - PLUMBING | 6/3/2002 | | 6/3/2002 | | FAIL |
|
|
|
see bld02-01060
|
Routing - PLAN CHECK | 6/3/2002 | | 6/3/2002 | | |
|
|
|
Routig to fire.
|
Plan resubmittals received | | | 5/31/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets C-1.0, C-2.0, C-2.1, C-2.2, C-3.0, C-3.1, C-3.2, C-4.0, C-4.1, C-4.2, C-4.3, C-5.0, C-5.1, C-5.2, C-6.0. Routed to Mike Phillips.
|
Routing - PLANNING | 5/24/2002 | | 5/31/2002 | | FAIL |
|
|
|
Approved as per CUP01-00164 (Dave Abo).
Plans do not comply with Design Review, DRH02-00005; please note conditions 1d, 1e and 2 (Martin Santoyo).
|
Routing - PLAN CHECK | 5/20/2002 | | 5/24/2002 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional information for further review prior to issuing permit.
|
Routing - PUBLIC WORKS | 5/10/2002 | | 5/20/2002 | | FAIL |
|
|
|
Requires revisions per Brian M. kmm
|
Routing Off Site - STRUCTURAL | 5/9/2002 | | 5/15/2002 | | FAIL |
|
|
|
contacted pdq to take plans to outside eng. kmm
Additional review required by outside engineering firm .
|
Routing - PLANNING Land Div | 5/9/2002 | | 5/10/2002 | | FAIL |
|
|
|
requested deed/legal decription
|
Plan routing begun/NEW & ADDTN | | | 5/9/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/9/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/6/2002 | | PEND |
|
|
|
Requires stamped and signed structural sheets. Contacted Scott McDonald of this need. kmm
|
Application received | | | 5/2/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/2/2002 | | DONE |
|
|
|
|
Permanent Occupancy | | 1/6/2002 | 1/6/2002 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 8/15/2003 | 8/15/2003 | | P | |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/15/2003 at 9:55:35 AM. Contact: ###-####.
|