Fee Review-notes | 5/2/2002 | 5/2/2002 | 8/10/2004 | | DONE |
|
|
|
|
BLD-Final | 12/8/2003 | 12/8/2003 | 12/8/2003 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/8/2003 at 10:36:06 AM. Contact: ###-####. OK for Perm Occ. :) 12/8/2003 4:18:13 PM
|
First Notice | | 12/8/2003 | 12/8/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 12/8/2003 | 12/8/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 12/8/2003 | | DONE |
|
|
|
Perm. Occ. Cert. # 9896 issued 12-8-03 to the Aspen Springs Apts.
|
FIRE-Final Inspection | 11/26/2003 | 11/26/2003 | 11/26/2003 | | |
Troy Cobbley
|
|
|
Final - approved by Troy Cobbley
|
FIRE-Final Inspection | 11/24/2003 | 11/24/2003 | 11/24/2003 | P | PART |
Troy Cobbley
|
|
|
A temp occupancy was given until adequate batteries are provided for the Nac panel. All other life safety items are ok
|
Code Occupancy Approval | | | 11/20/2003 | | PASS |
|
|
|
|
BLD-Wall cover | 8/28/2003 | 8/29/2003 | 8/29/2003 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/28/2003 at 4:36:08 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/25/2003 | 8/26/2003 | 8/26/2003 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 8/25/2003 at 11:54:00 AM. Contact: ###-####. C/N ok to insulate. 8/26/2003 10:38:08 AM
|
BLD-Wall cover | 8/19/2003 | 8/20/2003 | 8/20/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/19/2003 at 6:46:03 PM. Contact: ###-####.ok to side. 8/26/2003 9:57:59 AM
|
BLD-Framing/Rough-in | 7/29/2003 | 7/30/2003 | 7/30/2003 | P | PART |
Russ Owen
|
|
|
###-#### Ok some areas painted in green. 7/30/2003 4:57:03 PM
|
Override - Parcel Holds | | | 7/29/2003 | | |
|
|
|
|
BLD-Framing/Rough-in | 7/25/2003 | 7/28/2003 | 7/28/2003 | A | CANC |
Russ Owen
|
|
|
###-#### vincent
|
Override - Parcel Holds | | | 7/25/2003 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/16/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/16/2003 | | |
|
|
|
|
Case Summary (BLD) | | | 3/31/2003 | | |
|
|
|
|
BLD-Aging Inspection | 3/14/2003 | 3/14/2003 | 3/14/2003 | | CANC |
Russ Owen
|
|
|
still work 3/17/2003 9:38:32 AM
|
Issue PAID IN FULL permit | | | 12/10/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/22/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/22/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/14/2002 | | 11/15/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/2002 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/15/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/15/2002 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 5/6/2002 | | 11/15/2002 | | PASS |
Mike Phillips
|
|
|
11/15/2002 11:21:52 M_P - activity updated through activity BLDA022 from case BLD02-01063.
|
Routing - PLAN CHECK | 11/12/2002 | | 11/14/2002 | | |
|
|
|
|
Routing - FIRE | 11/14/2002 | | 11/14/2002 | | PASS |
Bill Alexander
|
|
|
|
Routing - FIRE | 11/6/2002 | | 11/8/2002 | | FAIL |
Bill Alexander
|
|
|
Hydrant locations have problems with obstructions (carports, parking) and need updated due to FD access modifications. Water supply is questionable due to the location of certificate. Fire loop is found to be 4" and minimum allowed is 6".
|
Routing - PLAN CHECK | 10/23/2002 | | 11/6/2002 | | |
|
|
|
Routing to fire.
|
Plan resubmittals received | | | 10/31/2002 | | DONE |
|
|
|
Received three sets of resubmittal sheets CS1, A02, A03, A04, A05, A06, A08, A10, A33, with cover letter. Routed to Mike Phillips.
|
Plan resubmittals received | | | 10/25/2002 | | DONE |
|
|
|
Received two copies of revised sheets C2.0, C2.1, C2.2, C3.1 and C3.2. Routed to Mike P. kmm
|
Routing - FIRE | 10/17/2002 | | 10/22/2002 | | FAIL |
Bill Alexander
|
|
|
Lack response to items #2, #3 and #5 review dated 06/6/2002 and now 10/22/2002.
|
Routing - PLAN CHECK | 10/3/2002 | | 10/17/2002 | | PEND |
|
|
|
10/17/02 * Waiting for others to approve prior to issuing permit.
|
Routing - PUBLIC WORKS | 10/4/2002 | | 10/15/2002 | | PASS |
|
|
|
Approved as change with fire department requirements.
|
Routing - PLANNING Land Div | 9/25/2002 | | 9/27/2002 | | PASS |
|
|
|
Approved. ROS 2842. Parcel is 13.1 acres in size. Parcels over 5 acres are exempt from subdivision requirements.
|
Plan resubmittals received | | | 9/24/2002 | | DONE |
|
|
|
Received three copies of revised struct. calcs., sheets A03, A04, A05, A06, A08, A10, A12, A20, A21, A22, A23, A24, A25, A26, A27, P-1, M02, E02, L01. and five copies of revised sheets C-1.0, C-2.0, C-2.1, C-2.2, C-3.0, C-3.1, C-3.2, C-4.0, C-4.1, C-4.2, C-4.3, C-5.0, C-5.1, C-5.2, C-6.0. Had client put into plans. kmm
|
Routing - PLANNING | 9/27/2002 | | 9/3/2002 | | PASS |
|
|
|
Approved per DRH02-5 and as noted on plans.
|
Routing Off Site - STRUCTURAL | 7/23/2002 | | 7/30/2002 | | PASS |
|
|
|
contacted pdq to take revised plans of 7.23.02 to outside eng. kmm
|
Plan resubmittals received | | | 7/25/2002 | | DONE |
|
|
|
Received comment letter by fax. Routed to Mike Phillips.
|
Routing - PLAN CHECK | 7/8/2002 | | 7/25/2002 | | |
|
|
|
|
Plan resubmittals received | | | 7/23/2002 | | DONE |
|
|
|
Received three copies of revised sheets A15, A16, A17, A18, A19, A20, A21, A22, A23, A24, A25, A26, A27, A28, A29, A30, A32, A34, M01, M02, M03, response letter and revised tructural calculations. Routed two copies to Mike P, and one copy to outside eng. kmm
|
Routing Off Site - STRUCTURAL | 6/27/2002 | | 7/11/2002 | | FAIL |
|
|
|
Contacted pdq to take revised plans of 6/27/02 to outside eng. kmm
Second review failed faxed comments to architect.
|
Plan resubmittals received | | | 7/8/2002 | | DONE |
|
|
|
Received two copies of resubmittal Sheet No. 1. Routed to Mike Phillips.
|
Routing - PLUMBING | 7/8/2002 | | 7/8/2002 | | PASS |
|
|
|
VENT ALL FIXTURES, COLD WATER BRANCH SERVING 2 BATH UNITS MUST BE 1".
|
Routing - PLAN CHECK | 6/26/2002 | | 7/8/2002 | | FAIL |
|
|
|
7/1/02 * Second review failed. Sent comments to architect requesting additional information for further review.
|
Plan resubmittals received | | | 6/27/2002 | | DONE |
|
|
|
Received three copies of structural calcs, sheets SO1, CS1, A01, A02, A03, A04, A05, A06, A08, A09, A10, A11, A15, A14, A17, A18, A21, A22, A25, A26, A31, A32, A33, A34, A35, A36, M01, M02, M03. Routed two copies to Mike P and one copy to outside eng. kmm
|
Routing - PUBLIC WORKS | 6/20/2002 | 6/18/2002 | 6/26/2002 | | PASS |
|
|
|
Send to PW
|
Routing - PLAN CHECK | 6/17/2002 | | 6/20/2002 | | |
|
|
|
|
Routing - PUBLIC WORKS | 6/10/2002 | | 6/17/2002 | | FAIL |
|
|
|
Requires drainage plan revisions. Per Brian Murphy
|
Routing - PLAN CHECK | 6/6/2002 | | 6/10/2002 | | |
|
|
|
|
Routing - FIRE | 6/3/2002 | 6/6/2002 | 6/6/2002 | | FAIL |
Bill Alexander
|
|
|
Reference attached and faxed notes 06/06/2002.
|
Plan Review Completed(1st rev) | | | 6/6/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/3/2002 | | 6/3/2002 | | |
|
|
|
Routing to fire.
|
Routing - PLUMBING | 6/3/2002 | | 6/3/2002 | | FAIL |
|
|
|
see bld02-01060
|
Plan resubmittals received | | | 5/31/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets C-1.0, C-2.0, C-2.1, C-2.2, C-3.0, C-3.1, C-3.2, C-4.0, C-4.1, C-4.2, C-4.3, C-5.0, C-5.1, C-5.2, C-6.0. Routed to Mike Phillips.
|
Routing - PLANNING | 5/24/2002 | | 5/31/2002 | | FAIL |
|
|
|
Approved as per CUP01-00164 (Dave Abo).
Plans do not comply with Design Review, DRH02-00005; please note conditions 1d, 1e and 2 (Martin Santoyo).
|
Routing - PLAN CHECK | 5/20/2002 | | 5/24/2002 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional information to be submitted for further review prior to issuing permit.
|
Routing - PUBLIC WORKS | 5/10/2002 | | 5/20/2002 | | FAIL |
|
|
|
Requires revisions per Brian M. kmm
|
Routing Off Site - STRUCTURAL | 5/9/2002 | | 5/15/2002 | | FAIL |
|
|
|
contacted pdq to take plans to outside eng. kmm
Additional review required by outside engineering firm .
|
Routing - PLANNING Land Div | 5/9/2002 | | 5/10/2002 | | FAIL |
|
|
|
requested deed/legal decription
|
Plan routing begun/NEW & ADDTN | | | 5/9/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/9/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/6/2002 | | PEND |
|
|
|
Requires stamped and signed structural sheets. Contacted Scott McDonald of this need. kmm
|
Application received | | | 5/2/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/2/2002 | | DONE |
|
|
|
|