Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD02-01067
StatusFinaled
Name PENTALON CONSTRUCTION, INC.
Site Address 8533 W FAIRVIEW
Project NameASPEN SPRINGS APARTMENTS
Customer Number 
ePlanReviewNo
Description
Building 6 Type E * PLAN MODIFICATION (Section 1 of 2) To construct a two hour area separation wall to divide this eight unit apartment building into two. This section is 5,984 sq.ft. and contains four, two story, townhome style (up down unit). All construction per the approved plans and attached comment list. Work to include on site landscaping and parking lot. Refer to BLD 03-01677 for other side of area separation wall. MJP DRH02-00005 CUP01-00164 PC#280-02
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes5/2/20025/2/20028/10/2004 DONE
First Notice 12/11/200312/11/2003 DONE
Permanent occupancy  12/11/2003 DONE
Perm. Occ. Cert. # 9901 issued 12-11-03 to the Aspen Springs Apts.
Permanent Occupancy 12/10/200312/10/2003 DONE
Details
BLD-Final12/10/200312/10/200312/10/2003PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 12/10/2003 at 9:44:48 AM. Contact: ###-####. OK for Perm Occ. :) 12/10/2003 4:55:00 PM 12/10/2003 4:55:18 PM
FIRE-Final Inspection12/8/200312/8/200312/8/2003PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/8/2003 at 10:31:48 AM. Contact: ###-####.
Code Occupancy Approval  11/20/2003 PASS
BLD-Wall cover8/28/20039/2/20039/2/2003PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 8/28/2003 at 8:22:48 AM. Contact: ###-####.
BLD-Framing/Rough-in8/25/20038/26/20038/26/2003APART
DetailsSteven Webb
Scheduled by a contractor via Hello! on 8/25/2003 at 5:38:39 PM. Contact: ###-####.
BLD-Framing/Rough-in8/11/20038/11/20038/11/2003PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 8/11/2003 at 10:02:29 AM. Contact: ###-####.ok to side 8/12/2003 10:32:32 AM
BLD-Framing/Rough-in8/7/20038/8/20038/8/2003APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 8/7/2003 at 3:52:21 PM. Contact: ###-####.Scheduled by a contractor via Hello! on 8/7/2003 at 3:58:29 PM. Contact: ###-####.Scheduled by a contractor via Hello! on 8/7/2003 at 3:55:31 PM. Contact: ###-####. 8/12/2003 10:21:53 AM needs addnl work shear. 8/12/2003 10:26:07 AM
BLD-Framing/Rough-in8/6/20038/7/20038/7/2003PPART
DetailsRuss Owen
###-#### vincent shear needs addnl work. 8/12/2003 10:14:20 AM
Routing - PLAN CHECK7/17/2003 7/18/2003 PASS
PLAN MODIFICATION
PLANS/APPL TAKEN TO FRONT DESK  7/18/2003 DONE
Override - Parcel Holds  7/18/2003  
Print Pending Permit.LaserJet4  7/18/2003 DONE
Case Summary (BLD)  7/18/2003 DONE
Received Certificate of Value  7/16/2003 DONE
PLAN MODIFICATION * Received revised certificate of value, with area separation wall.
Routing - FIRE7/11/2003 7/15/2003 PASS
PLAN MODIFICATION * No revised comments.
Override - Parcel Holds  7/11/2003  
Print permit w/o conditions  7/11/2003  
Routing - PLAN CHECK6/26/2003 7/11/2003 FAIL
PLAN MODIFICATION received and forwarded to Mike P.
Called Vencent Morgan and requested revised certificate of value.
Routing - PLAN CHECK6/23/2003 7/11/2003 FAIL
PLAN MODIFICATION received and forwarded to Mike P.
Called Vencent Morgan and requested revised certificate of value.
Plan resubmittals received  6/26/2003 DONE
PLAN MODFICATION received and routed to Mike P. and Fire.
Inspection Record Card- Bld  4/16/2003  
Print Occupancy Form  4/16/2003  
Case Summary (BLD)  3/31/2003  
BLD-Foundation2/25/20032/26/20032/26/2003PPASS
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
BLD-Footing2/20/20032/21/20032/21/2003APASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 2/20/2003 at 1:20:32 PM. Contact: ###-####.
Issue PAID IN FULL permit  12/10/2002 DONE
Telephone call  11/27/2002 DONE
called all permits ready and fees due
Inspection Record Card- Bld  11/22/2002 DONE
Print Occupancy Form  11/22/2002 DONE
Routing - PLAN CHECK11/14/2002 11/15/2002 PASS
PLANS/APPL TAKEN TO FRONT DESK  11/15/2002 DONE
Print Pending Permit.LaserJet4  11/15/2002 DONE
Case Summary (BLD)  11/15/2002 DONE
Plan assigned to (M_P)5/6/2002 11/15/2002 PASS
DetailsMike Phillips
11/15/2002 13:08:37 M_P - activity updated through activity BLDA022 from case BLD02-01067.
Routing - FIRE11/14/2002 11/14/2002 PASS
DetailsBill Alexander
Routing - FIRE11/6/2002 11/8/2002 FAIL
DetailsBill Alexander
Hydrant locations have problems with obstructions (carports, parking) and need updated due to FD access modifications. Water supply is questionable due to the location of certificate. Fire loop is found to be 4" and minimum allowed is 6".
Routing - PLAN CHECK10/23/2002 11/6/2002 PEND
Routing to fire.
Plan resubmittals received  10/31/2002 DONE
Received three sets of resubmittal sheets CS1, A02, A03, A04, A05, A06, A08, A10, A33, with cover letter. Routed to Mike Phillips.
Plan resubmittals received  10/25/2002 DONE
Received two copies of revised sheets C2.0, C2.1, C2.2, C3.1 and C3.2. Routed to Mike P. kmm
Routing - FIRE10/17/2002 10/22/2002 FAIL
DetailsBill Alexander
Lack response to items #2 review dated 06/6/2002 and now 10/22/2002. Turn radius (access) problems with building #6 and #7.
Routing - PLAN CHECK10/3/2002 10/17/2002 PEND
10/17/02 * Waiting for others to approve prior to issuing permit.
Routing - PUBLIC WORKS10/4/2002 10/15/2002 PASS
Approved as change with fire department requirements.
Routing - PLANNING9/27/2002 10/3/2002 PASS
Approved per DRH02-5 and as noted on plans.
Routing - PLANNING Land Div9/25/2002 9/27/2002 PASS
Approved. ROS 2842. Parcel is 13.1 acres in size. Parcels over 5 acres are exempt from subdivision requirements.
Plan resubmittals received  9/24/2002 DONE
Received three copies of revised struct. calcs., sheets A03, A04, A05, A06, A08, A10, A12, A20, A21, A22, A23, A24, A25, A26, A27, P-1, M02, E02, L01. and five copies of revised sheets C-1.0, C-2.0, C-2.1, C-2.2, C-3.0, C-3.1, C-3.2, C-4.0, C-4.1, C-4.2, C-4.3, C-5.0, C-5.1, C-5.2, C-6.0. Had client put into plans. kmm
Routing Off Site - STRUCTURAL7/23/2002 7/30/2002 PASS
contacted pdq to take revised plans of 7.23.02 to outside eng. kmm
Plan resubmittals received  7/25/2002 DONE
Received comment letter by fax. Routed to Mike Phillips.
Routing - PLAN CHECK7/8/2002 7/25/2002  
Plan resubmittals received  7/23/2002 DONE
Received three copies of revised sheets A15, A16, A17, A18, A19, A20, A21, A22, A23, A24, A25, A26, A27, A28, A29, A30, A32, A34, M01, M02, M03, response letter and revised tructural calculations. Routed two copies to Mike P, and one copy to outside eng. kmm
Routing Off Site - STRUCTURAL6/27/2002 7/11/2002 FAIL
contacted pdq to take revised plans of 6/27/02 to outside eng. kmm
Second review failed faxed comments to architect.
Plan resubmittals received  7/8/2002 DONE
Received two copies of resubmittal Sheet No. 1. Routed to Mike Phillips.
Routing - PLUMBING7/8/2002 7/8/2002 PASS
VENT ALL FIXTURES, COLD WATER BRANCH SERVING 2 BATH UNITS MUST BE 1".
Routing - PLAN CHECK6/26/2002 7/8/2002 FAIL
7/1/02 * Second review failed. Sent comments to architect requesting additional information for further review.
Plan resubmittals received  6/27/2002 DONE
Received three copies of structural calcs, sheets SO1, CS1, A01, A02, A03, A04, A05, A06, A08, A09, A10, A11, A15, A14, A17, A18, A21, A22, A25, A26, A31, A32, A33, A34, A35, A36, M01, M02, M03. Routed two copies to Mike P and one copy to outside eng. kmm
Routing - PUBLIC WORKS6/20/2002 6/26/2002 PASS
Routing - PLAN CHECK6/17/2002 6/20/2002  
Routing - PUBLIC WORKS6/10/2002 6/17/2002 FAIL
Requires drainage plan revisions. Per Brian Murphy
Routing - PLAN CHECK6/6/2002 6/10/2002  
Routing - FIRE6/3/20026/6/20026/6/2002 FAIL
DetailsBill Alexander
Reference attached and faxed notes 06/06/2002.
Routing - PLUMBING6/3/2002 6/3/2002 FAIL
see bld02-01060
Routing - PLAN CHECK6/3/2002 6/3/2002  
RRouting to fire
Routing - PLANNING5/24/2002 5/31/2002 FAIL
Approved as per CUP01-00164 (Dave Abo).
Plans do not comply with Design Review, DRH02-00005; please note conditions 1d, 1e and 2 (Martin Santoyo).
Plan resubmittals received  5/31/2002 DONE
Received two sets of resubmittal sheets C-1.0, C-2.0, C-2.1, C-2.2, C-3.0, C-3.1, C-3.2, C-4.0, C-4.1, C-4.2, C-4.3, C-5.0, C-5.1, C-5.2, C-6.0. Routed to Mike Phillips.
Routing - PLAN CHECK5/20/2002 5/24/2002 FAIL
Plan review completed, sent correction report to architect requesting additional informaiton to be submitted for further review prior to issuing permit.
Routing - PUBLIC WORKS5/10/2002 5/20/2002 FAIL
Requires revisions per Brian M. kmm
Routing Off Site - STRUCTURAL5/9/2002 5/15/2002 FAIL
contacted pdq to take plans back to outside eng
Additional review required by outside engineering firm .
Routing - PLANNING Land Div5/9/2002 5/10/2002 FAIL
requested deed
Plans ACCEPTED BY PLAN TECH  5/9/2002 DONE
Plan routing begun/NEW & ADDTN  5/9/2002 DONE
Plans ACCEPTED BY PLAN TECH  5/6/2002 PEND
Requires stamped and signed structural sheets. Contacted Scott McDonald of this need. kmm
Application received  5/2/2002  
Recd Pcfee & Taken To Pln CK  5/2/2002 DONE
Plan routing begun/NEW & ADDTN    DONE