BLD-Final | 8/30/2002 | 8/30/2002 | 8/30/2002 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 08/30/2002 at 09:37:43. Contact: ###-####. C. of C. #22459 issued. 8/30/2002 1:46:40 PM
|
BLD-Final | 8/30/2002 | 8/30/2002 | 8/30/2002 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 08/30/2002 at 09:37:43. Contact: ###-####. C. of C. #22459 issued. 8/30/2002 1:46:40 PM
|
DOC - Permit Finaled | 8/30/2002 | 8/30/2002 | 8/30/2002 | P | PASS |
Steven Webb
|
|
|
Finaled by inspector at 8/30/2002 1:46:46 PM
|
DOC - Permit Finaled | 8/30/2002 | 8/30/2002 | 8/30/2002 | P | PASS |
Steven Webb
|
|
|
Finaled by inspector at 8/30/2002 1:46:46 PM
|
BLD-Framing/Rough-in | 6/28/2002 | 6/28/2002 | 6/28/2002 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 06/28/2002 at 10:07:46. Contact: .--Corrections made Ok to cover 6/28/2002 3:44:02 PM
|
BLD-Framing/Rough-in | 6/27/2002 | 6/27/2002 | 6/27/2002 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 06/27/2002 at 07:18:04. Contact: ###-####. C/N ok to insulate 6/27/2002 12:08:22 PM
|
BLD-Wall cover | 6/13/2002 | 6/13/2002 | 6/13/2002 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 06/13/2002 at 07:05:57. Contact: ###-####. Ok to side 6/13/2002 10:56:41 AM
|
BLD-Wall cover | 6/12/2002 | 6/12/2002 | 6/12/2002 | P | NR |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 06/12/2002 at 06:30:55. Contact: ###-####. No approved plans 6/12/2002 1:55:10 PM
|
BLD-Foundation | 5/22/2002 | 5/23/2002 | 5/23/2002 | A | PART |
Steven Webb
|
|
|
JARED ###-#### wip 5/23/2002 11:27:21 AM
|
BLD-Footing | 5/22/2002 | 5/22/2002 | 5/22/2002 | P | PART |
Steven Webb
|
|
|
ft insp -###-####- jerald --wip-- Rear setback to patio post is not 15 feet. Contacted builder--informed him it's ok to pour house but either a variance request is needed to P. and Z. or shorten the patio to achieve the 15' feet rear setback. 5% ready at time of inspection. 5/22/2002 1:47:16 PM
|
Inspection Record Card- Bld | | | 5/21/2002 | | DONE |
|
|
|
|
Telephone call | | | 5/21/2002 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/21/2002 | | DONE |
|
|
|
|
Pending Assignment by DJO | 5/3/2002 | | 5/20/2002 | | DONE |
Dan Overy
|
|
|
5/20/2002 16:16:27 M_P - activity updated through activity BLDA170 from case BLD02-01081.
|
Routing - PLAN CHECK | 5/7/2002 | | 5/20/2002 | | PASS |
|
|
|
|
Plan assigned to (M_P) | 5/20/2002 | | 5/20/2002 | | DONE |
Mike Phillips
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2002 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/20/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/20/2002 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 5/6/2002 | | 5/6/2002 | | PASS |
|
|
|
|
Application received | | | 5/3/2002 | | |
|
|
|
|
Routing - PLANNING | 5/3/2002 | | | | PASS |
|
|
|
|