Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD02-01118
StatusFinaled
Name FIRST NATIONAL PAWN
Site Address 1404 W MAIN ST
Project Name 
Customer Number 
ePlanReviewNo
Description
(FIRST NATIONAL PAWN) The basement of this building is fire sprinklered. This building will be fully fire sprinklered throughout, under a separate fire sprinkler permit, to avoid the 1-hr occupancy separations at storage rooms. To remodel a 17,368 square foot one story building (11,820 square foot main floor and 5,548 square foot basement). A 5,235 square foot retail sales room is being created on the main floor. The 5,548 square foot basement will retain its storage occupancy. Work is to include interior nonbearing walls and suspended ceilings all per approved drawings and plan review conditions on file. The fire sprinkler system shall comply with NFPA 13-1999 as regulated by the Fire Department. The fire sprinkler system shall be completely installed and operational before a Certificate of Occupancy is issued to this tenant. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/21/200211/22/200211/22/2002APASS
DetailsCarl Dependahl
###-####...c/n ok. 11/22/02 5:50:51 PM
Permanent Occupancy 11/22/200211/22/2002 DONE
Details
Permanent occupancy UNPAID FEE  11/22/2002 DONE
Perm. Occ. Cert. #9452 issued 11-22-02 to First National Pawn.
BLD-Conference11/7/200211/7/200211/7/2002PPASS
DetailsCarl Dependahl
###-#### tim re handrails, keep c/n 11/8/02 10:11:18 AM
BLD-Final10/30/200210/31/200210/31/2002PFAIL
DetailsCarl Dependahl
###-#### TIM ...c/n, handrails, corridor door seals/hdwe...complete door install at store room occ. sep... ok for t/o. 10/31/02 4:20:25 PM
FIRE-Final Inspection10/31/200210/31/200210/31/2002PPASS
DetailsRick Jackson
BLD-Conference10/16/200210/16/200210/16/2002PPART
DetailsCarl Dependahl
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung; ok to add peg bd over gyp for displays 10/16/2002 1:04:39 PM
BLD-Framing/Rough-in10/2/200210/3/200210/3/2002APASS
DetailsTom Arcoraci
fr tim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Conference10/2/200210/2/200210/2/2002PPASS
DetailsCarl Dependahl
###-#### call first ....need hvac & elec. 1st for grid insp. 10/2/2002 1:37:33 PM
BLD-Framing/Rough-in7/3/20027/3/20027/3/2002PPASS
DetailsTom Arcoraci
FRED ###-####
BLD-Framing/Rough-in7/2/20027/3/20027/2/2002ACANC
DetailsCarl Dependahl
tim- ###-#### Disp set to [CANC] by a contractor via Hello! on 07/02/2002 at 17:07:25.
BLD-Framing/Rough-in7/1/20027/1/20027/1/2002PFAIL
DetailsRuss Owen
fr insp pat- ###-#### c/n posted on job card provide detail for 1 hr corridor changed from wood to steel ,also needs plm ,and ele inspections, appears fire sprinklers will be used for 1hr ceiling in basement, see notes on plans. 7/1/2002 2:24:30 PM
Inspection Record Card- Bld  6/17/2002 DONE
Print Occupancy Form  6/17/2002 DONE
Telephone call  6/17/2002 DONE
LEFT MESSAGE PERMIT READY AND FEES DUE
Issue PAID IN FULL permit  6/17/2002 DONE
Plan assigned to (CJW)5/20/2002 6/14/2002 PASS
DetailsCarl Westfall
6/14/2002 16:05:27 CJW - activity updated through activity BLDA022 from case BLD02-01118.
PLANS/APPL TAKEN TO FRONT DESK  6/14/2002 PASS
Routing - PLAN CHECK6/6/2002 6/14/2002 PASS
Drawings approved with conditions.
Plan resubmittals received  6/13/2002 DONE
Received two sets of resubmittal sheets A-2.0 with transmittal. Routed to Carl Westfall.
Routing - PLANNING5/31/2002 6/6/2002 PASS
Approved as noted. See letter dated 6/6/02 about the use and history of the building. Site plan added to illustrate parking requirements.
Plan resubmittals received  6/6/2002 DONE
Received two copies of revised sheets A-0.0, A-1.0 & A-2.0
One copy of letter of response. Routed to Carl W. kmm
Plan resubmittals received  6/6/2002 DONE
Received two copies of revised sheet A-1and one letter to Sara. Routed to Sara S. kmm
Plan Review Completed(1st rev)  5/30/2002  
Failed first UBC review.
Routing - FIRE5/28/2002 5/30/2002 PASS
approved without written comment
Routing - PLAN CHECK5/10/2002 5/28/2002  
Failed first UBC review. UBC plan review started May 24, 2002 and finished May 28, 2002. A response from the architect was required. See the conditions list.
Routing - PUBLIC WORKS5/9/2002 5/10/2002 DONE
Plan routing begun/TENANTS  5/9/2002 DONE
Plans ACCEPTED BY PLAN TECH  5/9/2002  
First Notice5/8/20025/8/20025/8/2002 DONE
Application received  5/8/2002  
Recd Pcfee & Taken To Pln CK  5/8/2002 DONE