BLD-Final | 8/27/2002 | 8/27/2002 | 8/27/2002 | P | PASS |
Jim Sly
|
|
|
C/C issued.
|
DOC - Permit Finaled | 8/27/2002 | 8/27/2002 | 8/27/2002 | P | PASS |
Jim Sly
|
|
|
Finaled by inspector at 8/27/2002 2:32:55 PM
|
BLD-Final | 8/26/2002 | 8/26/2002 | 8/26/2002 | A | NR |
Jim Sly
|
|
|
###-#### ROD (JIM: ROD WOULD LIKE TO TAKE YOU TO LUNCH AROUND 11:00AM)
|
BLD-Framing/Rough-in | 7/9/2002 | 7/10/2002 | 7/10/2002 | P | PASS |
Russ Owen
|
|
|
ROD ###-#### PLEASE CALL ROD AFTER INSPECTION SO HE KNOWS IF EVERY THING IS OK
|
BLD-Energy code compliance | 7/9/2002 | 7/10/2002 | 7/10/2002 | P | PASS |
Russ Owen
|
|
|
ROD ###-#### PLEASE CALL ROD AFTER INSPECTION SO HE KNOWS IF EVERY THING IS OK
|
BLD-Framing/Rough-in | 7/8/2002 | 7/9/2002 | 7/9/2002 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 20:25:34. Contact: ###-####.c/n on site ok to insulate 7/9/2002 9:05:10 AM
|
BLD-Energy code compliance | 7/8/2002 | 7/9/2002 | 7/9/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 07/08/2002 at 20:27:20. Contact: ###-####. seal package ok 7/9/2002 9:05:32 AM
|
BLD-Framing/Rough-in | 7/8/2002 | 7/8/2002 | 7/8/2002 | P | FAIL |
Russ Owen
|
|
|
ROD ###-#### FINAL FRAMING.c/n posted. 7/8/2002 5:23:08 PM
|
BLD-Framing/Rough-in | 6/26/2002 | 6/27/2002 | 6/27/2002 | A | PART |
Jim Sly
|
|
|
SHEER NAIL ROD ###-#### Shear OK. 6/27/2002 10:40:53 PM
|
BLD-Conference | 6/13/2002 | 6/13/2002 | 6/13/2002 | P | PASS |
Jim Sly
|
|
|
ROB ###-####
|
BLD-Foundation | 6/13/2002 | 6/13/2002 | 6/13/2002 | P | PASS |
Jim Sly
|
|
|
JED ###-####
|
Routing - PLAN CHECK | 5/30/2002 | | 6/11/2002 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 6/10/2002 | | 6/11/2002 | | PASS |
Steve Munroe
|
|
|
6/11/2002 07:31:45 SAM - activity updated through activity BLDA022 from case BLD02-01215.
|
Plan Review Report | | | 6/11/2002 | | |
|
|
|
|
Plan Reviewer's activity | | | 6/11/2002 | | PEND |
|
|
|
6/11/02 Only one set is being approved due to excessive red-lining.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/11/2002 | | DONE |
|
|
|
|
Telephone call | | | 6/11/2002 | | DONE |
|
|
|
SPOKE WITH ROD PERMIT READY AND FEES DUE
|
Issue PAID IN FULL permit | | | 6/11/2002 | | DONE |
|
|
|
|
Pending Assignment by DJO | 5/17/2002 | | 6/10/2002 | | DONE |
Dan Overy
|
|
|
6/10/2002 13:59:06 SAM - activity updated through activity BLDA183 from case BLD02-01215.
|
BLD-Footing | 6/5/2002 | 6/5/2002 | 6/5/2002 | P | PART |
Jim Sly
|
|
|
###-#### JED
|
Early Start Permit | | | 6/3/2002 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 5/29/2002 | | 5/30/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 5/17/2002 | | 5/29/2002 | | PASS |
|
|
|
|
Application received | | | 5/17/2002 | | |
|
|
|
|