Case Summary (BLD) | | | 7/2/2009 | | |
|
|
|
|
BLD - Request for Extension | 4/5/2005 | 4/6/2006 | 4/5/2006 | | CANC |
Tom Arcoraci
|
|
|
###-#### - george - Note: not quite finished with draining/air conditioning/sprinklers and landscaping????? already finaled???????
|
Second Notice BLD | 12/5/2005 | 12/5/2005 | 12/14/2005 | | DONE |
|
|
|
First Notice has not been responded to.///singed off 2004 permit per Jenifer & Rita
|
First Notice | | 11/16/2005 | 12/5/2005 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 11/16/2005 | 11/16/2005 | 11/16/2005 | | DONE |
|
|
|
Drainage project complete, signed off 11/16/05. R.Rokovitz
|
Permanent occupancy | | | 11/16/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10803 issued 11-16-05 o the Korean Baptist Church.
|
BLD-Final | 11/14/2005 | 11/15/2005 | 11/15/2005 | P | PASS |
Tom Arcoraci
|
|
|
requests 2:30//won; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok for perm when p/w signs
|
Code Occupancy Approval | | | 11/14/2005 | | |
|
|
|
ALL ITEMS IN PER PLANS APPROVED.
|
BLD-Final | 11/1/2005 | 11/2/2005 | 11/2/2005 | P | NR |
Tom Arcoraci
|
|
|
###-#### - cameron Note: parking lot
|
Temporary occupancy | | | 10/27/2005 | | PASS |
|
|
|
Extended temporary occupancy permit to January 25, 2006.
|
Telephone call | | | 10/20/2005 | | DONE |
|
|
|
Talked w/Won re: status of occ. cert. & he will write a ltr. requesting extending it.
|
BLD-Final | 7/27/2005 | 7/29/2005 | 7/29/2005 | A | PART |
Tom Arcoraci
|
|
|
###-#### - won chang Note: please call 1/2 hr prior to inspection ok for temp occ cn issued
|
Temporary occupancy | | | 7/29/2005 | | DONE |
|
|
|
Temp. Occ. Cert. # 5261 issued 7-29-05 to the Korean Baptist Church.
|
FIRE-Alarm Testing | 7/26/2005 | 7/27/2005 | 7/27/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
FIRE-Final Inspection | 7/21/2005 | 7/22/2005 | 7/22/2005 | A | FAIL |
Troy Cobbley
|
|
|
Repair the three exit signs as marked on plans, provide one additional emergency light as marked on plans. Provide duct smoke detectors as shown on sheet M1. Remote annunciators may be required if inaccessible or over 10' above finish floor.
|
Extend Permit 180 days | 6/29/2005 | 6/29/2005 | 6/29/2005 | P | PASS |
Tom Arcoraci
|
|
|
|
(F) Reprint permit | | | 6/8/2005 | | |
|
|
|
|
BLD-Conference | 4/13/2005 | 4/13/2005 | 4/13/2005 | P | PASS |
Tom Arcoraci
|
|
|
please call prior to inspection///meong; Phone #: ###-#### Internet Inspection Request from: Barbara Moore extend foor 90 more days slow progress 4/13/2005 2:57:35 PM
|
BLD-Aging Inspection | 3/14/2005 | 3/14/2005 | 3/14/2005 | | PASS |
Tom Arcoraci
|
|
|
|
Print Occupancy Form | | | 12/7/2004 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 11/23/2004 | | DONE |
|
|
|
Change occupant load from 313 to 188. Missed in plan review follow up.
|
BLD - Request for Extension | 11/2/2004 | 11/2/2004 | 11/2/2004 | | PASS |
Tom Arcoraci
|
|
|
Myong Ching - not quite finished with the church
|
BLD-Aging Inspection | 9/8/2004 | 9/8/2004 | 9/8/2004 | | NR |
Tom Arcoraci
|
|
|
|
Inspection Record Card- Bld | | | 8/24/2004 | | DONE |
|
|
|
|
BLD-Wall cover | 7/9/2004 | 7/9/2004 | 7/9/2004 | A | PASS |
Tom Arcoraci
|
|
|
east wall 5/8 x
|
BLD-Framing/Rough-in | 6/28/2004 | 6/29/2004 | 6/29/2004 | A | PASS |
Tom Arcoraci
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 6/23/2004 | 6/24/2004 | 6/24/2004 | A | PART |
Dave Hannah
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles crew needs to add lad suport bracing in over build trusses, needs to install draft stops in attic , needs to sheet rock gable truss east 1hr fire wall along with make sure hvac vent doesnt exceed 15% openning ok to insulate 6/24/2004 9:51:17 AM
|
BLD-Conference | 5/27/2004 | 6/16/2004 | 6/16/2004 | A | CANC |
Steven Webb
|
|
|
ESC
|
BLD-Conference | 5/12/2004 | 5/26/2004 | 5/26/2004 | A | DONE |
Steven Webb
|
|
|
Discussed with Andy--###-####. Pinnacle Eng. is preparing an ESC plan and Andy has secured Int. RP certification. 5/27/2004 1:11:15 PM
|
BLD - Request for Extension | 5/12/2004 | 5/13/2004 | 5/13/2004 | | PASS |
Tom Arcoraci
|
|
|
###-#### myong
|
BLD-Conference | 5/12/2004 | 5/12/2004 | 5/12/2004 | A | FAIL |
Steven Webb
|
|
|
Issued c/notice to Andy. Left message with Andy. Contractor to submit an Construction erosion and sediment plan and secure a esc permit within 2 weeks or a stop work order will be issued. Will follow up. 5/12/2004 11:13:24 AM
|
BLD-Foundation | 4/5/2004 | 4/6/2004 | 4/6/2004 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/5/2004 at 12:20:47 PM. Contact: ###-####.
|
BLD-Footing | 3/30/2004 | 3/30/2004 | 3/30/2004 | P | PASS |
Tom Arcoraci
|
|
|
andy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Footing | 3/25/2004 | 3/26/2004 | 3/26/2004 | A | NR |
Tom Arcoraci
|
|
|
|
BLD-Footing | 3/26/2004 | 3/26/2004 | 3/26/2004 | P | NR |
Tom Arcoraci
|
|
|
|
BLD-Footing | 3/24/2004 | 3/25/2004 | 3/25/2004 | P | NR |
Tom Arcoraci
|
|
|
Andy; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Aging Inspection | 2/13/2004 | 2/13/2004 | 2/13/2004 | | NR |
Tom Arcoraci
|
|
|
|
BLD-Conference | 12/1/2003 | 12/1/2003 | 12/1/2003 | P | PASS |
Tom Arcoraci
|
|
|
extend permit slow progress
|
BLD-Aging Inspection | 10/20/2003 | 10/20/2003 | 10/20/2003 | | NR |
Tom Arcoraci
|
|
|
|
(F) Reprint permit | | | 7/22/2003 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/21/2003 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 5/20/2002 | 5/20/2002 | 3/24/2003 | | PASS |
Mike Phillips
|
|
|
3/24/2003 11:10:38 M_P - activity updated through activity BLDA022 from case BLD02-01235.
|
Routing - PLANNING Land Div | 3/21/2003 | | 3/24/2003 | | PASS |
|
|
|
Parcel created prior to October 30, 1965.
|
Routing - PLAN CHECK | 3/24/2003 | | 3/24/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/24/2003 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/24/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/24/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/24/2003 | | |
|
|
|
|
Print Occupancy Form | | | 3/24/2003 | | |
|
|
|
|
Telephone call | | | 3/24/2003 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Routing - PLANNING | 3/19/2003 | | 3/21/2003 | | PASS |
|
|
|
Approved per DRH01-180 and as noted on plans.
|
Routing - PUBLIC WORKS | 3/6/2003 | | 3/19/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/5/2003 | | 3/6/2003 | | |
|
|
|
|
Routing - PUBLIC WORKS | 2/28/2003 | | 3/4/2003 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 2/13/2003 | | 2/28/2003 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Routing - PUBLIC WORKS | 2/6/2003 | | 2/13/2003 | | FAIL |
|
|
|
Need Geotech Report.
|
Routing - PLANNING | 1/29/2003 | | 2/6/2003 | | FAIL |
|
|
|
Plans do not comply with Design Review, DRH01-180, conditions of approval.
|
Routing - PLAN CHECK | 10/2/2002 | | 1/29/2003 | | |
|
|
|
|
Plan resubmittals received | | | 1/27/2003 | | DONE |
|
|
|
Received two sets of resubmittal sheets 1, 2, S.1, 3, 4, 5, 6, 7, 8, 8-A, 9, Topographic Survey, C1.0, c1.3, c1.4, c1.5, (2)Structural Calculations, and cover letter. Routed to Mike Phillips.
|
Routing - PUBLIC WORKS | 9/30/2002 | | 10/2/2002 | | FAIL |
|
|
|
Requires geotech report. kmm
|
Routing - PLAN CHECK | 6/26/2002 | | 9/30/2002 | | |
|
|
|
|
Routing - FIRE | 6/21/2002 | | 6/26/2002 | | PASS |
|
|
|
approved without written comment
|
Routing - PUBLIC WORKS | 6/26/2002 | | 6/26/2002 | | FAIL |
|
|
|
Requires Drainage Plan-Need Geotech Report
|
Plan Review Completed(1st rev) | | | 6/26/2002 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 6/6/2002 | | 6/21/2002 | | FAIL |
|
|
|
Plan review completed. Sent correctionreport to architec requesting additional information for further review prior to issuing permit.
|
Routing - PLUMBING | 5/31/2002 | | 6/5/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 5/29/2002 | | 5/31/2002 | | FAIL |
|
|
|
Plans do not comply with Design Review (DRH01-00130) conditions. The Design Review requires additional landscaping along the west building wall. Landscaping has been provided; however, it needs to be a more upright variety (not lavender) and the specific Dogwoods need to be identified (such as one with a +8' height in order to accent the wall). The original design also indicated a berm with the swale. The berm is no longer proposed; therefore, additional landscaping or fencing or some design features need to be added (see DRH01-00130 condition #5).
|
Routing - PUBLIC WORKS | 5/21/2002 | | 5/29/2002 | | FAIL |
|
|
|
Requires drainage plan ACHD ok, Geotech Report, per Brian M. kmm
|
Routing - PLANNING Land Div | 5/20/2002 | | 5/21/2002 | | FAIL |
|
|
|
need to clean up land division problems...need deed history or new deeds
|
Application received | | | 5/20/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/20/2002 | | DONE |
|
|
|
|
Fee Review-notes | 5/20/2002 | 5/20/2002 | | | |
|
|
|
|