Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD02-01261
StatusFinaled
Name HOMCO DEVELOPMENT
Site Address 2280 E SOLITUDE CT
Project NameHILLSIDE
Customer Number 
ePlanReviewNo
Description
To construct a 4031 sq. ft. two story single family dwelling with a 2077 sq. ft. unfinished basement, a 876 sq. ft. attached three car garage, 413 sq. ft. of wood deck at rear of structure and 232 sq. ft. of balcony decks off 2nd floor per approved plans, all engineering/red-lining and attached requirement lists. Note: Seperate permits will be required to finish basement. This lot is within a hillside area and is subject to the hillside ordinances. Class "A" roof system and 30 ft. defensible area will be required. This structure will be fitted with a NFPA 13D fire sprinkler system as regulated by Boise City Fire Department. The sprinkler flow alarm shall be attached to the residence smoke detection system. (1st floor 2003 sq. ft.)(2nd floor 2028 sq. ft.) PC #385 DJO
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/27/20033/28/20033/28/2003APASS
DetailsDave Hannah
steve; Phone #: ###-#### Internet Inspection Request from: Annette Moore c.c # 23802 issued 3/28/2003 12:38:26 PM
DOC - Permit Finaled3/28/20033/28/20033/28/2003PPASS
DetailsDave Hannah
FIRE-Final Inspection3/27/20033/27/20033/27/2003PPASS
DetailsRick Jackson
BLD-Final3/27/20033/27/20033/27/2003PNR
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Virginia Thornley
BLD-Grading Inspection3/27/20033/27/20033/27/2003 BON
DetailsRita DeYoung
final grading and drainage is conditionally approved upon receipt of $1500.00 bond for fine grading drainage and revegetation.
BLD-Footing3/20/20033/21/20033/21/2003PPASS
DetailsDave Hannah
Inspect footings for retaining wall. Engineering to be on site.; Phone #: ###-#### Internet Inspection Request from: Virginia Thornley
BLD-Framing/Rough-in12/9/200212/11/200212/11/2002APASS
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Virginia Thornley
BLD-Energy code compliance12/9/200212/11/200212/11/2002APASS
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Virginia Thornley
BLD-Framing/Rough-in12/5/200212/6/200212/6/2002AFAIL
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Virginia Thornley c/n on site ok to insulate after fire sprinkler r/i is done 12/6/2002 11:56:50 AM
BLD-Framing/Rough-in11/22/200211/22/200211/22/2002PPART
DetailsDave Hannah
shear- roger; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie shear ok to cover ext walls 11/22/2002 2:44:39 PM
BLD-Framing/Rough-in11/21/200211/21/200211/21/2002PFAIL
DetailsTony Young
roger; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
need to fix straps, re-nail some areas 11/21/2002 4:52:22 PM
BLD-Framing/Rough-in11/11/200211/13/200211/13/2002PNR
DetailsSteven Webb
Shear Wall Inspection; Phone #: ###-#### Internet Inspection Request from: Virginia Thornley C/N posted--No approved plans on site. 11/13/2002 2:08:57 PM
BLD-Framing/Rough-in11/4/200211/4/200211/4/2002PFAIL
DetailsDave Hannah
shear wall\\call steve ###-#### first prior to going; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung no cite aproved plans on site 11/4/2002 4:38:44 PM
BLD-Foundation8/21/20028/21/20028/21/2002PPART
DetailsTony Young
shawn ; Phone #: ###-####
garage walls and retaining wall 8/21/2002 1:59:20 PM
BLD-Footing8/19/20028/20/20028/20/2002APART
DetailsTony Young
Phone #: ###-####
garage ftgs 8/20/2002 12:26:11 PM
BLD-Wall cover8/2/20028/5/20028/5/2002ACANC
DetailsDave Hannah
SHAWN; Phone #: ###-####
BLD-Foundation8/5/20028/5/20028/5/2002APART
DetailsDave Hannah
95 % complete
BLD-Footing7/30/20027/31/20027/31/2002PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 07/30/2002 at 13:34:13. Contact: ###-####.
Plan assigned to (DJO)7/12/20027/12/20027/18/2002 PASS
DetailsDan Overy
7/18/2002 10:21:28 DJO - activity updated through activity BLDA022 from case BLD02-01261.
Plan Reviewer's activity  7/18/2002 DONE
received engineered red-lines showing grid lines. will red-line to submitted plans. designer has faxed 8" X 11" addendum for balcony deck. cramer truss has sent modified floor framing package to cover storage area.
PLANS/APPL TAKEN TO FRONT DESK  7/18/2002 DONE
Case Summary (BLD)  7/18/2002 DONE
Plan Review Report  7/18/2002 DONE
Inspection Record Card- Bld  7/18/2002 DONE
Print Occupancy Form  7/18/2002 DONE
Telephone call  7/18/2002 DONE
Issue PAID IN FULL permit  7/18/2002 DONE
Plan Reviewer's activity  7/15/2002 PEND
started initial review friday 7/12/02. grid lines and balcony deck framing were not indicated on plans. wall bracing cannot be checked without grid lines being established on plans. will issue when this information is received and reviewed.
Plans ACCEPTED BY PLAN CHECK  7/12/2002 PEND
BLD-Grading Inspection6/28/20026/28/20026/28/2002 PASS
DetailsRita DeYoung
Footing subgrade has been approved by the geotechnical engioneer
Routing - FIRE6/20/2002 6/25/2002 DONE
Block 1, lot 95, Fire sprinklers required, complying with 13D.
Routing - PLANNING6/17/20026/17/20026/17/2002 PASS
Revised site plan.
Routing - PLANNING6/4/2002 6/7/2002 FAIL
Excxeeds height allowed. Left message for Steve Yates.
Routing - PUBLIC WORKS6/4/2002 6/4/2002 PASS
Routing - PUBLIC WORKS GRADING5/22/2002 6/3/2002 PASS
DetailsRita DeYoung
APPROVED AS CATEGORY 3 WITH CONDITIONS OF APPROVAL IN LETTER ATTACHED TO PLANS
Application received  5/22/2002  
Routing - PLAN CHECK6/26/2002