Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD02-01263
StatusFinaled
Name ZIONS BANK
Site Address 100 N 9TH ST
Project NameALEXANDER BLDG
Customer Number 
ePlanReviewNo
Description
(ZIONS BANK - 1ST FLR) This building is fire sprinklered to allow the 3rd story. To convert a retail sales tenant space on the main floor to a 2,324 square foot office tenant space. Selective demolition is also covered under this permit. Work is to include interior nonbearing walls and interior finishes all per approved drawings and plan review conditions on file. The location of fire sprinkler heads shall comply with NFPA 13-1999 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD10/28/200310/28/20036/7/2005 DONE
Second Notice has not been responded to.
Second Fax Request4/28/20034/28/200310/28/2003 DONE
First Notice has not been responded to.
Fee Review-notes7/29/20037/29/20037/29/2003 DONE
Fee Review-notes5/22/20025/22/20023/21/2003 DONE
Permanent Occupancy 10/9/200210/9/2002 DONE
Details
FIRE-Final Inspection10/8/200210/9/200210/9/2002PCANC
DetailsRick Jackson
dave; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie--already an am set up
FIRE-Final Inspection10/8/200210/9/200210/9/2002APASS
DetailsRick Jackson
fire fn dave -###-####
BLD-Final10/9/200210/9/200210/9/2002PPASS
DetailsCarl Dependahl
re-insp fn -dave ###-#### ...card at city 10/9/02 4:11:27 PM
BLD-Conference10/9/200210/9/200210/9/2002APASS
DetailsCarl Dependahl
w/ Rick...will post final
Permanent occupancy  10/9/2002 DONE
Perm. Occ. Cert. #9392 issued 10-9-02 to Zion's Bank (addn.)
BLD-Final9/11/20029/11/20029/11/2002PPART
DetailsTom Arcoraci
temp occ -david; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok for temp 9/11/2002 4:05:28 PM
FIRE-Final Inspection9/11/20029/11/20029/11/2002PPART
DetailsRick Jackson
temp occ -david; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie approved by Dave Miller for temp occ pending completion of fire alarm permit for duct detectors for AHU shutdown 9/11/2002 4:08:28 PM
Temporary occupancy  9/11/2002 DONE
Temp. Occ. Cert. #4859 issued 9-11-02 to Zion's Bank.
BLD-Final9/4/20029/5/20029/5/2002PNR
DetailsCarl Dependahl
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
FIRE-Final Inspection9/4/20029/5/20029/5/2002AFAIL
DetailsRick Jackson
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung need door hardware completed; per Dave Miller a temp occ can be issued if door hardware is completed; alarm plans not submitted as of today; will need to verify duct detectors/ alarms plans for permanent occ 9/5/2002 4:02:48 PM
FIRE-Conference8/26/20028/26/20028/26/2002PPART
DetailsRick Jackson
met with GC while doing the fire sprinkler r/i; door hardware per plans; exit signs per plans; need fire alarm plans for new duct detectors
BLD-Framing/Rough-in8/8/20028/9/20028/9/2002APART
DetailsCarl Dependahl
###-####... 8/9/2002 3:05:18 PM
BLD-Framing/Rough-in8/8/20028/8/20028/8/2002PPART
DetailsCarl Dependahl
DAVE ###-####...ok to 1 side...fireblock all floor penetrations. 8/8/2002 10:21:10 AM
BLD-Framing/Rough-in8/8/20028/8/20028/8/2002PPART
DetailsCarl Dependahl
from 8-7; complete elec, recall when ready. 8/8/2002 1:41:38 PM
BLD-Framing/Rough-in8/7/20028/7/20028/7/2002PCANC
DetailsJim Storey
DAVE ###-#### out fo time to perform insp. due to work load. 8/7/2002 5:48:38 PM
BLD-Framing/Rough-in8/7/20028/7/20028/7/2002PNR
DetailsCarl Dependahl
out of time to perform insp. due to work load...done by 301 8/8/2002 10:23:02 AM
Issue PAID IN FULL permit  6/24/2002 DONE
Print Occupancy Form  6/11/2002 DONE
Inspection Record Card- Bld  6/11/2002 DONE
Telephone call  6/11/2002 DONE
permit ready
Routing - FIRE6/5/2002 6/11/2002 DONE
Plan assigned to (CJW)5/24/2002 6/10/2002 PASS
DetailsCarl Westfall
6/10/2002 16:18:16 CJW - activity updated through activity BLDA022 from case BLD02-01263.
Plan Review Completed(1st rev)  6/10/2002 PASS
Routing - PLAN CHECK6/10/2002 6/10/2002 PASS
PLANS/APPL TAKEN TO FRONT DESK  6/10/2002 PASS
Routing - PLAN CHECK5/24/2002 6/5/2002 PASS
UBC plan review was started June 4, 2002 and finished the next day. The drawings were approved with conditions. See the conditions list.
Plan resubmittals received  6/4/2002 DONE
Received two copies of sheets M-1, M-2, DE-1, 3-1, E-2, E-3, and one copy of cover letter. Routed to Carl W. kmm
Plans ACCEPTED BY PLAN TECH  5/23/2002 DONE
Application received  5/22/2002  
Recd Pcfee & Taken To Pln CK  5/22/2002 DONE