(C & R DISTRIBUTING)(GOWEN BUSINESS PARK) Establishing occupancy for a new tenant in an existing 15,642 sq.ft. space for warehouse and office use per approved plans on file. A "vanilla finish" permit was done under BLD02-00331. A Racking permit is being done under BLD02-01306. Both the "vanilla finish" and Racking permit need to be finaled in conjunction with this Tenant Permit. Products stored in the warehouse to be dry foods and canned foods in cardboard boxes. A Certificate of Occupancy is to be issued when all permits are completed and approved. DO NOT ISSUE Certificate of Occupancy without final of the racking permit BLD02-01306 and "vanilla finish" BLD02-00331. No motor vehicles in the warehouse. NOTE: This building is fully fire sprinklered. (PC#0349-02) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes7/29/20037/29/20037/29/2003 DONE
Permanent occupancy  10/31/2002 DONE
Perm. Occ. Cert. #9423 issued 10-31-02 to C & R Distributing.
Permanent Occupancy 10/28/200210/28/2002 DONE
Details
BLD-Final10/28/200210/28/200210/28/2002APASS
DetailsRick Jackson
this is the one I just called you about. thanks j.storey
BLD-Final10/28/200210/28/200210/28/2002APASS
DetailsJim Storey
need cdhd sign off. final perm ok upon sign off. 10/28/2002 9:41:00 AM
Issue PAID IN FULL permit  9/30/2002  
Telephone call  8/8/2002 DONE
SPOKE WITH MATT SAID HE WOULD GET IN TOUCH WITH HIS CLIENT
Telephone call  7/24/2002 DONE
left mess for matt that permit is ready
Print Occupancy Form  6/12/2002 DONE
Inspection Record Card- Bld  6/12/2002 DONE
Telephone call  6/12/2002 DONE
left message permit ready and fees due
Routing - FIRE6/6/20026/11/20026/11/2002 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  6/11/2002 DONE
Routing - PLAN CHECK6/11/2002 6/11/2002 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  6/11/2002 PASS
Plan assigned to (JCB)5/31/2002 6/11/2002 PASS
DetailsJason Blais
6/11/2002 14:46:49 JCB - activity updated through activity BLDA022 from case BLD02-01305.
Routing - PLAN CHECK5/31/2002 6/6/2002 PEND
Plan review sent and faxed to architect. No response required. When approved by Fire Dept. permit can be issued. Plans routed to Fire Dept.
First Notice5/29/20025/29/20025/29/2002 DONE
Plans ACCEPTED BY PLAN TECH  5/29/2002 DONE
Application received  5/29/2002  
Recd Pcfee & Taken To Pln CK  5/29/2002