BLD-Final | 11/20/2002 | 11/21/2002 | 11/21/2002 | P | PASS |
Jim Sly
|
|
|
###-#### CARLA C/C issued. 11/21/2002 3:50:22 PM
|
DOC - Permit Finaled | 11/21/2002 | 11/21/2002 | 11/21/2002 | P | PASS |
Jim Sly
|
|
|
Finaled by inspector at 11/21/2002 3:50:31 PM
|
BLD-Energy code compliance | 9/19/2002 | 9/20/2002 | 9/20/2002 | A | PASS |
Dave Hannah
|
|
|
bill; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie c/n items completed ok to cover 9/20/2002 8:42:14 AM
|
BLD-Framing/Rough-in | 9/13/2002 | 9/17/2002 | 9/17/2002 | A | FAIL |
Dave Hannah
|
|
|
###-#### ; Phone #: ###-#### Internet Inspection Request from: Linda Hartwell c/n on site ok to insulate 9/17/2002 1:20:18 PM
|
BLD-Framing/Rough-in | 9/9/2002 | 9/11/2002 | 9/11/2002 | A | NR |
Jim Sly
|
|
|
###-#### bill Need trade R/I's foam seal. 9/11/2002 11:14:20 AM
|
BLD-Framing/Rough-in | 8/30/2002 | 9/3/2002 | 9/3/2002 | P | PART |
Dave Hannah
|
|
|
###-#### shear ok to cover ext 9/3/2002 4:03:46 PM
|
BLD-Foundation | 7/19/2002 | 7/22/2002 | 7/22/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 07/19/2002 at 13:22:48. Contact: ###-####.w.i.p about 80% 7/22/2002 4:20:50 PM
|
BLD-Footing | 7/18/2002 | 7/19/2002 | 7/19/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 07/18/2002 at 13:05:52. Contact: ###-####. work in progress setbacks ok 7/19/2002 10:58:39 AM
|
BLD-Footing | 7/18/2002 | 7/18/2002 | 7/18/2002 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/18/2002 at 08:33:47. Contact: ###-####.
|
(F) Reprint permit | | | 7/17/2002 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 7/5/2002 | | 7/8/2002 | | PASS |
Perry Paine
|
|
|
7/8/2002 08:56:17 PEP - activity updated through activity BLDA022 from case BLD02-01375.
|
Inspector's copy Bld permit | | | 7/8/2002 | | |
|
|
|
|
Plan Review Report | | | 7/8/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/8/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/8/2002 | | DONE |
|
|
|
|
Telephone call | | | 7/8/2002 | | DONE |
|
|
|
permit ready and fees due
|
Print Pending Permit.LaserJet4 | | | 7/8/2002 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/8/2002 | | DONE |
|
|
|
|
Pending Assignment by DJO | 6/5/2002 | | 7/5/2002 | | DONE |
Dan Overy
|
|
|
7/5/2002 13:08:08 PEP - activity updated through activity BLDA176 from case BLD02-01375.
|
Routing - PUBLIC WORKS | 6/21/2002 | | 6/21/2002 | | PASS |
|
|
|
Easement from Par B to Par A required. Assessment for 7,794 s.f. ROS 5811
|
Routing - PLANNING | 6/20/2002 | 6/20/2002 | 6/20/2002 | | PASS |
|
|
|
After working with Carla Bulen on site plan on 6/19 & reviewing conditions of approval on CAA02-00154, the site plan will be passed per SS because of KG's approval--keeping in mind garage side total back up of 25'. AKT
|
Routing - PLANNING | 6/17/2002 | | 6/18/2002 | | FAIL |
|
|
|
Left msg. 6/18 to Bill & Carla. Informed of inadequate site plan--not to any specifications! Hold bin until updated, accurate & acceptable plan is brought in. Was told during earlier application new site plan would be required. AKT
|
Routing - PLANNING Land Div | 6/17/2002 | 6/17/2002 | 6/17/2002 | | PASS |
|
|
|
rec'd new deeds, parcel #'s, legals and recorded ROS
|
Application received | | | 6/5/2002 | | |
|
|
|
|
Routing - PLAN CHECK | 6/21/2002 | | | | |
|
|
|
|