Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD02-01413
StatusFinaled
Name BOISE CITY ADMINISTRATIVE OFFICES
Site Address 150 N CAPITOL BLVD
Project NameCITY HALL EXPANSION-1ST FLR
Customer Number 
ePlanReviewNo
Description
(BOISE CITY ADMINISTRATIVE OFFICES)(CITY HALL EXPANSION-1st FLOOR) (ARTS COMMISSION, DFM & UTILITY BILLING) To perform selective demolition of entire 1st floor. To remodel a 12,812 sq. ft. area for use as offices and support areas. To construct interior, non-bearing, non-combustible, fire-resistive walls to create offices, wprk rooms, conference rooms, training room & break room; to upgrade restrooms for accessibility compliance; new suspended grid ceiling system; upgrade mechanical, electrical, plumbing, fire sprinkler and alarm systems to meet tenant needs and comply with current adopted Boise City codes. All per approved plans, to include red-line notes & attached plan reviews. NOTE: The entire building is fire sprinklered. A Certificate of Occupancy is required. PC#02-372/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 6/1/20096/1/2009 DONE
DetailsBarbara Stitt
CHANGE STATUS TO (ISS)  6/1/2009 DONE
DetailsBarbara Stitt
Per Bob Archibald-see scanned documents///6-1-09 BAS
Permanent Occupancy  6/1/2009 DONE
DetailsBarbara Stitt
BLD-Final5/29/20095/29/20095/29/2009PPASS
DetailsBob Archibald
Fire alarm and sprinker requirements completed. FIR02-00515 & 00451
Meeting  11/27/2007 DONE
Reviewed project status with Mike Timmerman. He willl follow up with Bob Archibald to get remaining items resolved and permit finaled.
BLD-Aging Inspection3/1/20043/1/20043/1/2004 DONE
DetailsDave Hannah
DOC - Permit Expired3/1/20043/1/20043/1/2004APASS
DetailsDave Hannah
Expired by inspector at 3/1/2004 9:41:13 AM
Case Summary (BLD)  1/12/2004  
BLD-Conference7/22/20037/22/20037/22/2003PPASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 7/22/2003 at 11:10:16 AM. Contact: ###-####.w/ arch at site: need dampers at bsmt occupancy separation as per c/n. 7/22/2003 3:18:19 PM
BLD-Conference6/2/20036/4/20036/4/2003PCANC
DetailsCarl Dependahl
BLD-Final5/30/20036/2/20036/2/2003APART
DetailsCarl Dependahl
###-####
FIRE-Final Inspection3/20/20033/20/20033/20/2003PPART
DetailsRick Jackson
temp occ aprroved per agreementletter to interconnect standpipes and monitor tampers in basement
BLD-Final3/20/20033/20/20033/20/2003APART
DetailsGeorge Slane
ok for temp. occ.
Temporary occupancy  3/20/2003 DONE
Temp. Occ. Cert. #4935 issued 3-20-03 to the City Hall Expansion, 1st floor (arts commission, DFM & UB).
BLD-Final3/14/20033/17/20033/17/2003AFAIL
DetailsCarl Dependahl
###-####; keep c/n....arch to clarify occupancy separation...(s/f dampers, elevator lobby at bsmt?) 3/17/2003 1:19:36 PM
FIRE-Final Inspection3/14/20033/17/20033/17/2003AFAIL
DetailsRick Jackson
###-#### ###-#### need alternate floor elevator recall; monitor all tampers; sprinkler all areas; interconnect all standpipes; install alarm notification in all walkways and lobbies; need alarm notification on second floor open office area; 3/17/2003 10:45:49 AM
BLD-Final3/13/20033/14/20033/14/2003ANR
DetailsCarl Dependahl
###-####...keep c/n (fire final...?)
3/14/2003 5:04:02 PM
BLD-Final3/13/20033/14/20033/14/2003ANR
DetailsCarl Dependahl
###-####...keep c/n re fire; struct. issues ok 3/17/2003 1:14:09 PM
FIRE-Final Inspection3/13/20033/14/20033/14/2003ACANC
DetailsRick Jackson
###-####
BLD-Final3/6/20033/7/20033/7/2003AFAIL
DetailsCarl Dependahl
###-####...c/n obtain fire, complete misc items, post occ load at training rm; egress/access controll devices (OFOI) to be approved (N.I.C?) 3/7/2003 3:42:02 PM
FIRE-Final Inspection3/5/20033/6/20033/6/2003AFAIL
DetailsRick Jackson
###-#### need timeline for fixing standpipe interconnection and sprinklering all areas; remove head in east comm room; need standard response sprinklers on second floor as QR's were installed; need max occupant load sign in training room 3/6/2003 1:02:30 PM
BLD-Final3/5/20033/6/20033/6/2003ANR
DetailsCarl Dependahl
###-####...no insp, need fire ok, etc. 3/6/2003 3:48:19 PM
BLD-Conference2/11/20032/11/20032/11/2003PPASS
DetailsCarl Dependahl
scott...re T/O....need all trade ok's 2/11/2003 2:40:43 PM
BLD-Conference1/30/20031/31/20031/31/2003PPASS
DetailsCarl Dependahl
grid reinsp...ok, braces added 1/31/2003 3:32:32 PM
BLD-Framing/Rough-in1/29/20031/30/20031/30/2003ANR
DetailsCarl Dependahl
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung...need elec ok'd; add braces at t.o.w. ...some missed; chk spreaders at final 1/30/2003 1:51:18 PM
BLD-Framing/Rough-in1/30/20031/30/20031/30/2003PPART
DetailsCarl Dependahl
###-####
BLD-Framing/Rough-in1/30/20031/30/20031/30/2003PCANC
DetailsCarl Dependahl
grid reinsp.
BLD-Framing/Rough-in12/19/200212/20/200212/20/2002APART
DetailsCarl Dependahl
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung; int partitions,floor penetrations, ok ; verbal for arch to investigate hvac penetrations at east stair enclosure. 12/20/2002 1:06:02 PM
BLD-Framing/Rough-in12/10/200212/11/200212/11/2002ANR
DetailsCarl Dependahl
###-####
BLD-Framing/Rough-in12/11/200212/11/200212/11/2002PPART
DetailsCarl Dependahl
8694101 scott...SEAL PLBG FL. PENETRATIONS...OK TO 1 SIDE. NEED FIRE SPRINKLER INSP. PRIOR TO CEILING COVER; HAS HVAC PENETRATION AT EAST STAIR ENCLOSURE... 12/11/2002 3:56:18 PM
BLD-Conference11/5/200211/6/200211/6/2002ADONE
DetailsTom Arcoraci
Scott cn issued by 340 11/6/2002 8:46:29 AM 11/6/2002 8:47:15 AM
Issue & PRINT to be Invoiced  8/23/2002 DONE
Telephone call  8/8/2002 DONE
LEFT MESSAGE WITH TED ISBELL TO PICK UP PERMIT//TED CALLED BACK AT 11:50AM TODAY SAID HE WOULD BE IN TO PICK UP PERMIT
Routing - PLAN CHECK6/29/2002 7/8/2002 PASS
Approved as noted and attached.
PLANS/APPL TAKEN TO FRONT DESK  7/8/2002 PASS
Plans to front desk for issue.
Inspection Record Card- Bld  7/8/2002 DONE
Print Occupancy Form  7/8/2002 DONE
Plan assigned to (DRS)6/13/2002 7/8/2002 PASS
DetailsDan Stuart
7/8/2002 08:44:31 DRS - activity updated through activity BLDA022 from case BLD02-01413.
Routing - FIRE6/21/2002 6/29/2002 PASS
Plan Review Completed(1st rev)  6/26/2002 FAIL
Meeting  6/21/2002  
MET WITH tED iSBELL TO REVIEW ITEMS ON PLANS NEEDING CORRECTED BY CLARIFICATION OR RESUBMITTAL SHEETS. tED WILL HAVE INFORMATION AND PLAN RESUBMITTALS IN BY LATE WEDNESDAY THE 26 OF JUNE. I TOLD HIM I WOULD BE OUT OF TOWN ON VACATION UNTIL THE 8TH OF JULY. HE SAID THIS WOULD NOT CAUSE A PROBLEM. I WILL FORWARD THE PLANS TO FIRE CODE ANALYST FOR REVIEW WHILE WAITING FOR RESPONSE.
Plan resubmittals requested  6/21/2002 FAIL
Met with architect to review data missing or incorrect on plans. He will submit clarifications.
Routing - PLAN CHECK6/14/2002 6/21/2002 FAIL
Clarifications required. Met with architect to review. He will submit requested information.
Routing - PUBLIC WORKS6/13/2002 6/14/2002 CANC
Plans ACCEPTED BY PLAN TECH  6/11/2002 DONE
Fee Review-notes6/10/20026/10/20026/10/2002 DONE
DetailsBarbara Stitt
Application received  6/10/2002