Fee Review-notes | 7/29/2003 | 7/29/2003 | 7/29/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/24/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9419 issued 10-24-02 to Idaho Power Operations Center.
|
BLD-Final | 10/22/2002 | 10/23/2002 | 10/23/2002 | A | PASS |
Russ Owen
|
|
|
###-####ok perm oc. 10/23/2002 2:55:29 PM
|
Permanent Occupancy | | 10/23/2002 | 10/23/2002 | | DONE |
|
|
|
|
BLD-Final | 10/21/2002 | 10/22/2002 | 10/22/2002 | P | CANC |
Tom Arcoraci
|
|
|
bill ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Final | 9/19/2002 | 9/20/2002 | 9/20/2002 | P | PART |
Jim Sly
|
|
|
fn -bill- ###-#### - OK for Temp Occ. C/N install toilet partitions. 9/20/2002 12:57:47 PM
|
FIRE-Alarm Testing | 9/19/2002 | 9/20/2002 | 9/20/2002 | A | PASS |
Troy Cobbley
|
|
|
fire alarm system finaled 9/20/2002 8:58:43 AM
|
FIRE-Final Inspection | 9/19/2002 | 9/20/2002 | 9/20/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled 9/20/2002 8:59:18 AM
|
BLD-Final | 9/18/2002 | 9/19/2002 | 9/19/2002 | P | CANC |
Russ Owen
|
|
|
bill; Phone #: ###-#### Internet Inspection Request from: Darla Downs----cancel per bill with krizenbeck
|
FIRE-Final Inspection | 9/17/2002 | 9/18/2002 | 9/18/2002 | P | FAIL |
Troy Cobbley
|
|
|
provide smoke detectors at door hold opens, add exit sign near breaker box, repair the other exit signs 9/18/2002 3:49:44 PM
|
BLD-Framing/Rough-in | 9/5/2002 | 9/6/2002 | 9/6/2002 | A | PART |
Russ Owen
|
|
|
BILL; Phone #: ###-#### Internet Inspection Request from: Annette Moore. ceiling grid ok. 9/6/2002 10:15:03 AM
|
BLD-Framing/Rough-in | 8/13/2002 | 8/14/2002 | 8/14/2002 | P | PART |
Russ Owen
|
|
|
###-####floor only needs crossbracing and insulation. 8/14/2002 1:42:08 PM
|
BLD-Framing/Rough-in | 8/8/2002 | 8/8/2002 | 8/8/2002 | P | FAIL |
Russ Owen
|
|
|
BILL ; Phone #: ###-####. needs some plates shot at top of walls contractor on site. 8/8/2002 3:24:34 PM
|
BLD-Framing/Rough-in | 8/7/2002 | 8/7/2002 | 8/7/2002 | P | NR |
Russ Owen
|
|
|
###-#### bill
|
Issue PAID IN FULL permit | | | 7/18/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/17/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/17/2002 | | DONE |
|
|
|
|
Telephone call | | | 7/17/2002 | | DONE |
|
|
|
PERMIT READY AND FEES DUE
|
Plan assigned to (CJW) | 6/14/2002 | | 7/16/2002 | | PASS |
Carl Westfall
|
|
|
7/16/2002 14:29:07 CJW - activity updated through activity BLDA022 from case BLD02-01435.
|
Routing - PLAN CHECK | 7/11/2002 | | 7/16/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/16/2002 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/12/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets G101, A101, AND A201 to include comment letter. Routed to Carl Westfall.
|
Routing - PLUMBING | 7/8/2002 | | 7/10/2002 | | PASS |
|
|
|
24 f.u. max on 2" vent. your plan view shows 5 wc-02 and 01s and your DWV iso shows 4. increase vent to 3" from last tee to vtr, add water supply for 5th wc.
|
Plan Review Completed(1st rev) | | | 7/8/2002 | | DONE |
|
|
|
|
Routing - FIRE | 7/3/2002 | | 7/8/2002 | | PASS |
|
|
|
approved without written comment
|
Routing - PLAN CHECK | 6/14/2002 | | 7/3/2002 | | |
|
|
|
Failed first UBC review. UBC plan review started June 18, 2002. (6-18-02 Waiting for original drawings, additions, and remodels - called Mr. Read to request them.) UBC plan review recommenced July 2, 2002 and finished the next day. A response was required from the architect. See the conditions list.
|
Additional plans submitted | | | 7/1/2002 | | DONE |
|
|
|
Received additional drawings from Idaho Power (with transmittal letter and additional values for Certificate of Value Sheet) as follows:
1. Original set of construction drawings for Boise Operation Center Phase 2
2. Computer Room Tenant Improvement on mezzanine level.
3. UPS Tenant Improvement for Data Processing.
4. Tenant Improvement to mezzanine level.
5. Dispatch Center Addition.
Routed to Carl Westfall.
|
Telephone call | | | 6/14/2002 | | DONE |
|
|
|
Called and left message with Tracy Read: 1. Copy of original plans: building annexed into the City 12/30/99
2. Values for elec. plumb. mech. etc.
kmm
|
Routing - PUBLIC WORKS | 6/14/2002 | | 6/14/2002 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 6/13/2002 | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/13/2002 | | DONE |
|
|
|
|
First Notice | 6/11/2002 | 6/11/2002 | 6/11/2002 | | DONE |
|
|
|
|
Application received | | | 6/11/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/11/2002 | | DONE |
|
|
|
|