Permit Information
Permit NumberBLD02-01461
StatusFinaled
Name BAJA FRESH
Site Address 992 N MILWAUKEE ST
Project NameBaja Fresh Mexican Grill
Customer Number 
ePlanReviewNo
Description
Baja Fresh Mexican Grill * To construct a new 2685 square foot, one story, wood framed, fast food restaurant and related site improvements. All construction per the approved plans and attached comment list. DRH01-00207/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 2/19/20032/19/2003 DONE
Details
Permanent occupancy  2/19/2003 DONE
Perm. Occ. Cert. #9562 issued 2-19-03 to Baja Fresh.
PubWorks Occupancy Approval12/11/200212/11/200212/11/2002 DONE
Drainage project complete, signed permanent occupancy 12/11/02. S.Landaluce
BLD-Final12/10/200212/11/200212/11/2002APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 12/10/2002 at 17:26:47. Contact: ###-####.temp oc ok pending all req signatures for a perm. 12/11/2002 6:30:37 PM
BLD-Final12/10/200212/11/200212/11/2002APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 12/10/2002 at 17:26:47. Contact: ###-####.temp oc ok pending all req signatures for a perm. 12/11/2002 6:30:37 PM
FIRE-Final Inspection12/11/200212/11/200212/11/2002APASS
DetailsTroy Cobbley
fire life/safety finaled 12/11/2002 2:11:05 PM
Temporary occupancy  12/11/2002 DONE
Temp. Occ. Cert. #4902 issued 12-11-02 to Baja Fresh.
BLD-Final12/10/200212/10/200212/10/2002PNR
DetailsRuss Owen
###-#### dave This needs all required signatures on card prior to calling for a final. 12/10/2002 1:50:50 PM
FIRE-Final Inspection12/10/200212/10/200212/10/2002PFAIL
DetailsTroy Cobbley
three emergency lights and two duct detectors do not work. Still need air balance reports 12/10/2002 3:39:14 PM
Code Occupancy Approval Temp12/10/200212/9/200212/9/2002ADONE
DetailsScott M.Brown
BOND POSTED FOR LANDSCAPE IN THE AMOUNT OF $2500.00, TEMP OCCUPANCY SIGNED OFF. 12/10/2002 11:16:26 AM
BLD-Conference12/9/200212/9/200212/9/2002PPART
DetailsRuss Owen
adding fire blanket to top of hood 12/9/2002 4:36:19 PM
BLD-Framing/Rough-in12/6/200212/6/200212/6/2002PPART
DetailsRuss Owen
grid insp --dave ###-####
FIRE-Final Inspection12/6/200212/6/200212/6/2002PFAIL
DetailsTroy Cobbley
fire suppression test . The lights under the hood need to shut off when the fire suppression system activates
BLD-Conference12/4/200212/5/200212/5/2002APART
DetailsRuss Owen
conference on kitchen hood. 12/4/2002 5:55:23 PM Posted a c/n for grease hood. 12/5/2002 1:37:57 PM
BLD-Conference12/4/200212/4/200212/4/2002PCANC
DetailsRuss Owen
###-#### called contractor will meet am. 12/4/2002 5:54:59 PM
BLD-Framing/Rough-in11/18/200211/19/200211/19/2002APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 11/18/2002 at 13:20:45. Contact: ###-####.ok subject to other inspectors electrical, plumbing. framing completed. 11/19/2002 12:29:35 PM
BLD-Conference11/12/200211/12/200211/12/2002PPART
DetailsRuss Owen
will be useing duct wrap at 1 hr shaft. 11/12/2002 2:55:50 PM
BLD-Framing/Rough-in11/7/200211/8/200211/8/2002APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 11/07/2002 at 13:07:56. Contact: ###-####.engineer approved retro fit anchor bols at plate breaks . 11/8/2002 10:47:45 AM
BLD-Framing/Rough-in11/6/200211/7/200211/7/2002APART
DetailsRuss Owen
dave; Phone #: ###-#### Internet Inspection Request from: Marsha Smylieneeds ancho 11/7/2002 12:30:06 PM exterior walls only needs anchor bolts at plate breaks. notified contractor on site,to check with engineer. 11/7/2002 12:41:35 PM
BLD-Framing/Rough-in10/29/200210/30/200210/30/2002APART
DetailsRuss Owen
ok to side. 10/30/2002 5:24:25 PM
BLD-Framing/Rough-in10/28/200210/29/200210/29/2002PPART
DetailsRuss Owen
###-####still makeing rwepairs. 10/29/2002 2:27:52 PM
BLD-Framing/Rough-in10/25/200210/28/200210/28/2002AFAIL
DetailsRuss Owen
###-#### dave c/n pon site. 10/28/2002 2:13:04 PM
BLD-Framing/Rough-in10/22/200210/23/200210/23/2002AFAIL
DetailsRuss Owen
###-####. posted c/n. 10/23/2002 4:18:19 PM
BLD-Framing/Rough-in10/22/200210/22/200210/22/2002PPART
DetailsTom Arcoraci
roof load; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung roof ok for cover 10/22/2002 4:38:53 PM
BLD-Framing/Rough-in10/22/200210/22/200210/22/2002PPART
DetailsTom Arcoraci
roof load; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung roof ok for cover 10/22/2002 4:38:53 PM
BLD-Foundation9/23/20029/24/20029/24/2002APASS
DetailsRuss Owen
###-####
BLD-Footing9/19/20029/20/20029/20/2002APASS
DetailsJim Sly
###-####
BLD-Concrete9/18/20029/19/20029/19/2002PNR
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung rebar not finished about 10% crew will re schedule for tomorrow am 9/19/2002 1:08:38 PM
(F) Reprint permit  8/19/2002  
Issue PAID IN FULL permit  8/14/2002 DONE
Inspection Record Card- Bld  8/7/2002 DONE
Print Occupancy Form  8/7/2002 DONE
Telephone call  8/7/2002 DONE
permit ready and fees due
Routing - PLAN CHECK8/6/2002 8/6/2002 PASS
PLANS/APPL TAKEN TO FRONT DESK  8/6/2002 PASS
Plan assigned to (JCM)6/17/2002 8/6/2002 PASS
DetailsJohn Menard
8/6/2002 11:33:07 JCM - activity updated through activity BLDA022 from case BLD02-01461.
Routing - FIRE7/30/2002 8/2/2002 PASS
DetailsBill Alexander
Plan resubmittals received  8/2/2002 DONE
Received two sets of resubmittal sheets E1 and E2.0 with memo letter/transmittal. Routed to John Menard.
Routing - PUBLIC WORKS8/2/2002 8/2/2002 DONE
site revisions
Plan Reviewer's activity  7/30/2002 PASS
Resubmitted plans and information have been reviewed and approved, as submitted, with attached comment lists and red lined notes. JCM
Routing - PLAN CHECK7/10/2002 7/30/2002 PASS
Plan resubmittals received  7/26/2002 DONE
Received two sets of resubmittal sheets SD-1, SD-2, L-1, C1 OF 4, C2 OF 4, C3 OF 4, C4 OF 4, 1 OF 1, A-1, A-1.00, A-1.10, A-2.00, with (1) comment letter addressed to John Menard. Received one set of resubmittal sheets SD-1, SD-2, L-1, C1 OF 4, C2 OF 4, C3 OF 4, C4 OF 4, 1 OF 1, A-1, A-1.00, A-1.10, A-2.00, with (1) comment letter addressed to Bill Alexander. Routed to John Menard.
Routing - FIRE7/9/2002 7/10/2002 FAIL
DetailsBill Alexander
Plans don't correlate. Need Type 1 Hood construction details.
Plan Review Completed(1st rev)  7/10/2002 DONE
Routing - PLAN CHECK7/2/2002 7/9/2002 FAIL
Plan resubmittals requested  7/9/2002  
Mailed the architect of record a copy of the plan review comment list requesting revisions. JCM
Routing - PLUMBING6/28/2002 7/2/2002 PASS
INCREASE WATER SERVICE PIPING TO 1 1/2" TO MATCH P-2, NOTE 3/P-2 R.P. REQUIRED ON SODA DISPENSOR, IF AN AUTO SOAP DISPENSOR IS INSTALLED AT THE MOP SINK PROVIDE A WATER SUPPLY FOR IT, PROVIDE A PVB FOR THE HOSE REEL, 2" MIN. WASTE AND VENT PIPING BELOW GRADE.
Routing - Erosion and Sediment6/21/2002 6/28/2002 PASS
Received for review on 6/26/2002

Pass with conditions attached to plans.
Routing - PLANNING6/21/2002 6/27/2002 PASS
Approved per CUP01-00142 conditions of approval.
Routing - PUBLIC WORKS6/14/2002 6/21/2002 PASS
Pending Assignment by JCM6/14/2002 6/17/2002 DONE
DetailsJohn Menard
6/17/2002 08:01:19 JCM - activity updated through activity BLDA166 from case BLD02-01461.
Plan routing begun/NEW & ADDTN  6/14/2002 DONE
Routing - PLANNING Land Div6/14/2002 6/14/2002 PASS
lot line adjustment ROS 2931
Plans ACCEPTED BY PLAN TECH  6/14/2002 DONE
grading done under Home Depot development.
First Notice6/13/20026/13/20026/13/2002 DONE
Application received  6/13/2002  
Recd Pcfee & Taken To Pln CK  6/13/2002