Second Notice BLD | 9/25/2006 | 9/25/2006 | 9/25/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 8/23/2006 | 8/23/2006 | 9/25/2006 | | DONE |
Jim Sly
|
|
|
|
BLD-Aging Inspection | 8/23/2006 | 8/23/2006 | 8/23/2006 | | PASS |
Jim Sly
|
|
|
Scott Henderson ###-#### has Cert of Occ........Fire and trades finaled Final OK
|
DOC - Permit Finaled | 8/23/2006 | 8/23/2006 | 8/23/2006 | P | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 5/9/2006 | 5/10/2006 | 5/10/2006 | A | CANC |
Jim Sly
|
|
|
|
(F) Reprint permit | | | 5/6/2003 | | DONE |
|
|
|
|
BLD-Conference | 8/23/2002 | 8/23/2002 | 8/23/2002 | A | PASS |
Tom Arcoraci
|
|
|
meeting with plumbing insp 8/23/2002 9:26:36 AM
|
BLD-Framing/Rough-in | 8/19/2002 | 8/21/2002 | 8/21/2002 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/19/2002 at 10:35:14. Contact: ###-####. ok pending spec insp and eng ok 8/21/2002 12:24:49 PM
|
Issue PAID IN FULL permit | | | 7/17/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/28/2002 | | 7/9/2002 | | PASS |
|
|
|
Plans approved as noted on plans & attached plan review comments from third party structural engineer, fire dept. & plan review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/9/2002 | | PASS |
|
|
|
To permit desk for issue.
|
Plan resubmittals received | | | 7/9/2002 | | PASS |
|
|
|
All resubmittal request answered.
|
Inspection Record Card- Bld | | | 7/9/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/9/2002 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 6/14/2002 | | 7/9/2002 | | PASS |
Dan Stuart
|
|
|
7/9/2002 11:39:10 DRS - activity updated through activity BLDA022 from case BLD02-01469.
|
Routing Off Site - STRUCTURAL | 6/17/2002 | | 7/9/2002 | | PASS |
|
|
|
Contacted PDQ to take plans to outside eng. kmm
6/20/02 - Received copy of structural review. A response is required for clarification / correction of details and second review. Copy of review faxed to Tom Brophy for response as the architect of record.
6/26/02 - Response from Structural Engineer faxed to me. Faxed copy to Third party review firm.
6/28/02 - Structural Engineer plan reviewer had one item that was not clearly answered. His original comment #3 on the MC8 x 8.5 channel instead of the C8 x 11. This information was forwarded to the Engineering company for further clarification.
7/8/02 - Received fax from Jan Welch clarifying item #3 to be the MC8 x 8.5 channel. Was not required to be resubmitted to third party review.
|
Routing - FIRE | 6/26/2002 | | 6/28/2002 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 6/28/2002 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 6/17/2002 | | 6/26/2002 | | FAIL |
|
|
|
NEED RE-SUBMITTALS FOR 3RD PARTY STRUCTURAL ENGINEERING REVIEW THAT PERFORMED FIRST REVIEW OF STRUCTURAL PLANS. COPY OF REVIEW COMMENTS FAXED TO ARCHITECT ON 6/20/02. routing to fire for review.
|
Plan resubmittals requested | | | 6/20/2002 | | FAIL |
|
|
|
Received plan review report from structural engineer acting as third party plan review of structural engineering for the HP project. A response is required. A copy of the report with cover letter was faxed to Tom Brophy at LCA for a response.
|
Routing - PUBLIC WORKS | 6/14/2002 | | 6/17/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/14/2002 | | DONE |
|
|
|
1. Dan Stuart okayed plans being submitted along as architectural and structural were stamped and signed.
|
Application received | | | 6/13/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/13/2002 | | |
|
|
|
|
Fee Review-notes | 6/13/2002 | 6/13/2002 | | | |
|
|
|
|