BLD-Final | 10/28/2002 | 10/28/2002 | 10/28/2002 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
DOC - Permit Finaled | 10/28/2002 | 10/28/2002 | 10/28/2002 | P | PASS |
Jim Sly
|
|
|
Finaled by inspector at 10/28/2002 3:10:46 PM
|
BLD-Energy code compliance | 8/28/2002 | 8/29/2002 | 8/29/2002 | P | PASS |
Dave Hannah
|
|
|
91-8607 TODD all framing c/n items completed ok t o cover 8/29/2002 2:20:07 PM
|
BLD-Framing/Rough-in | 8/28/2002 | 8/28/2002 | 8/28/2002 | P | FAIL |
Dave Hannah
|
|
|
###-#### c/n on site 8/28/2002 2:45:59 PM
|
BLD-Framing/Rough-in | 8/13/2002 | 8/13/2002 | 8/13/2002 | P | PART |
Tom Arcoraci
|
|
|
todd shear nail; Phone #: ###-#### ok to side 8/13/2002 2:03:58 PM
|
BLD-Foundation | 7/18/2002 | 7/19/2002 | 7/19/2002 | P | PART |
Dave Hannah
|
|
|
chris ###-#### found wall
|
BLD-Footing | 7/18/2002 | 7/18/2002 | 7/18/2002 | P | PART |
Dave Hannah
|
|
|
set backs ok still working on placing rebar 7/18/2002 1:49:04 PM
|
Issue PAID IN FULL permit | | | 7/18/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/27/2002 | | 7/16/2002 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 7/12/2002 | | 7/16/2002 | | PASS |
Steve Munroe
|
|
|
7/16/2002 07:31:03 SAM - activity updated through activity BLDA022 from case BLD02-01559.
|
Case Summary (BLD) | | | 7/16/2002 | | |
|
|
|
|
Plan Review Report | | | 7/16/2002 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/16/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/16/2002 | | DONE |
|
|
|
|
Telephone call | | | 7/16/2002 | | DONE |
|
|
|
|
Pending Assignment by DJO | 6/25/2002 | | 7/12/2002 | | DONE |
Dan Overy
|
|
|
7/12/2002 10:45:55 SAM - activity updated through activity BLDA183 from case BLD02-01559.
|
Routing - PLANNING | 6/25/2002 | | 6/27/2002 | | PASS |
|
|
|
Approved per CUP01-00042 conditions of approval.
|
Routing - PUBLIC WORKS | 6/27/2002 | | 6/27/2002 | | PASS |
|
|
|
|
Application received | | | 6/25/2002 | | |
|
|
|
|