Permit Information
Permit NumberBLD02-01572
StatusFinaled
Name CAPITAL SECURITIES WATER CO
Site Address 6006 W LUBKIN ST
Project NameCapital Water Corporation
Customer Number 
ePlanReviewNo
Description
(Well House #5 for Capital Water Corporation)-Replace old 500s.f. 1-story well house which has been torn down, with a new Type VN / "B" Occupancy 1-story 512s.f. well house. All per the approved plans; attached engineering and calculations PC# 389-02 pep
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval1/26/20051/26/20051/26/2005 DONE
Finaled without PW approval, no inspections, drive-by shows complete 1/26/05. R.Rokovitz
BLD-Final10/1/200210/1/200210/1/2002PPASS
DetailsDave Hannah
###-#### bill
DOC - Permit Finaled10/1/200210/1/200210/1/2002PPASS
DetailsDave Hannah
Finaled by inspector at 10/1/2002 1:47:27 PM
BLD-Framing/Rough-in8/14/20028/15/20028/15/2002PPASS
DetailsTom Arcoraci
###-####
BLD-Framing/Rough-in8/14/20028/14/20028/14/2002PPART
DetailsDave Hannah
the later the better ###-#### shear ok to cover ext 8/14/2002 3:16:45 PM
BLD-Foundation7/11/20027/12/20027/12/2002APART
DetailsRuss Owen
cal ###-#### found wall there are (3) #4 in the wall with verts on 4 foot, the engineer is to supply a new detail for as constructed, contractor on site,said this will be done. Subject to detail. 7/12/2002 1:28:36 PM
BLD-Footing7/11/20027/11/20027/11/2002PPART
DetailsRuss Owen
ft insp- cal ###-#### Arived on site waiting for 1/2 the rebar to be delivered, no approved plans on site footing is not per plan, I have made (2) phone calls, got ahold of the engineer and he verbally said footing would be ok at 14" wide with (2) # 4 horizontals in the footing. Un-approved plans at the site, indicate a 20 " wide footing with (4) #4 bars horizontal. Have been on job site approximately 45 min to do a 5 min inspection also note the concrete truck is on site now. I told them there needs to be an approved plan at the job site for the wall inspection or there will be no pour, As is pouring at there own risk. 7/11/2002 5:02:42 PM 7/11/2002 5:12:57 PM
(F) Reprint permit  7/10/2002  
Issue PAID IN FULL permit  7/9/2002 DONE
Plan assigned to (PEP)6/26/20026/26/20027/1/2002 PASS
DetailsPerry Paine
7/1/2002 08:56:47 PEP - activity updated through activity BLDA022 from case BLD02-01572.
Print Pending Permit.LaserJet4  7/1/2002  
PLANS/APPL TAKEN TO FRONT DESK  7/1/2002 DONE
Inspection Record Card- Bld  7/1/2002 DONE
Telephone call  7/1/2002 DONE
PERMIT READY AND FEES DUE
Telephone call  7/1/2002 DONE
PERMIT READY AND FEES DUE
Routing - PUBLIC WORKS6/27/2002 6/28/2002 PASS
Routing - PLANNING Land Div6/26/2002 6/27/2002 PASS
First Notice6/26/20026/26/20026/26/2002 DONE
Application received  6/26/2002  
Recd Pcfee & Taken To Pln CK  6/26/2002 DONE
Routing - Erosion and Sediment6/26/2002 6/26/2002 PASS
Waiver Letter
Passed with conditions
Routing - PLANNING6/18/2002 6/18/2002 PASS
Routing - PLUMBING6/18/2002 6/18/2002 PASS
Routing - PLAN CHECK6/28/2002