Fee Review-notes | 8/12/2003 | 8/12/2003 | 8/12/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Permanent occupancy | | | 10/24/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9421 issued 10-24-02 to Orthopedic Associates.
|
Permanent Occupancy | | 10/23/2002 | 10/23/2002 | | DONE |
|
|
|
|
BLD-Final | 10/23/2002 | 10/23/2002 | 10/23/2002 | P | PASS |
Russ Owen
|
|
|
Don Bryan, ###-####ok perm oc. 10/23/2002 4:57:58 PM
|
FIRE-Final Inspection | 10/23/2002 | 10/23/2002 | 10/23/2002 | P | PASS |
Troy Cobbley
|
|
|
fire alarm, fire sprinkler and fire life/safety finaled 10/23/2002 1:23:13 PM
|
FIRE-Sprinkler Rough-in | 9/16/2002 | 9/16/2002 | 9/16/2002 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 09/16/2002 at 08:43:55. Contact: ###-####. okay to cover; plans not required per plan review notes 9/16/2002 3:18:32 PM
|
BLD-Other | 9/16/2002 | 9/16/2002 | 9/16/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/16/2002 at 08:44:37. Contact: ###-####.ceiling ok. 9/16/2002 1:27:35 PM
|
BLD-Framing/Rough-in | 8/16/2002 | 8/19/2002 | 8/19/2002 | P | PASS |
Russ Owen
|
|
|
Don -###-####
|
(F) Reprint permit | | | 8/8/2002 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/7/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/6/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/6/2002 | | DONE |
|
|
|
|
Telephone call | | | 8/6/2002 | | DONE |
|
|
|
PERMIT READY AND FEES DUE
|
Routing - PLUMBING | 7/24/2002 | | 8/5/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/5/2002 | | 8/5/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/5/2002 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 7/2/2002 | | 8/5/2002 | | PASS |
|
|
|
8/5/2002 15:25:36 RMH - activity updated through activity BLDA022 from case BLD02-01601.
|
Routing - PLAN CHECK | 7/12/2002 | | 7/24/2002 | | PASS |
|
|
|
|
Routing - FIRE | 7/19/2002 | | 7/24/2002 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 7/24/2002 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 7/24/2002 | | 7/24/2002 | | |
|
|
|
|
Plan resubmittals received | | | 7/22/2002 | | DONE |
|
|
|
Received three copies of sheet P-1. Routed to Ron Hill. KMM
|
Routing - PLUMBING | 7/9/2002 | | 7/12/2002 | | FAIL |
|
|
|
see bld02-01600 for review comments
|
Routing - PLANNING | 7/3/2002 | | 7/9/2002 | | PASS |
|
|
|
Marty Santoyo. Office in M-1D zone.
|
Plan resubmittals received | | | 7/9/2002 | | DONE |
|
|
|
Received three sets of resubmittal sheets M-1 with transmittal. Routed to Ron Hill.
|
Routing - PUBLIC WORKS | 7/2/2002 | | 7/3/2002 | | PASS |
|
|
|
|
First Notice | 7/1/2002 | 7/1/2002 | 7/1/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/1/2002 | | DONE |
|
|
|
Informed applicant that Plumbing and Mechanical sheets were required. Applicant will submit by 7/5/02.
|
Application received | | | 7/1/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/1/2002 | | DONE |
|
|
|
|