PostCard Mailed | | | 12/10/2003 | | SENT |
|
|
|
PostCard has been mailed requesting inspection.
|
BLD-Wall cover | 10/14/2002 | 10/15/2002 | 10/15/2002 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 10/14/2002 at 14:50:35. Contact: . SHEAR--Ok to side 10/15/2002 10:33:40 AM
|
BLD-Wall cover | 10/10/2002 | 10/11/2002 | 10/11/2002 | A | FAIL |
Jim Storey
|
|
|
batts in flat ceilling 9.5 only r-30 min r-38 need cut and fit/ no access to master bedrm attic space provide or bat attic. 10/11/2002 9:18:18 AM
|
BLD-Wall cover | 10/10/2002 | 10/10/2002 | 10/10/2002 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/10/2002 at 08:18:25. Contact: . out of time 10/10/2002 7:44:33 PM
|
BLD-Framing/Rough-in | 10/9/2002 | 10/9/2002 | 10/9/2002 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 10/09/2002 at 06:50:31. Contact: . Prior c/n items completed including engineering on drag strut wall--ok to insulate. 10/9/2002 8:51:17 AM
|
BLD-Framing/Rough-in | 10/2/2002 | 10/3/2002 | 10/3/2002 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/02/2002 at 14:22:59. Contact: .no insp not ready need engineers feild report. c/n on site. 10/3/2002 11:23:32 AM
|
BLD-Other | 9/26/2002 | 9/26/2002 | 9/26/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 09/26/2002 at 08:15:49. Contact: .shear ok to cover ext 9/26/2002 4:19:26 PM
|
BLD-Other | 9/20/2002 | 9/23/2002 | 9/23/2002 | A | CANC |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 09/20/2002 at 15:15:25. Contact: . Cancelled by contractor--not ready. 9/23/2002 10:47:18 AM
|
BLD-Foundation | 8/1/2002 | 8/2/2002 | 8/2/2002 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 08/01/2002 at 15:53:09. Contact: ###-####. wip--95% ready--rebar in place. 8/2/2002 12:05:27 PM
|
BLD-Foundation | 8/1/2002 | 8/1/2002 | 8/1/2002 | P | PART |
Steven Webb
|
|
|
mike; Phone #: ###-####wip--footing not foundation-- 80% ready. 8/1/2002 4:22:36 PM
|
Issue PAID IN FULL permit | | | 7/19/2002 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/17/2002 | | DONE |
|
|
|
|
Telephone call | | | 7/17/2002 | | DONE |
|
|
|
permit ready and fees due
|
Plan assigned to (DJO) | 7/16/2002 | 7/16/2002 | 7/16/2002 | | PASS |
Dan Overy
|
|
|
7/16/2002 16:45:21 DJO - activity updated through activity BLDA022 from case BLD02-01607.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/16/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/16/2002 | | DONE |
|
|
|
|
Plan Review Report | | | 7/16/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 7/16/2002 | | |
|
|
|
|
Routing - PLANNING | 7/2/2002 | | 7/5/2002 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/5/2002 | | 7/5/2002 | | DONE |
|
|
|
|
Application received | | | 7/2/2002 | | |
|
|
|
|
Pending Assignment by DJO | 7/2/2002 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 7/5/2002 | | | | |
|
|
|
|