Permanent Occupancy | | | 7/17/2015 | | DONE |
|
|
|
|
Second Notice BLD | 7/13/2005 | 7/13/2005 | 7/20/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/6/2005 | 7/13/2005 | | DONE |
|
|
|
|
BLD-Final | 6/3/2005 | 6/6/2005 | 6/6/2005 | P | PASS |
Jim Sly
|
|
|
chip ###-#### call 1st before insp OK for Perm Occ. :)
|
FIRE-Final Inspection | 6/3/2005 | 6/6/2005 | 6/6/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
Permanent occupancy | | | 6/6/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10626 issued 6-6-05 to Idaho Self Storage, Bldg. G.
|
Print Occupancy Form | | | 6/3/2005 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 2/14/2003 | 2/14/2003 | 2/14/2003 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/14/2003 at 9:32:38 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/9/2003 | 1/9/2003 | 1/9/2003 | P | PART |
Jim Sly
|
|
|
rob--shear; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Shear OK. 1/9/2003 3:57:41 PM
|
BLD-Foundation | 11/4/2002 | 11/4/2002 | 11/4/2002 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung 90% found complete and OK. 11/4/2002 12:36:19 PM
|
BLD-Footing | 11/1/2002 | 11/1/2002 | 11/1/2002 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung OK pending MTI insp and appr. 11/1/2002 2:31:22 PM
|
(F) Reprint permit | | | 10/25/2002 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/24/2002 | | DONE |
|
|
|
|
BLD-Footing | 10/8/2002 | 10/8/2002 | 10/8/2002 | P | PASS |
Dave Hannah
|
|
|
|
Plan assigned to (JCM) | 7/9/2002 | | 9/4/2002 | | PASS |
John Menard
|
|
|
9/4/2002 10:58:23 JCM - activity updated through activity BLDA022 from case BLD02-01636.
|
Routing - PLAN CHECK | 9/3/2002 | | 9/4/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 9/4/2002 | | DONE |
|
|
|
|
Telephone call | | | 9/4/2002 | | DONE |
|
|
|
permit ready and need ACHD
|
Routing - PLANNING | 8/29/2002 | | 9/3/2002 | | PASS |
|
|
|
Approved per DRH02-125 and per revised landscape plans dated received 9/3/02.
|
Plan resubmittals received | | | 8/30/2002 | | DONE |
|
|
|
Received three copies of revised sheets A1.0, A2.0, A2.1, A2.2, A2.3, A2.4, A2.5, A6.0, M1.0, S0.1, S1.1, S1.2. One copy of response letter, four copies of structural design calculations. Routed to John M. kmm
|
Routing - PLANNING Land Div | 8/28/2002 | | 8/29/2002 | | PASS |
|
|
|
Ada Cty ROS 5844
|
Routing - FIRE | 8/27/2002 | | 8/28/2002 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 8/16/2002 | | 8/27/2002 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 8/27/2002 | | FAIL |
|
|
|
E-mailed tha architect of record a letter requesting additional revisions and clarifications. JCM
|
Plan resubmittals received | | | 8/22/2002 | | DONE |
|
|
|
Received three sets of resubmittal sheets A1.0, A1.2, A1.2, A2.0, A2.1, A2.2, A2.3, A2.4, A2.5, A5.0, A6.0, A7.0, E1.0, M1.0, S0.1, S1.1, S1.2, and five sets of resubmittal sheets C-1.0, C-1.1, C-1.2, C-2.0, C-3.0, C-4.0 with cover letter and transmittal. Routed to John Menard.
|
Routing - PUBLIC WORKS | 8/14/2002 | | 8/16/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/5/2002 | | 8/14/2002 | | |
|
|
|
|
Routing - PUBLIC WORKS | 8/2/2002 | | 8/5/2002 | | FAIL |
|
|
|
Drainage plan does not meet mimimun criteria established in Boise City Storm Water Design Manual. Per Brian M. kmm
|
Plan Review Completed(1st rev) | | | 8/2/2002 | | DONE |
|
|
|
|
Routing - FIRE | 7/30/2002 | | 8/2/2002 | | FAIL |
Bill Alexander
|
|
|
Require fire flow information ceritification (plus).
|
Plan resubmittals requested | | | 7/30/2002 | | FAIL |
|
|
|
Mailed the architect of record a copy of the comment list requesting revisions. JCM
|
Routing - PLAN CHECK | 7/23/2002 | | 7/30/2002 | | FAIL |
|
|
|
|
Routing - PLUMBING | 7/22/2002 | | 7/23/2002 | | PASS |
|
|
|
see attached
|
Routing - PLANNING | 7/16/2002 | | 7/22/2002 | | FAIL |
|
|
|
See bld02-01629
|
Routing - Erosion and Sediment | 7/15/2002 | | 7/16/2002 | | PASS |
|
|
|
ESC approved with conditions attached to plan
|
Routing - PUBLIC WORKS | 7/9/2002 | | 7/15/2002 | | FAIL |
|
|
|
|
Routing - PLANNING Land Div | 7/9/2002 | | 7/9/2002 | | FAIL |
|
|
|
need legal descriptions and deeds
|
Pending Assignment by JCM | 7/8/2002 | | 7/9/2002 | | DONE |
John Menard
|
|
|
7/9/2002 11:52:23 JCM - activity updated through activity BLDA166 from case BLD02-01636.
|
Plans ACCEPTED BY PLAN TECH | | | 7/8/2002 | | DONE |
|
|
|
Received (3) extra sets of Civil Drawings, Structural Calculations, and Drainage Calculations. Attached to Plans.
|
Override - Parcel Holds | | | 7/8/2002 | | |
|
|
|
|
Application received | | | 7/5/2002 | | |
|
|
|
|
Override - Parcel Holds | | | 7/5/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/5/2002 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/5/2002 | | HOLD |
|
|
|
Informed applicant that structural calculations, drainage calculations, and (3) extra copies of civil drawings are required before routing.
|
First Notice | | 7/27/2015 | | | |
|
|
|
|
Fee Review-notes | 7/5/2002 | 7/5/2002 | | | |
|
|
|
|