BLD-Aging Inspection | 1/22/2003 | 1/22/2003 | 1/22/2003 | | PASS |
Jim Storey
|
|
|
final ok 1/22/2003 8:27:35 AM
|
BLD-Final | 1/22/2003 | 1/22/2003 | 1/22/2003 | A | PASS |
Jim Storey
|
|
|
talked with rick jackson fire insp. aproved for final ok
|
DOC - Permit Finaled | 1/22/2003 | 1/22/2003 | 1/22/2003 | A | PASS |
Jim Storey
|
|
|
Finaled by inspector at 1/22/2003 8:28:54 AM
|
Issue PAID IN FULL permit | | | 8/19/2002 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 7/11/2002 | | 8/2/2002 | | PASS |
Jason Blais
|
|
|
8/2/2002 13:16:48 JCB - activity updated through activity BLDA022 from case BLD02-01678.
|
Routing - FIRE | 7/26/2002 | | 8/2/2002 | | FAIL |
Bill Alexander
|
|
|
Waiting response from Petco / Carolyn Glossner on commodity and commodity storage height verification, of which she did not address in the 07/22/2002 review?. (Called 07/29/2002 - 10:30am). Called 08/02/2002 - 8:50am, (Carolyn not in, left voice mail to responsd)
08/02/2002 - No response so returning plans to Plan Check
|
Routing - PLAN CHECK | 8/2/2002 | | 8/2/2002 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
Routing - FIRE | 8/2/2002 | | 8/2/2002 | | PASS |
Bill Alexander
|
|
|
Letter from Petco attached.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/2/2002 | | DONE |
|
|
|
|
Telephone call | | | 8/2/2002 | | DONE |
|
|
|
MESSAGE PERMIT READY AND FEES DUE
|
Routing - PLAN CHECK | 7/22/2002 | | 7/26/2002 | | PEND |
|
|
|
When approved by Fire Dept. permit can be issued. Plans routed to Fire Dept.
|
Plan resubmittals received | | | 7/26/2002 | | DONE |
|
|
|
Received two copies of resubmittal sheets F1 with comment letter. Routed to jason Blais.
|
Plan resubmittals received | | | 7/26/2002 | | DONE |
|
|
|
Received one copy of resubmittal sheet F1 with comments and transmittal. Routed to Jason Blais.
|
Routing - FIRE | 7/19/2002 | | 7/22/2002 | | FAIL |
Bill Alexander
|
|
|
Lack readable and detailed information on racks permitting. Lack commodity classes and storage heights/locations. All required to make a UFC review complete.
|
Plan Review Completed(1st rev) | | | 7/22/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/16/2002 | | 7/19/2002 | | FAIL |
|
|
|
Plan review report sent and faxed to engineer. Plan resubmittals and written response required for further review. Plans routed to Fire Dept.
|
Plan resubmittals requested | | | 7/19/2002 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Plans ACCEPTED BY PLAN TECH | | | 7/17/2002 | | DONE |
|
|
|
Received floor plan. Put with plans and routed to Jason. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 7/11/2002 | | FAIL |
|
|
|
Requires two copies of floor plans showing racking lay out and copy of application cover sheet. Have contacted Dale at ###-####. kmm
7/12/02 Received application cover letter from Carolyn Glossner. Still waiting for two copies of floor plans showing racking layout. KMM
7/16/02, am routing plans to Jason for formal wright up. kmm
|
First Notice | 7/10/2002 | 7/10/2002 | 7/10/2002 | | DONE |
|
|
|
|
Application received | | | 7/10/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/10/2002 | | DONE |
|
|
|
|
Plan routing begun/TENANTS | | | | | |
|
|
|
|