Fee Review-notes | 8/12/2003 | 8/12/2003 | 8/12/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Permanent occupancy | | | 12/10/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9468 issued 12-10-02 to Wings of Health.
|
Permanent Occupancy | | 12/6/2002 | 12/6/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/4/2002 | 12/6/2002 | 12/6/2002 | A | FAIL |
Troy Cobbley
|
|
|
no access to the building and I called the phone number three times 12/6/2002 8:45:03 AM
|
BLD-Final | 12/4/2002 | 12/6/2002 | 12/6/2002 | P | PASS |
Steven Webb
|
|
|
###-####
|
FIRE-Final Inspection | 12/6/2002 | 12/6/2002 | 12/6/2002 | P | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 12/6/2002 1:19:47 PM
|
FIRE-Final Inspection | 10/24/2002 | 10/25/2002 | 10/25/2002 | A | FAIL |
Troy Cobbley
|
|
|
door hardware still not right 10/25/2002 4:29:42 PM
|
FIRE-Final Inspection | 10/18/2002 | 10/21/2002 | 10/21/2002 | A | FAIL |
Troy Cobbley
|
|
|
repair exit sign, rovide approved door hardware, provide "cfm" rating for the hvac system for possible automatic shutdown requirements, provide fire extinguisher 10/21/2002 3:59:15 PM
|
BLD-Final | 10/17/2002 | 10/18/2002 | 10/18/2002 | P | CANC |
Tom Arcoraci
|
|
|
late am ###-####
|
BLD-Framing/Rough-in | 9/16/2002 | 9/16/2002 | 9/16/2002 | P | PART |
Tom Arcoraci
|
|
|
###-#### pending elec ok 9/16/2002 4:02:14 PM
|
Issue PAID IN FULL permit | | | 9/4/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/9/2002 | | 8/30/2002 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
Plan assigned to (JCB) | 7/26/2002 | | 8/30/2002 | | PASS |
Jason Blais
|
|
|
8/30/2002 10:58:06 JCB - activity updated through activity BLDA022 from case BLD02-01764.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/30/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/30/2002 | | DONE |
|
|
|
|
Telephone call | | | 8/30/2002 | | DONE |
|
|
|
PERMIT READY AND FEES DUE
|
Plan resubmittals received | | | 8/27/2002 | | DONE |
|
|
|
Received three copies of revised sheetsA1.0, A2.0. One copy of correction letter. Routed to Jason B. kmm
|
Routing - FIRE | 8/7/2002 | | 8/9/2002 | | PASS |
|
|
|
approved without written comment
|
Plan Review Completed(1st rev) | | | 8/9/2002 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 8/7/2002 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 8/5/2002 | | 8/6/2002 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept. for review.
|
Routing - PLUMBING | 7/29/2002 | | 8/5/2002 | | PASS |
|
|
|
provide water heater and sauna t&p drainage to an approved floor sink, additional cross connection protection may be required.
|
Routing - PUBLIC WORKS | 7/26/2002 | | 7/29/2002 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 7/29/2002 | | DONE |
|
|
|
PARTIAL PERMIT issued at the request of the contractor.
|
Plans ACCEPTED BY PLAN TECH | | | 7/22/2002 | | DONE |
|
|
|
|
First Notice | 7/19/2002 | 7/19/2002 | 7/19/2002 | | DONE |
|
|
|
|
Application received | | | 7/19/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/19/2002 | | DONE |
|
|
|
|