BLD-Final | 1/15/2003 | 1/15/2003 | 1/15/2003 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/15/2003 at 08:11:48. Contact: . c.c # 22622issued 1/15/2003 2:08:11 PM
|
DOC - Permit Finaled | 1/15/2003 | 1/15/2003 | 1/15/2003 | P | PASS |
Dave Hannah
|
|
|
Finaled by inspector at 1/15/2003 2:25:25 PM
|
BLD-Wall cover | 11/4/2002 | 11/4/2002 | 11/4/2002 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/04/2002 at 06:53:37. Contact: .
|
BLD-Energy code compliance | 11/4/2002 | 11/4/2002 | 11/4/2002 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 10/28/2002 | 10/29/2002 | 10/29/2002 | A | PASS |
Dave Hannah
|
|
|
###-#### meet terry on site he had letters from truss comp and strut engin on all repairs and changes all ok ok insulate 10/29/2002 10:01:27 AM
|
BLD-Framing/Rough-in | 10/24/2002 | 10/25/2002 | 10/25/2002 | A | CANC |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 10/24/2002 at 15:26:50. Contact: . Cancelled by contractor--not ready. 10/25/2002 8:25:22 AM
|
BLD-Framing/Rough-in | 10/25/2002 | 10/25/2002 | 10/25/2002 | P | NR |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 10/25/2002 at 08:54:37. Contact: . Still not complete set of plans. 10/25/2002 3:44:36 PM
|
BLD-Framing/Rough-in | 10/23/2002 | 10/24/2002 | 10/24/2002 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/23/2002 at 14:52:13. Contact: . no truss eng on site 10/24/2002 1:48:40 PM
|
BLD-Framing/Rough-in | 10/8/2002 | 10/8/2002 | 10/8/2002 | P | PART |
Tom Arcoraci
|
|
|
sheer panel ###-#### dustin 10/8/2002 2:40:41 PM
|
BLD-Other | 10/4/2002 | 10/7/2002 | 10/7/2002 | A | FAIL |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 10/04/2002 at 12:05:14. Contact: ###-####. SHEER PANEL INSPECT C/N posted--Many items not completed. 10/7/2002 10:58:17 AM
|
BLD-Other | 10/7/2002 | 10/7/2002 | 10/7/2002 | P | NR |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 10/07/2002 at 10:40:05. Contact: .
|
BLD-Foundation | 8/20/2002 | 8/21/2002 | 8/21/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 08/20/2002 at 16:41:36. Contact: ###-####.work in progress 65% completed 8/21/2002 11:33:42 AM
|
BLD-Footing | 8/19/2002 | 8/20/2002 | 8/20/2002 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 08/19/2002 at 17:11:28. Contact: ###-####. wip--80% ready. 8/20/2002 11:45:30 AM
|
Issue PAID IN FULL permit | | | 8/8/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/24/2002 | | 8/1/2002 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 7/31/2002 | | 8/1/2002 | | PASS |
|
|
|
8/1/2002 08:16:51 RMH - activity updated through activity BLDA022 from case BLD02-01779.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/1/2002 | | DONE |
|
|
|
|
Telephone call | | | 8/1/2002 | | DONE |
|
|
|
permit ready and fees due
|
Case Summary (BLD) | | | 7/31/2002 | | DONE |
|
|
|
|
Plan Review Report | | | 7/31/2002 | | DONE |
|
|
|
|
Pending Assignment by DJO | 7/23/2002 | | 7/31/2002 | | DONE |
Dan Overy
|
|
|
7/31/2002 10:29:15 SAM - activity updated through activity BLDA175 from case BLD02-01779.
|
Routing - PUBLIC WORKS | 7/23/2002 | | 7/24/2002 | | PASS |
|
|
|
|
Application received | | | 7/23/2002 | | |
|
|
|
|
Routing - PLANNING | 7/23/2002 | | 7/23/2002 | | PASS |
|
|
|
|