Permit Information
Permit NumberBLD02-01844
StatusFinaled
Name AVEST LIMITED PARTNERSHIP
Site Address 9632 W EMERALD ST
Project NameEMERALD IND CONDOS
Customer Number 
ePlanReviewNo
Description
(ANDERSON CHIROPRACTIC) To construct a 2,984 sq.ft. chiropractic office in the south end of the structure per approved plans on file. Work to include, construction of interior partitions creating exam rooms, offices, breakroom, warehouse storage area, reception area, two accessible restrooms, an X-Ray room & rehab room, Installation of a new suspended ceiling system and miscelaneous related interior finishes. (pc#478-02) rmh
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent occupancy UNPAID FEE  10/22/2002 DONE
Perm. Occ. Cert. #9412 issued 10-22-02 to Anderson Chiropractic.
Permanent Occupancy 10/18/200210/18/2002 DONE
Details
BLD-Final10/17/200210/18/200210/18/2002APASS
DetailsRuss Owen
###-#### This job only needed all other req signatures for a final oc, if done ok for a perm oc. Contractor and records indicate that this is done.10/18/2002 10:48:21 AM 10/18/2002 10:48:44 AM
FIRE-Final Inspection9/27/20029/30/20029/30/2002APASS
DetailsTroy Cobbley
fire life/safety finaled 9/30/2002 8:31:58 AM
BLD-Final9/27/20029/30/20029/30/2002APART
DetailsRuss Owen
temp only \\###-####ok temp. 9/30/2002 5:02:32 PM
Temporary occupancy  9/30/2002 DONE
Temp. Occ. Cert. #4869 issued 9-30-02 to Anderson Chiropractic.
FIRE-Final Inspection9/26/20029/27/20029/27/2002AFAIL
DetailsTroy Cobbley
contractor needs to install remote led/reset for the three duct smoke detectors. door hardware not installed yet 9/27/2002 12:59:20 PM
BLD-Wall cover9/20/20029/23/20029/23/2002APASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 09/20/2002 at 18:08:34. Contact: ###-####.grid ceiling. 9/23/2002 1:02:04 PM
BLD-Framing/Rough-in9/13/20029/13/20029/13/2002APART
DetailsRuss Owen
working on repairs , will re-inspect. 9/13/2002 11:40:11 AM
BLD-Framing/Rough-in9/13/20029/13/20029/13/2002PPASS
DetailsRuss Owen
BLD-Framing/Rough-in9/11/20029/12/20029/12/2002AFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 09/11/2002 at 17:21:10. Contact: ###-####. Sheetrocking with out approval. Posted a stop work notice. 9/13/2002 9:41:06 AM
BLD-Conference9/11/20029/12/20029/12/2002ACANC
DetailsRuss Owen
Scheduled by a contractor via Hello! on 09/11/2002 at 17:21:46. Contact: ###-####.
BLD-Conference9/12/20029/12/20029/12/2002PPART
DetailsRuss Owen
Meet with Steed (Jim -Odie, myself and Jim Story, to go over framing corrections contractor willcomplete all nessasary work and recall. 9/13/2002 9:42:25 AM
BLD-Framing/Rough-in9/10/20029/11/20029/11/2002PFAIL
DetailsRuss Owen
jim; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung. walls need to braceing. 9/11/2002 4:34:35 PM
BLD-Framing/Rough-in9/6/20029/9/20029/9/2002APART
DetailsJim Sly
###-#### OK to cover Ext walls. 9/9/2002 10:12:31 AM
BLD-Framing/Rough-in9/3/20029/4/20029/4/2002APART
DetailsRuss Owen
jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
Issue PAID IN FULL permit  8/27/2002 DONE
Plan assigned to (R_H)8/2/2002 8/26/2002 DONE
Details
Routing - PLAN CHECK8/21/2002 8/26/2002 DONE
PLANS/APPL TAKEN TO FRONT DESK  8/26/2002 PASS
Inspection Record Card- Bld  8/26/2002 DONE
Print Occupancy Form  8/26/2002 DONE
Telephone call  8/26/2002 DONE
PERMIT READY AND FEES DUE
Routing - FIRE8/19/2002 8/21/2002 PASS
approved without written comment
Plan Review Completed(1st rev)  8/21/2002 FAIL
Routing - PLUMBING8/15/2002 8/19/2002 PASS
Routing - PUBLIC WORKS8/15/2002 8/15/2002 PASS
Routing - PLAN CHECK8/8/2002 8/15/2002  
Additional plans submitted  8/14/2002 DONE
Received two copies of additional sheets M0.0, M1.0, P0.0, P1.0, P1.1, P2.0, E1.1, E2.1. Routed to Ron Hill.
Routing - PLUMBING8/5/2002 8/7/2002 FAIL
please provide a complete plumbing plan showing the above listed items
Routing - PUBLIC WORKS8/2/2002 8/5/2002 FAIL
Need to supply plumbing plans to public works for review
First Notice7/31/20027/31/20027/31/2002 DONE
Plans ACCEPTED BY PLAN TECH  7/31/2002 DONE
1. Informed applicant that plumbing schematic might be required.
Application received  7/31/2002  
Recd Pcfee & Taken To Pln CK  7/31/2002 DONE