BLD-Final | 11/25/2002 | 11/26/2002 | 11/26/2002 | A | PASS |
Carl Dependahl
|
|
|
JUST NEEDS DOC FINAL
|
DOC - Permit Finaled | 11/26/2002 | 11/26/2002 | 11/26/2002 | P | PASS |
Carl Dependahl
|
|
|
Finaled by inspector at 11/26/2002 1:23:03 PM
|
Letter of compliance | | | 11/7/2002 | | DONE |
|
|
|
Letter of Compliance #22765 issued 11-7-02.
|
FIRE-Final Inspection | 10/30/2002 | 10/31/2002 | 10/31/2002 | A | PASS |
Rick Jackson
|
|
|
dave ###-####
|
BLD-Final | 10/30/2002 | 10/31/2002 | 10/31/2002 | P | PASS |
Carl Dependahl
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
BLD-Conference | 10/29/2002 | 10/30/2002 | 10/30/2002 | A | PASS |
Carl Dependahl
|
|
|
dave-for each insp -suite 225 , 250 , 251 , 252, 253, 254, 255, 256, 257 ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Conference | 10/21/2002 | 10/21/2002 | 10/21/2002 | P | PASS |
Carl Dependahl
|
|
|
###-#### refuge area sign ok w/ ext emergency illumination ...to 5 foot candles. 10/21/02 4:02:54 PM
|
BLD-Conference | 10/17/2002 | 10/18/2002 | 10/18/2002 | A | PASS |
Carl Dependahl
|
|
|
###-#### DAVE ...glass block detail ok 10/18/02 1:50:00 PM
|
BLD-Framing/Rough-in | 10/7/2002 | 10/8/2002 | 10/8/2002 | A | PART |
Carl Dependahl
|
|
|
###-#### dave... wall/glass assy. at corr. wall ok to continue. 10/8/02 11:46:57 AM
|
BLD-Framing/Rough-in | 9/19/2002 | 9/20/2002 | 9/20/2002 | A | PART |
Tom Arcoraci
|
|
|
dave; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok to cover walls 9/20/2002 9:53:31 AM
|
(F) Reprint permit | | | 9/9/2002 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/6/2002 | | DONE |
|
|
|
|
Routing - FIRE | 8/26/2002 | | 8/27/2002 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 8/9/2002 | | 8/27/2002 | | PASS |
Jason Blais
|
|
|
8/27/2002 10:50:51 JCB - activity updated through activity BLDA022 from case BLD02-01902.
|
Plan Review Completed(1st rev) | | | 8/27/2002 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/27/2002 | | 8/27/2002 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/27/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/27/2002 | | DONE |
|
|
|
|
Telephone call | | | 8/27/2002 | | DONE |
|
|
|
permit ready
|
Routing - PLAN CHECK | 8/15/2002 | | 8/26/2002 | | PEND |
|
|
|
Plan review report sent and faxed to architect. No response required. When approved by Fire Dept. permit can be issued. Plans routed to Fire Dept.
|
Plan resubmittals received | | | 8/21/2002 | | DONE |
|
|
|
Received two copies of revised sheets A1.1 of 3, A1.2 of 3 and A1.3 of 3. Routed to Jason B. kmm
|
Routing - PLANNING | 8/14/2002 | | 8/15/2002 | | PASS |
|
|
|
Approved.
|
Routing - PLAN CHECK | 8/13/2002 | | 8/14/2002 | | FAIL |
|
|
|
Called architect and let them know of some issues needing to be addressed and new plans to be provided. Plans on hold until new sheets provided.
|
Routing - PLAN CHECK | 8/14/2002 | | 8/14/2002 | | FAIL |
|
|
|
Plans to route to Planning for approval of new exterior windows.
|
Telephone call | | | 8/14/2002 | | DONE |
|
|
|
Called architect and went over some issues needing to be addressed and new plan sheets needing to be provided.
|
Plan resubmittals requested | | | 8/14/2002 | | |
|
|
|
Resubmittal plan sheets need to be submitted.
|
Routing - PUBLIC WORKS | 8/9/2002 | | 8/13/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/8/2002 | | |
|
|
|
|
First Notice | 8/7/2002 | 8/7/2002 | 8/7/2002 | | DONE |
|
|
|
|
Application received | | | 8/7/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/7/2002 | | DONE |
|
|
|
|