Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 7/28/2003 | 4/26/2005 | | DONE |
|
|
|
|
DOC - Permit Finaled | 7/28/2003 | 7/28/2003 | 7/28/2003 | A | PASS |
Jim Storey
|
|
|
Finaled by inspector at 7/28/2003 11:26:22 AM
|
BLD-Aging Inspection | 7/28/2003 | 7/28/2003 | 7/28/2003 | | PASS |
Jim Storey
|
|
|
|
Code Occupancy Approval | 5/27/2003 | 5/27/2003 | 5/27/2003 | P | PASS |
Wm. Michael Meloy
|
|
|
Inspection noted compliance met. 5/27/2003 3:10:37 PM
|
PubWorks Occupancy Approval | 5/26/2003 | 5/26/2003 | 5/26/2003 | | DONE |
|
|
|
Drainage project complete, issued final acceptance 5/26/03. D.Erskine
|
BLD-Aging Inspection | 4/22/2003 | 4/22/2003 | 4/22/2003 | | PASS |
Jim Storey
|
|
|
wip 4/22/2003 8:12:59 AM
|
BLD-Footing | 10/5/2002 | 10/7/2002 | 10/7/2002 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/05/2002 at 17:27:06. Contact: ###-####.center peir pads and thichened ft to be covered by mti pending report. 10/7/2002 3:21:02 PM
|
Inspection Record Card- Bld | | | 9/24/2002 | | DONE |
|
|
|
|
Telephone call | | | 9/24/2002 | | DONE |
|
|
|
permit ready
|
Issue PAID IN FULL permit | | | 9/24/2002 | | DONE |
|
|
|
|
Plan assigned to (KMM) | 8/8/2002 | | 9/23/2002 | | PASS |
Kathy Miller
|
|
|
9/23/2002 12:45:41 KMM - activity updated through activity BLDA022 from case BLD02-01917.
|
Routing - PUBLIC WORKS | 9/18/2002 | | 9/23/2002 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/23/2002 | | 9/23/2002 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/23/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/23/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/4/2002 | | 9/18/2002 | | |
|
|
|
Placed plans in hold box until information is received for Brian Murphy.
|
Routing - PUBLIC WORKS | 9/3/2002 | | 9/4/2002 | | FAIL |
|
|
|
Requires drainage plan revision and ACHD letter per Brian Murphy.
|
Routing - PLAN CHECK | 8/29/2002 | | 9/3/2002 | | |
|
|
|
|
Routing - PLAN CHECK | 8/21/2002 | | 8/29/2002 | | HOLD |
|
|
|
plans in hold box waiting re-review by PW. kmm
|
Routing - Erosion and Sediment | 8/29/2002 | | 8/29/2002 | | PASS |
|
|
|
ESC Plan approved with condtions attached to drawings.
|
Plan resubmittals received | | | 8/29/2002 | | DONE |
|
|
|
Received three copies of revised Storm Water Pollution Prevention Plan. Put with plans and re-routed to ESC. kmm
|
Routing - FIRE | 8/19/2002 | | 8/21/2002 | | PASS |
|
|
|
approved without written comment
|
Routing - PLANNING | 8/15/2002 | | 8/16/2002 | | PASS |
|
|
|
Approved per DRH02-70.
|
Routing - Erosion and Sediment | 8/14/2002 | | 8/15/2002 | | FAIL |
|
|
|
No Construction Site Inpsection Check list included in Narrative Plan.See Appendix "A" and "C" in plan designer manual for requirements. Contacted Vaughn Thurgood, American Geo-Technics on 8/15 concerning problesm
|
Routing - PUBLIC WORKS | 8/9/2002 | | 8/14/2002 | | FAIL |
|
|
|
Requires Drainage Plan Revision and ACHD Letter.
|
Plan routing begun/NEW & ADDTN | | | 8/8/2002 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 8/8/2002 | | 8/8/2002 | | PASS |
|
|
|
|
Application received | | | 8/8/2002 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/8/2002 | | DONE |
|
|
|
|
Routing - PLUMBING | 8/16/2002 | | 8/19/2001 | | PASS |
|
|
|
provide a vent for the pump chamber, pumps must be grinder pumps.
|