BLD-Final | 10/22/2002 | 10/24/2002 | 10/24/2002 | P | PASS |
Tom Arcoraci
|
|
|
###-####
|
DOC - Permit Finaled | 10/24/2002 | 10/24/2002 | 10/24/2002 | P | PASS |
Tom Arcoraci
|
|
|
Finaled by inspector at 10/24/2002 4:43:34 PM
|
BLD-Final | 10/21/2002 | 10/22/2002 | 10/22/2002 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/21/2002 at 11:45:51. Contact: ###-####.
|
BLD-Footing | 9/6/2002 | 9/6/2002 | 9/6/2002 | P | PART |
Carl Dependahl
|
|
|
###-#### donny...rec' stamped eng' 9/6/2002 4:03:17 PM letter:native soils ok for concrete 9/6/2002 4:04:47 PM, need spec. insp/testing for remainder of concrete & welding operations; existing glu-lams to be observed/approved for integrity. Seal/flash all ends of lumber. 9/6/2002 4:06:45 PM
|
Issue PAID IN FULL permit | | | 9/4/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/4/2002 | | |
|
|
|
|
Routing - Erosion and Sediment | 8/28/2002 | | 8/29/2002 | | PASS |
|
|
|
ESC plan approved with conditions attached to drawings.
|
Routing - PLAN CHECK | 8/29/2002 | | 8/29/2002 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/29/2002 | | DONE |
|
|
|
|
Telephone call | | | 8/29/2002 | | DONE |
|
|
|
PERMIT READY AND FEES DUE
|
Plan assigned to (JCB) | 8/12/2002 | | 8/29/2002 | | PASS |
Jason Blais
|
|
|
8/29/2002 12:12:03 JCB - activity updated through activity BLDA022 from case BLD02-01934.
|
Routing - PLAN CHECK | 8/15/2002 | | 8/28/2002 | | PEND |
|
|
|
Permit approval pending approval from Erosion/Sediment Control department. Erosion and Sediment Control plan provided and to route to that department.
|
Additional plans submitted | | | 8/28/2002 | | DONE |
|
|
|
Received two copies of ESC Plan signed by Cert. Plan Designer and one copy of cover letter, ESC application and ESC narrative. Routed to Jason B. kmm
|
Plan resubmittals received | | | 8/26/2002 | | DONE |
|
|
|
Received three sets of resubmittal sheets A-1 with structural calculations and cover letter. Routed to Jason Blais.
|
Routing - PLAN CHECK | 8/14/2002 | | 8/15/2002 | | FAIL |
|
|
|
Plan review report sent to architect. Response required.
|
Routing - Erosion and Sediment | 8/13/2002 | | 8/14/2002 | | FAIL |
|
|
|
No ESC plan submitted for review.
|
Routing - PLANNING | 8/12/2002 | | 8/13/2002 | | PASS |
|
|
|
Approved per building permit plans.
|
First Notice | 8/9/2002 | 8/9/2002 | 8/9/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/9/2002 | | DONE |
|
|
|
1. Informed applicant that two copies of an ESC prepared plan with narrative will be required. He will call Strata or EHM Engineers asap to get this done.
2. Accept plans, no key/vicinity map required. Per Jason Blais.
|
Application received | | | 8/9/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/9/2002 | | |
|
|
|
|