BLD-Final | 3/3/2003 | 3/4/2003 | 3/4/2003 | P | PASS |
Dave Hannah
|
|
|
###-#### call for access c.c # 23789 issued 3/4/2003 1:43:04 PM
|
DOC - Permit Finaled | 3/4/2003 | 3/4/2003 | 3/4/2003 | P | PASS |
Dave Hannah
|
|
|
Finaled by inspector at 3/4/2003 1:43:07 PM
|
BLD-Final | 2/28/2003 | 3/3/2003 | 3/3/2003 | A | FAIL |
Dave Hannah
|
|
|
###-#### access code 193 c/n on site 3/3/2003 9:46:24 AM
|
BLD-Energy code compliance | 12/16/2002 | 12/17/2002 | 12/17/2002 | A | PASS |
Dave Hannah
|
|
|
TERRY; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok to cover 12/17/2002 9:08:19 AM
|
BLD-Framing/Rough-in | 12/11/2002 | 12/12/2002 | 12/12/2002 | A | PASS |
Dave Hannah
|
|
|
###-#### TERRY
|
BLD-Framing/Rough-in | 12/9/2002 | 12/10/2002 | 12/10/2002 | A | NR |
Dave Hannah
|
|
|
terry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 12/10/2002 | 12/10/2002 | 12/10/2002 | P | FAIL |
Dave Hannah
|
|
|
c/n on site ok to insulate 12/10/2002 3:28:58 PM
|
BLD-Framing/Rough-in | 12/9/2002 | 12/9/2002 | 12/9/2002 | P | FAIL |
Dave Hannah
|
|
|
###-#### terry needs to have foam seal package installed befor calling for framing insp no inspection done at this time 12/9/2002 1:52:00 PM
|
BLD-Framing/Rough-in | 11/22/2002 | 11/22/2002 | 11/22/2002 | P | PART |
Dave Hannah
|
|
|
shear ok to cover ext
|
BLD-Framing/Rough-in | 11/13/2002 | 11/14/2002 | 11/14/2002 | P | FAIL |
Dave Hannah
|
|
|
###-#### hold downs under windows some panels note blocked some areas need to be restapled need engineering on hold donws and area that wall line was changed also needs to finish roof 11/14/2002 2:52:39 PM
|
BLD-Foundation | 9/9/2002 | 9/10/2002 | 9/10/2002 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/09/2002 at 08:59:44. Contact: ###-####.rebar in place no panels in place. 9/10/2002 10:20:08 AM
|
BLD-Footing | 9/9/2002 | 9/9/2002 | 9/9/2002 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/09/2002 at 08:59:07. Contact: ###-####. wip ok 9/9/2002 2:07:35 PM
|
Plan assigned to (PEP) | 8/27/2002 | | 8/28/2002 | | PASS |
Perry Paine
|
|
|
8/28/2002 11:10:00 PEP - activity updated through activity BLDA022 from case BLD02-01945.
|
Plan Review Report | | | 8/28/2002 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/28/2002 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/28/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/28/2002 | | DONE |
|
|
|
|
Telephone call | | | 8/28/2002 | | DONE |
|
|
|
permit ready and fees due
|
Issue PAID IN FULL permit | | | 8/28/2002 | | DONE |
|
|
|
|
Pending Assignment by DJO | 8/12/2002 | | 8/27/2002 | | DONE |
Dan Overy
|
|
|
8/27/2002 09:32:54 PEP - activity updated through activity BLDA176 from case BLD02-01945.
|
Routing - PUBLIC WORKS | 8/19/2002 | | 8/20/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 8/19/2002 | | 8/19/2002 | | PASS |
|
|
|
Setbacks/site plan approved. Treat front door/garage elevation as front on this flag lot. AKT
|
Routing - PLANNING | 8/12/2002 | | 8/13/2002 | | FAIL |
|
|
|
Notified Scott of: Width of drive in front setback, front/side vs. rear incorrect, front door etc. Many problems with determination of appropriate setbacks. Please contact Angela for specifics. AKT
|
Application received | | | 8/12/2002 | | |
|
|
|
|
Routing - PLAN CHECK | 8/20/2002 | | | | |
|
|
|
|