Permit NumberBLD02-01947
StatusFinaled
Name HEWLETT-PACKARD CO
Site Address 11311 W CHINDEN BLVD
Project NameHP-Chiller Building Addition
Customer Number 
ePlanReviewNo
Description
(CHILLER BUILDING ADDITION) (Serving HP# NPCR Expansion, Phase II, Package II, Building #6, BLD02-01682) To construct a 14,431 sq. ft. addition to an existing 4,680 sq. ft. Chiller Building for a total of 19,111 sq. ft. THIS BUILDING IS REVIEWED AS A STAND ALONE FACILITY AND IS NOT SPRINKLERED. Construction to include reinforced concrete footings, foundations; CMU, solid grouted, reinforced screen walls and roof support wall structure; non-combustible roof system over electrical & pump rooms; a 'Class "A" Roof Covering System and non-bearing, non-combustible wall framing with sheetrock covering within the roofed areas. To provide electrical, mechanical & plumbing systems per tenant needs to comply with current building codes. PC#02-441/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes8/12/20038/12/20038/12/2003 DONE
(F) Reprint permit  5/6/2003 DONE
Permanent occupancy  1/13/2003 DONE
Perm. Occ. Cert. #9527 issued 1-13-03 to Hewlett Packard, Bldg. #6 chiller addn.
BLD-Final1/9/20031/10/20031/10/2003PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 01/09/2003 at 09:57:00. Contact: ###-####. OK for Perm. 1/10/2003 3:55:25 PM
Permanent Occupancy 1/10/20031/10/2003 DONE
Details
FIRE-Final Inspection1/7/20031/9/20031/9/2003APASS
DetailsTroy Cobbley
fire life safety finaled 1/9/2003 1:36:47 PM
BLD-Framing/Rough-in11/26/200211/26/200211/26/2002PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 11/26/2002 at 11:00:25. Contact: ###-####.
Issue PAID IN FULL permit  8/27/2002 DONE
Inspection Record Card- Bld  8/21/2002 DONE
Print Occupancy Form  8/21/2002 DONE
Telephone call  8/21/2002 DONE
Plan assigned to (DRS)7/6/20027/6/20028/20/2002 PASS
DetailsDan Stuart
8/20/2002 15:42:19 DRS - activity updated through activity BLDA022 from case BLD02-01947.
Routing - PLANNING8/16/2002 8/20/2002 PASS
Approved under DRH02-126.
Routing - PLAN CHECK8/20/2002 8/20/2002 PASS
Approved as noted and attached plan review comments & conditions.
PLANS/APPL TAKEN TO FRONT DESK  8/20/2002 PASS
To permit desk for issue.
Routing - FIRE8/12/2002 8/16/2002 PASS
Routing - Erosion and Sediment8/12/2002 8/13/2002 PASS
Resubmittals received 7/28/02 for ESC plan and routed to Jim Rogers on 8/12/02
ESC plan approved with conditions attached to drawings.
Routing - PLAN CHECK8/12/2002 8/12/2002 PEND
Routing to planning for review and approval
Application received  8/12/2002  
Telephone call  8/12/2002 DONE
DetailsDan Stuart
This is a new addition to an existing 4,680 sq. ft. structure. This building is declarted to be unsprinklered and will therefore be considered a separate facility from the other areas. I explained this to Tom Brophy and he said he would get with the contractor to provide correct application and C.V. values.
Telephone call  8/12/2002 DONE
Call to Tom Brophy concerning need for separate applications and permits for two projects. Can use same plan for both but one facility is sprinklered and the other isn't and both are stand alone structure's.
Routing - PLUMBING7/22/2002 8/6/2002 PASS
Plans approved as part of BLD02-01682 for HP#6 - NPCR expansion. Separate building permit created as the chiller room will not be sprinklered and is not a part of HP#6.
Routing - PUBLIC WORKS7/18/2002 7/22/2002 PASS
This plan was reviewed and approved in conjunction with BLD02-01682, HP#6 - NPCR expansion.
Routing - PLANNING Land Div7/12/2002 7/16/2002 PASS
Plan was routed and approved as part of BLD02-01682 for HP#6 - NPCR expansion. A separate building permit is required for each project.