Permanent occupancy | | | 3/6/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9578 issued 3-6-03 to CSDI Investments, LLC.
|
Permanent Occupancy | | 3/5/2003 | 3/5/2003 | | DONE |
|
|
|
|
BLD-Final | 3/5/2003 | 3/5/2003 | 3/5/2003 | P | PART |
Jim Storey
|
|
|
MIKE; Phone #: ###-#### Internet Inspection Request from: Darla Downs c/n made ok for final pending all others done. 3/5/2003 2:46:39 PM
|
Temporary occupancy | | | 2/24/2003 | | DONE |
|
|
|
Temp. Occ. Cert. #4918 issued 2-20-03 to CSDI Construction, Inc.
|
BLD-Final | 2/19/2003 | 2/20/2003 | 2/20/2003 | A | PART |
Jim Storey
|
|
|
###-#### mike ###-#### mike tenp ok need mech and reinsp for glazing in doors/ visqueen on walls to meet sm/flame. 2/20/2003 3:52:50 PM
|
PubWorks Occupancy Approval | 2/19/2003 | 2/19/2003 | 2/19/2003 | | DONE |
|
|
|
Found complete, signed permanent occupancy 02/19/03. G.Fitts
|
FIRE-Final Inspection | 2/18/2003 | 2/19/2003 | 2/19/2003 | P | PASS |
Rick Jackson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Code Occupancy Approval | | | 2/18/2003 | | PASS |
|
|
|
ALL IN AS REQUIRED UNDER DRH02-00096 FINAL SIGNED OFF.
|
FIRE-Final Inspection | 2/14/2003 | 2/14/2003 | 2/14/2003 | P | FAIL |
Rick Jackson
|
|
|
###-#### not ready for final; need exit signs installed, address, extinguishers and detectors on AHU's as it is a common plenum for three AHU's 2/14/2003 1:48:50 PM
|
BLD-Framing/Rough-in | 2/10/2003 | 2/11/2003 | 2/11/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 2/10/2003 at 10:10:35 AM. Contact: ###-####.ceilling ok pending ele. 2/11/2003 11:31:31 AM
|
BLD-Framing/Rough-in | 1/11/2003 | 1/13/2003 | 1/13/2003 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/11/2003 at 07:58:32. Contact: ###-####.walls ok 1/13/2003 2:17:19 PM
|
BLD-Framing/Rough-in | 1/6/2003 | 1/6/2003 | 1/6/2003 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/06/2003 at 08:48:08. Contact: ###-####. ceilling ok to gyp. 1/6/2003 5:15:13 PM
|
BLD-Wall cover | 12/13/2002 | 12/13/2002 | 12/13/2002 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/13/2002 at 09:07:07. Contact: ###-####.
|
BLD-Foundation | 11/1/2002 | 11/4/2002 | 11/4/2002 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung wall rbar ok still need compaction report for fill under ft. 11/4/2002 9:37:30 AM
|
BLD-Foundation | 10/30/2002 | 10/31/2002 | 10/31/2002 | A | PART |
Jim Storey
|
|
|
mark; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie interior ft ok for cover stil need soil compacktion report. 10/31/2002 9:18:08 AM
|
BLD-Footing | 10/25/2002 | 10/28/2002 | 10/28/2002 | A | PART |
Jim Storey
|
|
|
###-#### robert need soil compaction test for fill under footings. rebar ok / ok to pour pending approval results from soil report. 10/28/2002 9:09:35 AM
|
(F) Reprint permit | | | 10/22/2002 | | |
|
|
|
|
(F) Reprint permit | | | 10/22/2002 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/21/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/18/2002 | | |
|
|
|
|
Print Occupancy Form | | | 10/18/2002 | | |
|
|
|
|
Telephone call | | | 10/18/2002 | | DONE |
|
|
|
talked to connie to verify that plans are ready
|
Routing Off Site - STRUCTURAL | 10/7/2002 | | 10/17/2002 | | PASS |
|
|
|
Contacted PDQ to take resubmitted plans of 10/4/02. KMM Verbal approval by phone from Jan. W. MLO
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/17/2002 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 8/13/2002 | | 10/17/2002 | | PASS |
Mike Otto
|
|
|
10/17/2002 15:15:27 MLO - activity updated through activity BLDA022 from case BLD02-01958.
|
Routing - FIRE | 10/1/2002 | | 10/4/2002 | | PASS |
|
|
|
review request for complete building instead of shell and core
|
Plan resubmittals received | | | 10/4/2002 | | DONE |
|
|
|
Received three copies of resubmittal sheet S1.1 with Wall panel design, structural calculations, and cover letters. Routed to Mike Otto.
|
Routing Off Site - STRUCTURAL | 10/4/2002 | | 10/4/2002 | | FAIL |
|
|
|
resubmittals incomplete. Information on wall panels has no engineers stamps and letter from designing engineer states wall panels not in scope of work. Connie St. George contacted on 10-4-2002. This information was requested in two comments lists from the reviewing structural engineer.
|
Plan resubmittals received | | | 10/4/2002 | | DONE |
|
|
|
Received two copies of wall panel connection. routed to mike otto.
|
Plan resubmittals requested | | | 10/2/2002 | | DONE |
|
|
|
structural corrections
|
Routing Off Site - STRUCTURAL | 9/20/2002 | | 10/2/2002 | | FAIL |
|
|
|
Called pdq to send resubmittals to outside engineering. dkl Corrections faxed and mailed to architect. MLO
|
Routing - PUBLIC WORKS | 10/1/2002 | | 10/1/2002 | | PASS |
|
|
|
|
Routing - PLUMBING | 9/27/2002 | | 9/30/2002 | | PASS |
|
|
|
1. building sewer must be 4 inch to inside foundation 2. water heater will require pan with drain 3. no fixture schedule-ADA requirements must be used
|
Plan resubmittals received | | | 9/26/2002 | | DONE |
|
|
|
recieved sheet p-1
|
Routing - PLAN CHECK | 9/18/2002 | | 9/20/2002 | | PASS |
|
|
|
|
Routing - FIRE | 9/18/2002 | | 9/18/2002 | | PASS |
|
|
|
plans to be signed off and final reviews attached
|
Routing - PUBLIC WORKS | 9/17/2002 | | 9/18/2002 | | PASS |
|
|
|
route after fire
|
Routing - FIRE | 9/16/2002 | | 9/16/2002 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/13/2002 | | DONE |
|
|
|
Received three sets of resubmittal sheets A2.1, A4.2, S1.1, S1.2, with cover letters and structural calculations. Routed to Mike Otto.
|
Plan Review Completed(1st rev) | | | 9/9/2002 | | FAIL |
|
|
|
|
Routing - FIRE | 9/6/2002 | | 9/9/2002 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 9/6/2002 | | DONE |
|
|
|
UBC struc and non-struc corrections
|
Routing - PLAN CHECK | 8/30/2002 | | 9/5/2002 | | FAIL |
|
|
|
corrections mailed and faxed to architect
|
Routing Off Site - STRUCTURAL | 8/22/2002 | | 9/5/2002 | | FAIL |
|
|
|
Will contact pdq to take plans to outside eng. when pre-engineered plans are received. kmm. Corrections mailed and faxed to architect with non-struc review. MLO
|
Routing - PLUMBING | 8/28/2002 | | 8/30/2002 | | FAIL |
|
|
|
need stamped drawings for plumbing water , dwv and a fixture schedule.
|
Routing - PLANNING | 8/26/2002 | | 8/28/2002 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 8/23/2002 | | 8/26/2002 | | PASS |
|
|
|
ESC plan approved with conditions attached to drawings. Plan designer was contacted on 8/26/02 about modifing Plan to include BMP maintance check list for use by Responsible Person.
|
Routing - PUBLIC WORKS | 8/14/2002 | | 8/23/2002 | | FAIL |
|
|
|
|
Additional plans submitted | | | 8/22/2002 | | DONE |
|
|
|
Received three copies of pre-engineered building plans. kmm
|
Routing - PLANNING Land Div | 8/13/2002 | | 8/14/2002 | | PASS |
|
|
|
Orig. lot of record.
|
First Notice | 8/13/2002 | 8/13/2002 | 8/13/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/13/2002 | | PEND |
|
|
|
Requires 1. Three copies of pre-engineered plans.
Contacted Robert Feldmann at ###-#### of this need. Will hold outside eng. until engineered plans are received. Robert is aware that this will hold up the permit time frame. Robert stated plans should be received by 8/21/02.
|
Plan routing begun/NEW & ADDTN | | | 8/13/2002 | | DONE |
|
|
|
|
Application received | | | 8/13/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/13/2002 | | DONE |
|
|
|
|