BLD-Final | 2/26/2003 | 2/26/2003 | 2/26/2003 | P | PASS |
Tom Arcoraci
|
|
|
Call Cathy when final ok for perm occ 2/26/2003 2:42:35 PM
|
Permanent Occupancy | | 2/26/2003 | 2/26/2003 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 2/26/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9567 issued 2-26-03 to the A-1 Fireplace Shop.
|
Print Occupancy Form | | | 2/26/2003 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/25/2003 | 2/25/2003 | 2/25/2003 | P | PASS |
Troy Cobbley
|
|
|
Phone #: ###-#### Fire life safety finaled 2/25/2003 3:10:00 PM
|
BLD-Conference | 1/15/2003 | 2/19/2003 | 2/19/2003 | P | CANC |
Tom Arcoraci
|
|
|
power disconnect o final insp
|
BLD-Framing/Rough-in | 2/14/2003 | 2/14/2003 | 2/14/2003 | P | PART |
Tom Arcoraci
|
|
|
ok to cover corridor 2/14/2003 3:32:07 PM
|
BLD-Conference | 1/7/2003 | 1/15/2003 | 1/15/2003 | A | FAIL |
Tom Arcoraci
|
|
|
follow up on 5 day notice issued 25 sya notice and order 1/15/2003 3:27:16 PM
|
FIRE-Final Inspection | 1/2/2003 | 1/6/2003 | 1/6/2003 | A | CANC |
Troy Cobbley
|
|
|
The owner stated that they did not call in for the inspection and they are not ready for an inspection 1/6/2003 12:01:31 PM
|
BLD-Aging Inspection | 1/2/2003 | 1/2/2003 | 1/2/2003 | | FAIL |
Tom Arcoraci
|
|
|
occ w/o occ letter 1/7/2003 10:28:11 AM
|
Issue PAID IN FULL permit | | | 9/24/2002 | | DONE |
|
|
|
|
Routing - FIRE | 9/23/2002 | | 9/23/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/23/2002 | | DONE |
|
|
|
|
Telephone call | | | 9/23/2002 | | DONE |
|
|
|
permit ready
|
Print Occupancy Form | | | 9/23/2002 | | DONE |
|
|
|
|
Telephone call | | | 9/23/2002 | | DONE |
|
|
|
permit ready
|
Plan assigned to (R_H) | 8/21/2002 | | 9/23/2002 | | PASS |
|
|
|
9/23/2002 10:59:32 RMH - activity updated through activity BLDA022 from case BLD02-01971.
|
Routing - PLAN CHECK | 9/13/2002 | | 9/23/2002 | | DONE |
|
|
|
|
Telephone call | | | 9/17/2002 | | DONE |
|
|
|
Call Glenn Walker (Architect) and notified him of the water and hydrant issue pending the permit approval. Said he was faxing requirest to United Water and driving out to verify hydrant locations/distances.
|
Routing - FIRE | 9/12/2002 | | 9/13/2002 | | FAIL |
Bill Alexander
|
|
|
Did not answer reference to an exceptable hydrant (fire protection system) location. General notes reference fire sprinkler which is not being provided.
|
Routing - PLAN CHECK | 9/3/2002 | | 9/12/2002 | | PEND |
|
|
|
Permit pending fire departments review and approval / No further corrections required by building department. Routed to fire department on 9/10/02
|
Case Summary (BLD) | | | 9/12/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/12/2002 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/10/2002 | | DONE |
|
|
|
received two sets of resubmittal sheets A-1, A-2, A-3, with cover letter. Routed to Ron Hill.
|
Routing - FIRE | 8/28/2002 | | 9/3/2002 | | FAIL |
Bill Alexander
|
|
|
Verify operable hydrant system UFC 901.2.2.2, 901.3 and 903, mixed occupancy separation UFC Table 3-B, egress requirements UFC Table 10-A, exit travel to be identified UFC 1212.
|
Plan Review Completed(1st rev) | | | 9/3/2002 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/3/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A-1, A-2, A-3, with cover letter. Routed to Ron Hill.
|
Plan resubmittals received | | | 8/29/2002 | | DONE |
|
|
|
Received two copies of revised sheets A-1, A-2 and one copy of response letter. Routed to Ron Hill. kmm
|
Routing - PLAN CHECK | 8/23/2002 | | 8/28/2002 | | FAIL |
|
|
|
Faxed and mailed requirements to Cornel Larson on 8/28/02, Routed plans to the fire department on the same day.
|
Routing - PUBLIC WORKS | 8/21/2002 | | 8/23/2002 | | PASS |
|
|
|
|
Application received | | | 8/15/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/15/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/15/2002 | | DONE |
|
|
|
|