Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD02-02008
StatusFinaled
Name CHURCH OF JESUS CHRIST LATTER DAY S
Site Address 1022 W CHAMBERLIN ST
Project NameBROADWAY WARD STAKE CENTER
Customer Number 
ePlanReviewNo
Description
*Broadway Ward Stake Parking Lot Expansion* - To clear, grub, excavate, grade, and pave for an additional 82 parking lot spaces per engineered plans on file as approved by public works department. Install curbing, paving, striping, and landscaping as noted on the plans. No buildings to be constructed or installed under this permit. PC#530-02 CUP02-00082 SR ESC02-00346
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD4/26/20054/26/20054/26/2005 DONE
First Notice has not been responded to.
First Notice 8/27/20044/26/2005 DONE
Letter of compliance  3/16/2005 DONE
Letter of Compliance issued 3-16-05.
PubWorks Occupancy Approval1/19/20051/19/20051/19/2005 DONE
Finaled without PW approval, no final inspection, drive-by shows complete 1/19/05. R.Rokovitz
Override - Condition Holds  8/27/2004  
Permanent occupancy  8/27/2004 PASS
DetailsWm. Michael Meloy
Compliance met.
FIRE-Final Inspection8/25/20048/26/20048/26/2004APASS
DetailsRick Jackson
darin; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Print Occupancy Form  8/23/2004 DONE
BLD-Aging Inspection8/18/20048/18/20048/18/2004 PART
DetailsJim Storey
pw signed off cw calling to get all others sign off. 8/25/2004 9:54:18 AM
BLD-Aging Inspection6/3/20046/3/20046/3/2004 FAIL
DetailsJim Storey
no resolve info as of yet. 6/4/2004 4:35:40 PM
BLD-Aging Inspection3/19/20043/19/20043/19/2004 FAIL
DetailsJim Storey
First that I have heard about it. I'll talk to Doug, but I believe it is standard that we will not sign off until condition is met or bonded for. CO is our leverage.

Can anyone shed some light on this?


>>> JENIFER GILLILAND 03/15/04 10:04AM >>>
Teresa--

We have a permit that we are having a hard time finaling out because they put in a storm drainage system that did not conform with the plans that were approved by the city. At least that is what the engineer who drew up the plans says. The project, a church parking lot, is completed. Before the project is finaled out, the engineer is supposed to provide the city with a letter that certifies that the design has been built per his specs. Public Works will not sign off on the project until that letter is provided. This permit keeps going around and around in our permit aging system. The permit only involved a parking lot, so going after someone's CO or turning off the lights might be a little drastic. It is also a public works issue and P and Z hasn't signed off on it yet. Any suggestions on how we can get some action on this?


*Broadway Ward Stake Parking Lot Expansion* - To clear, grub, excavate, grade, and pave for an additional 82 parking lot spaces per engineered plans on file as approved by public works department. Install curbing, paving, striping, and landscaping as noted on the plans. No buildings to be constructed or installed under this permit. PC#530-02 CUP02-00082 SR ESC02-00346
3/22/2004 4:54:01 PM
BLD-Aging Inspection1/8/20041/8/20041/8/2004 FAIL
DetailsJim Storey
pending p/w 1/8/2004 8:08:39 AM
BLD-Aging Inspection10/21/200310/21/200310/21/2003 FAIL
DetailsJim Storey
pending sign off from p/w isue addressed with b murphy and j gililand. 10/21/2003 8:15:08 AM
BLD-Aging Inspection7/31/20037/31/20037/31/2003 PART
DetailsJim Storey
don at ###-#### starting all sign off as soon as arch. provides card in his possition. 7/31/2003 10:31:42 AM
Override - Parcel Holds  5/1/2003  
Issue PAID IN FULL permit  5/1/2003  
Telephone call  4/28/2003 DONE
LEFT MESS THAT PERMIT IS READY
Telephone call  4/28/2003 DONE
TALKED TO NAN WITH THE A.C.H.D. NEEDS TO SEE PLANS BEFORE ISSUING BLD PERMIT/MLS
Telephone call  4/28/2003 DONE
TALKED TO REX HANSEN WILL PICKUP PERMIT OR WILL VOID
Telephone call  10/29/2002 DONE
talked to rex hansen to verify plans are ready-waiting on letter from a.c.h.d. will pickup in a week from wed
Print Pending Permit.LaserJet4  9/27/2002 DONE
PLANS/APPL TAKEN TO FRONT DESK  9/27/2002 DONE
Inspection Record Card- Bld  9/27/2002 DONE
Telephone call  9/27/2002 DONE
CALLED LEFT MESSAGE FOR REX PLANS READY 9-27-02///DLD
Routing - PLAN CHECK9/23/2002 9/27/2002 PASS
Routing - PUBLIC WORKS9/17/2002 9/23/2002 PASS
Routing - Erosion and Sediment9/11/2002 9/17/2002 PASS
ESC plan approved with conditions attached to plans.
Routing - FIRE9/6/2002 9/11/2002 PASS
Plan Review Completed(1st rev)  9/11/2002 FAIL
Routing - PLUMBING9/5/2002 9/5/2002 PASS
no pumbing
Routing - PLANNING9/3/2002 9/5/2002 PASS
Routing - PUBLIC WORKS8/26/2002 8/30/2002 FAIL
Requires Drainage Plan Revision
Routing - PLANNING Land Div8/21/2002 8/26/2002 PASS
Okay. Block 32 of Dundees 3rd Subdivision
Plans ACCEPTED BY PLAN TECH  8/21/2002 DONE
Application received  8/21/2002 DONE