Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 10/3/2003 | 4/26/2005 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 1/18/2005 | 1/18/2005 | 1/18/2005 | | DONE |
|
|
|
Finaled without PW approval, no final inspection. Drive-by shows complete 1/18/05. R.Rokovitz
|
Fee Review-notes | 9/10/2002 | 9/10/2002 | 8/10/2004 | | DONE |
|
|
|
|
BLD-Final | 10/3/2003 | 10/3/2003 | 10/3/2003 | P | PASS |
Jim Sly
|
|
|
darin; Phone #: ###-#### Internet Inspection Request from: Annette Moore C/C issued. 10/3/2003 4:05:26 PM
|
DOC - Permit Finaled | 10/3/2003 | 10/3/2003 | 10/3/2003 | P | PASS |
Jim Sly
|
|
|
Finaled by inspector at 10/3/2003 4:05:32 PM
|
FIRE-Final Inspection | 9/24/2003 | 9/25/2003 | 9/25/2003 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety is ok. I spoke to the Action people about getting their fire extinguishers inspected 9/25/2003 2:42:14 PM
|
BLD-Framing/Rough-in | 7/21/2003 | 7/21/2003 | 7/21/2003 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/21/2003 at 10:31:10 AM. Contact: ###-####. needs stand off on posts 7/21/2003 3:18:30 PM
|
BLD-Conference | 6/19/2003 | 6/20/2003 | 6/20/2003 | A | PASS |
Tom Arcoraci
|
|
|
###-#### ok to pour footins for posts 6/19/2003 2:53:03 PM
|
Issue PAID IN FULL permit | | | 6/11/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/10/2003 | | DONE |
|
|
|
|
Telephone call | | | 6/10/2003 | | DONE |
|
|
|
permit ready and fees due
|
Routing - PUBLIC WORKS | 6/9/2003 | | 6/9/2003 | | PASS |
|
|
|
REVISED SCOPE OF WORK
|
Routing - PLAN CHECK | 6/9/2003 | | 6/9/2003 | | PASS |
|
|
|
revised scope of work
|
Routing - PLUMBING | 6/5/2003 | | 6/9/2003 | | PASS |
|
|
|
REVISED SCOPE OF WORK. no plumbing
|
Routing - FIRE | 6/5/2003 | | 6/5/2003 | | PASS |
|
|
|
Based on meeting today with architect, Robert Hess and clarification of plans and permit scope, plans approved without written comments. No IFC requirements for the proposed modifications. No grading or change to existing FD access routes is being done. Revised work is NOT related to pending permit BLD 02-01727.
|
Routing - FIRE | 5/27/2003 | | 6/4/2003 | | FAIL |
|
|
|
REVISED SCOPE OF WORK(MS).
Plans are not consistent with scope of work. Plan C2.10 indicates replacement of asphalts indicate replace Called architect, set up meeting to discuss 6/5/03 9:00 am
|
Plan resubmittals received | | | 6/3/2003 | | DONE |
|
|
|
Revised scope of work. Received five copies of revised sheet C2.31 and one copy of cover letter. Routed to Marlene. kmm
|
Routing - PLANNING | 5/20/2003 | | 5/25/2003 | | PASS |
|
|
|
Approved per DRH02-82 and Modification.
|
Routing - Erosion and Sediment | 5/19/2003 | | 5/20/2003 | | PASS |
|
|
|
REVISED SCOPE OF WORK. Original ESC permit has expired. (180 days). New ESC permit application is required with fees. Tim Hogland Extended Permit. A revised ESC plan has been submitted and approved. Original ESC permit # esc02-00210.
|
Routing - PUBLIC WORKS | 5/14/2003 | | 5/19/2003 | | PASS |
|
|
|
REVISED SCOPE OF WORK.
|
CHANGE STATUS TO (PND) | | | 5/14/2003 | | |
|
|
|
PER MARLENE
|
Plan resubmittals received | | | 5/14/2003 | | DONE |
|
|
|
REVISED SCOPE OF WORK plans submitted by Bob Hess. No longer to building new building (BLD02-01727), only to remodel existing structure (BLD02-02201). Took plans out of the "ready" status from permit desk and began routing revised plans.
|
CHANGE STATUS TO (R) | | | 4/8/2003 | | DONE |
|
|
|
not picked up they have extension until July 4
|
Inspection Record Card- Bld | | | 4/4/2003 | | |
|
|
|
|
Permit EXTENDED | | | 4/4/2003 | | DONE |
|
|
|
per tim hogland extend permit until july 4th/mls
|
Telephone call | | | 10/29/2002 | | DONE |
|
|
|
CALLED BOB 10-29-02///DLD
|
Inspection Record Card- Bld | | | 9/13/2002 | | DONE |
|
|
|
|
Telephone call | | | 9/13/2002 | | DONE |
|
|
|
permit ready and fees due...said they would pick up in january
|
Plan assigned to (MLO) | 9/10/2002 | 9/10/2002 | 9/12/2002 | | PASS |
Mike Otto
|
|
|
9/12/2002 14:43:22 MLO - activity updated through activity BLDA022 from case BLD02-02201.
|
Routing - PLAN CHECK | 9/12/2002 | | 9/12/2002 | | PASS |
|
|
|
all other office activity on BLD02-01727
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/12/2002 | | DONE |
|
|
|
|
Application received | | | 9/10/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/10/2002 | | DONE |
|
|
|
|