(FAIRVIEW PLAZA OFFICE COMPLEX) To construct a 16' x 40' canopy structure, an extension to the existing canopy at the front of the above address. The new and existing canopy to be faced with metal standing seam roofing, to be under separate roofing permit, per approved plans, to include notes, plan review comments and attached structural engineering details, on file and CZC02-00136. Work includes structural wood beams & joists, plywood sheathing, tube steel columns, concrete footings & piers and brick facade at columns. A "Letter of Completion / Compliance" is required for this project. PC#02-615/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/18/20032/19/20032/19/2003APASS
DetailsJim Sly
steve--call 1st before insp; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie C/C issued. 2/19/2003 9:10:34 AM
DOC - Permit Finaled2/19/20032/19/20032/19/2003APASS
DetailsJim Sly
Finaled by inspector at 2/19/2003 9:10:40 AM
BLD-Framing/Rough-in11/20/200211/21/200211/21/2002APASS
DetailsJim Sly
STEVE; Phone #: ###-#### Internet Inspection Request from: Darla Downs
Plan Reviewer's activity  10/18/2002  
Plan resubmittal of 10/17/02 distributed to structural field inspector as the permit has allready been issued. This is in accord with Boise City PDS Dept. Policy once the permit is issued. It is then up to the inspector and their immediate supervisor to determine if the plans need to be re-routed through the plan review division or can be handled by the structural inspection division of the PDS Dept.
Plan resubmittals received  10/17/2002 DONE
Received two copies of detail "Existing Roof to New Canopy" . Routed to Dan Stuart.
CHANGE ISSUED DATE  10/14/2002  
Issue PAID IN FULL permit  10/14/2002 DONE
CHANGE STATUS TO (R)  10/14/2002 DONE
darla issured wrong plans should have been fire
Plan assigned to (DRS)9/23/2002 10/1/2002 PASS
DetailsDan Stuart
10/1/2002 13:32:45 DRS - activity updated through activity BLDA022 from case BLD02-02233.
Routing - PLAN CHECK9/26/2002 10/1/2002 PASS
Approved as noted & attached plan review comments & engineering details, all as part of the approved plans requiring compliance for issuance of a letter of completion for this project.
PLANS/APPL TAKEN TO FRONT DESK  10/1/2002 PASS
To permit desk to issue.
Inspection Record Card- Bld  10/1/2002 DONE
Telephone call  10/1/2002 DONE
permit ready and fees due
Routing - PUBLIC WORKS9/23/2002 9/25/2002 PASS
Routing - PLANNING9/25/2002 9/25/2002 PASS
Approved per CZC02-136.
Plans ACCEPTED BY PLAN TECH  9/13/2002 DONE
First Notice9/12/20029/12/20029/12/2002 DONE
Application received  9/12/2002  