BLD-Final | 3/11/2003 | 3/13/2003 | 3/13/2003 | A | PASS |
Dave Hannah
|
|
|
Josh, ###-#### c.c # 23798 issued 3/13/2003 9:29:22 AM
|
DOC - Permit Finaled | 3/13/2003 | 3/13/2003 | 3/13/2003 | A | PASS |
Dave Hannah
|
|
|
Finaled by inspector at 3/13/2003 9:29:26 AM
|
BLD-Final | 3/7/2003 | 3/7/2003 | 3/7/2003 | P | FAIL |
Dave Hannah
|
|
|
Josh, ###-#### c/n on site 3/7/2003 3:23:12 PM
|
BLD-Energy code compliance | 12/23/2002 | 12/24/2002 | 12/24/2002 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: alan gossi ok to cover 12/24/2002 3:17:56 PM
|
BLD-Framing/Rough-in | 12/19/2002 | 12/20/2002 | 12/20/2002 | P | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: alan gossi ok to insulate after plumbing r/i aproval 12/20/2002 2:18:12 PM
|
BLD-Wall cover | 12/6/2002 | 12/6/2002 | 12/6/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/06/2002 at 09:49:01. Contact: ###-####. shear ok to cover ext 12/6/2002 3:56:23 PM
|
BLD-Wall cover | 12/3/2002 | 12/4/2002 | 12/4/2002 | A | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: alan gossi no city aproved plans on site 12/4/2002 8:35:59 AM
|
BLD-Wall cover | 12/4/2002 | 12/4/2002 | 12/4/2002 | P | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: alan gossi every thing ok but for six floor to floor mst36 straps on front of house 12/4/2002 2:50:15 PM
|
BLD-Foundation | 10/7/2002 | 10/8/2002 | 10/8/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/07/2002 at 19:24:58. Contact: ###-####.work in progress about 25% complete 10/8/2002 10:53:12 AM
|
BLD-Footing | 10/7/2002 | 10/7/2002 | 10/7/2002 | P | PART |
Steven Webb
|
|
|
###-#### wip-5% ready 10/7/2002 3:09:46 PM
|
Issue PAID IN FULL permit | | | 10/4/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/2/2002 | | DONE |
|
|
|
|
CHANGE STATUS TO (PND) | | | 10/1/2002 | | DONE |
|
|
|
CHANGE TO PEND PER STEVE MONROE
|
Routing - PLAN CHECK | 10/1/2002 | | 10/1/2002 | | DONE |
|
|
|
Builder decided to change the attached two car garage to a three car garage. Route to Planning and Zoning and Plan Review.
|
Case Summary (BLD) | | | 10/1/2002 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/16/2002 | | 9/25/2002 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 9/24/2002 | | 9/25/2002 | | PASS |
Steve Munroe
|
|
|
9/25/2002 08:42:38 SAM - activity updated through activity BLDA022 from case BLD02-02250.
|
Case Summary (BLD) | | | 9/25/2002 | | |
|
|
|
|
Plan Review Report | | | 9/25/2002 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/25/2002 | | DONE |
|
|
|
|
Telephone call | | | 9/25/2002 | | DONE |
|
|
|
called left message 9-25-02///dld
|
Pending Assignment by DJO | 9/16/2002 | | 9/24/2002 | | DONE |
Dan Overy
|
|
|
9/24/2002 10:41:09 SAM - activity updated through activity BLDA183 from case BLD02-02250.
|
Application received | | | 9/16/2002 | | |
|
|
|
|
Routing - PLANNING | 9/16/2002 | | 9/16/2002 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/16/2002 | | 9/16/2002 | | DONE |
|
|
|
|