(Gas Station Canopy) - To construct a new 2080 square foot, 20 foot high, four column, steel canopy for weather protection over a fuel pump island. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - L/C Approved  4/7/2003 DONE
#22842 for Ultra Touch Car Wash Canopy
BLD-Framing/Rough-in3/27/20033/28/20033/28/2003APASS
DetailsRuss Owen
eric; Phone #: ###-#### Internet Inspection Request from: Annette MooreOk perm oc. 3/28/2003 5:37:20 PM
FIRE-Final Inspection3/28/20033/28/20033/28/2003PPASS
DetailsRick Jackson
Code Occupancy Approval  3/28/2003 PASS
ALL IN FINAL SIGNED OFF.
BLD-Foundation12/5/200212/5/200212/5/2002PPASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 12/05/2002 at 09:51:48. Contact: ###-####. footings for canopy. 12/5/2002 3:56:51 PM
Plan assigned to (JCM)9/16/20029/16/200211/25/2002 PASS
DetailsJohn Menard
11/25/2002 09:52:03 JCM - activity updated through activity BLDA022 from case BLD02-02258.
Routing - PLAN CHECK10/23/2002 11/25/2002 PASS
PLANS/APPL TAKEN TO FRONT DESK  11/25/2002 PASS
Inspection Record Card- Bld  11/25/2002 DONE
Print Occupancy Form  11/25/2002 DONE
Telephone call  11/25/2002 DONE
CALLED 11-25-02
Issue PAID IN FULL permit  11/25/2002 DONE
Plan resubmittals received  11/13/2002 DONE
Received four sets of resubmittal sheets 1, 2, and (3) sets of TFC Canopy calculations with cover letter. Routed to John Menard.
Plan resubmittals received  10/23/2002 DONE
Received two copies of revised sheets, CS-1, SD-1, A-2, A-3, A-4, A-5, A-6, A-7, A-9, A-10, A-11 and EX-1. Structural sheets S2.1 & S7.1. Routed to John M. kmm
Plan resubmittals received  10/23/2002 DONE
Received three copies of revised structural sheets 1 and 2. Revised calcs. Routed to John M. kmm
Routing - FIRE10/18/2002 10/22/2002 PASS
DetailsBill Alexander
No notes attached
Plan Review Completed(1st rev)  10/22/2002 DONE
Plan resubmittals requested  10/18/2002 FAIL
Mailed and faxed the architect of record a copy of the plan review comment list requesting revisions. JCM
Routing - PLAN CHECK10/11/2002 10/18/2002 FAIL
Routing - PLUMBING10/8/2002 10/11/2002 PASS
1. building cleanouts are required on sewer lines exiting building 2 feet outside 4 locations 2. water heater p-15 will require expansion protection 3. water heaters may require a pan with a drain effective 11/1/02.
Routing - PLANNING10/1/2002 10/8/2002 PASS
Approve per DRH02-88 - condition 1(i): Lights at the canopy shall be restricted to 320 watts with a diffuser baffle installed with a vertical burn lamp...
Routing - PUBLIC WORKS9/30/2002 10/1/2002 PASS
Routing - Erosion and Sediment9/26/2002 9/27/2002 PASS
ESC Plan approved with attached conditions.
Additional plans submitted  9/25/2002 DONE
Received two copies of ESC sheet 1 and 2 and two copies of narrative. Put with plans. kmm
Routing - PUBLIC WORKS9/17/2002 9/20/2002 FAIL
requires drainage plan revision per Brian M. kmm
Routing - PLANNING Land Div9/16/2002 9/17/2002 PASS
ROS 5877.
First Notice9/16/20029/16/20029/16/2002 DONE
Plans ACCEPTED BY PLAN TECH  9/16/2002 DONE
Received drawings with calculations, incorporated into building permit drawings as per John Menard.
Application received  9/16/2002  
Recd Pcfee & Taken To Pln CK  9/16/2002 DONE