Information based on query as of Saturday, August 17, 2024.
Permit Information
Permit NumberBLD02-02263
StatusFinaled
Name AVIATION FINANCE GROUP
Site Address 4355 W EMERALD ST Unit: 100
Project NameEMERALD SQUARE-1ST FLR
Customer Number 
ePlanReviewNo
Description
(AVIATION FINANCE GROUP)(EMERALD SQUARE-1ST FLR-SUITE #100) New 1,796 sq. ft. expansion to an existing 7,200 sq. ft. office tenant on first floor of existing building per approved plans on file. New tenant space total will be 8,996 sq.ft. Work to include some minor interior demolition work, new portions of one-hour rated corridor walls/ceiling, new 20 minute rated door, new interior walls, some new interior doors and sidelights, some new suspended ceiling work, interior finish, mechanical work, and electrical work. A new Certificate of Occupancy is to be issued with the new occupant load total when completed and approved. NOTE: This building is NOT fire sprinklered. (PC#0619-02) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent occupancy UNPAID FEE  11/29/2002 DONE
issued Perm. Occ. Cert. #9460 to Aviation Finance Group
Permanent Occupancy 11/26/200211/26/2002 DONE
Details
BLD-Final11/25/200211/26/200211/26/2002PPASS
DetailsTom Arcoraci
robert; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie o 11/26/2002 1:35:03 PM for 11/26/2002 1:35:05 PM perm 11/26/2002 1:35:10 PM
BLD-Framing/Rough-in11/20/200211/21/200211/21/2002PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 11/20/2002 at 15:25:17. Contact: ###-####. GRID INSPECTION grid ok 11/21/2002 4:30:16 PM
BLD-Final11/20/200211/21/200211/21/2002ACANC
DetailsTom Arcoraci
###-#### NEEDED A R/I NOT A FINAL
FIRE-Final Inspection11/21/200211/21/200211/21/2002PPASS
DetailsTroy Cobbley
fire life/safety ok. No office doors or hardware have been installed yet and will have to be verified by the structural inspector 11/21/2002 2:01:55 PM
BLD-Framing/Rough-in11/15/200211/18/200211/18/2002AFAIL
DetailsTom Arcoraci
###-####
grid not ready 11/18/2002 10:39:05 AM
BLD-Framing/Rough-in10/22/200210/22/200210/22/2002PPASS
DetailsTom Arcoraci
###-####
BLD-Conference10/16/200210/17/200210/17/2002APASS
DetailsTom Arcoraci
call first so robert can meet you; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung wip ok 10/17/2002 9:34:55 AM
Issue PAID IN FULL permit  10/15/2002  
Telephone call  10/2/2002 DONE
message permit ready and fees due
Plan assigned to (JCB)9/24/2002 10/1/2002 PASS
DetailsJason Blais
10/1/2002 15:41:10 JCB - activity updated through activity BLDA022 from case BLD02-02263.
Routing - FIRE9/30/2002 10/1/2002 PASS
approved without written comment
Routing - PLAN CHECK10/1/2002 10/1/2002 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  10/1/2002 PASS
Inspection Record Card- Bld  10/1/2002 DONE
Print Occupancy Form  10/1/2002 DONE
Routing - PLAN CHECK9/25/2002 9/30/2002 PEND
Plan review report sent and faxed to architect. No response required. When approved by Fire Dept. permit can be issued. Plans routed to Fire Dept.
Routing - PUBLIC WORKS9/24/2002 9/25/2002 PASS
Plans ACCEPTED BY PLAN TECH  9/18/2002 DONE
First Notice9/16/20029/16/20029/16/2002 DONE
Application received  9/16/2002  
Recd Pcfee & Taken To Pln CK  9/16/2002 DONE