BLD-Final | 5/12/2003 | 5/13/2003 | 5/13/2003 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/12/2003 at 2:08:43 PM. C/C issued. 5/13/2003 11:49:35 AM
|
DOC - Permit Finaled | 5/13/2003 | 5/13/2003 | 5/13/2003 | P | PASS |
Jim Sly
|
|
|
Finaled by inspector at 5/13/2003 11:49:42 AM
|
PostCard Mailed | | | 5/10/2003 | | SENT |
|
|
|
PostCard has been mailed requesting inspection.
|
BLD-Framing/Rough-in | 11/5/2002 | 11/6/2002 | 11/6/2002 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/05/2002 at 13:15:03. Contact: ###-####. Energy OK 11/6/2002 9:39:06 AM
|
BLD-Framing/Rough-in | 11/4/2002 | 11/5/2002 | 11/4/2002 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/04/2002 at 13:43:33. Contact: ###-####. waiting on plumbing
|
BLD-Framing/Rough-in | 10/24/2002 | 10/25/2002 | 10/25/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/24/2002 at 16:20:50. Contact: ###-####.shear ok to cover ext needs plumb r/i also talked about rafter ties and picking up point load on roof ridge 10/25/2002 10:14:36 AM
|
BLD-Foundation | 10/1/2002 | 10/2/2002 | 10/2/2002 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/01/2002 at 11:58:26. Contact: ###-####.
|
BLD-Foundation | 9/30/2002 | 9/30/2002 | 9/30/2002 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 09/30/2002 at 10:14:55. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 9/23/2002 | | DONE |
|
|
|
|
Application received | | | 9/20/2002 | | |
|
|
|
|
Plan assigned to (PEP) | 9/20/2002 | | 9/20/2002 | | PASS |
Perry Paine
|
|
|
9/20/2002 14:55:34 PEP - activity updated through activity BLDA022 from case BLD02-02322.
|
Print Pending Permit.LaserJet4 | | | 9/20/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/20/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/20/2002 | | DONE |
|
|
|
|
Telephone call | | | 9/20/2002 | | DONE |
|
|
|
PERMIT READY AND FEED DUE
|