Fee Review-notes | 9/23/2002 | 9/23/2002 | 8/10/2004 | | DONE |
|
|
|
|
First Notice | | 11/6/2003 | 11/6/2003 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 11/6/2003 | | DONE |
|
|
|
Perm. Occ. Cert. # 9866 issued 11-6-03 to the Digestive Health Clinic.
|
Permanent Occupancy | | 11/5/2003 | 11/5/2003 | | DONE |
|
|
|
|
BLD-Final | 11/5/2003 | 11/5/2003 | 11/5/2003 | P | PASS |
Tom Arcoraci
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok for perm occ 11/5/2003 1:55:32 PM
|
BLD-Final | 10/27/2003 | 10/28/2003 | 10/28/2003 | P | PART |
Tom Arcoraci
|
|
|
Jan; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes cn posted ok for temp 10/28/2003 3:50:57 PM
|
FIRE-Final Inspection | 10/27/2003 | 10/28/2003 | 10/28/2003 | A | PASS |
Troy Cobbley
|
|
|
fire sprinklers, fire alarm and fire life safety finaled 10/28/2003 12:01:34 PM
|
FIRE-Final Inspection | 10/23/2003 | 10/24/2003 | 10/24/2003 | A | FAIL |
Troy Cobbley
|
|
|
Provide signage per review note 10, provide emergency light by south exit and provide verification that the sliding glass exam room doors meet ada 10/24/2003 9:08:33 AM
|
Code Occupancy Approval | | | 10/17/2003 | | PASS |
|
|
|
Compliance to DRH02-00203 Mod.
|
PubWorks Occupancy Approval | 10/16/2003 | 10/16/2003 | 10/16/2003 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 10/16/03. R.Rokovitz
|
BLD-Aging Inspection | 10/13/2003 | 10/13/2003 | 10/13/2003 | | PART |
Tom Arcoraci
|
|
|
wip 10/13/2003 9:23:22 AM
|
BLD-Framing/Rough-in | 8/11/2003 | 8/12/2003 | 8/12/2003 | A | PART |
Tom Arcoraci
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie 2 hr must go to deck 8/12/2003 10:55:28 AM
|
FIRE-Conference | 7/30/2003 | 7/30/2003 | 7/30/2003 | P | FAIL |
Troy Cobbley
|
|
|
I stopped at this project to verify that no fire alarm work was being performed and found conduit, boxes and fire alarm FPLP 12 guage wiring installed. A stop work order was issued to Quality Electrics (###-####) job foreman who's name is Alan. The actually man that installed the fire alarm, who also works for quality is Scott according to Alan.
|
BLD-Framing/Rough-in | 7/21/2003 | 7/22/2003 | 7/22/2003 | P | CANC |
Tom Arcoraci
|
|
|
ROOF DRAINS
|
BLD-Framing/Rough-in | 6/13/2003 | 6/13/2003 | 6/13/2003 | P | PART |
Tom Arcoraci
|
|
|
OK TO COVER- JAN; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok to cover east side 6/13/2003 2:22:34 PM
|
BLD-Framing/Rough-in | 6/9/2003 | 6/10/2003 | 6/10/2003 | A | PART |
Jim Sly
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Bsmnt OK to cover.....S.C. 6/10/2003 11:47:01 AM
|
BLD-Framing/Rough-in | 6/2/2003 | 6/2/2003 | 6/2/2003 | P | PART |
Tom Arcoraci
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Annette Moore wip ok 6/2/2003 2:33:39 PM
|
BLD-Framing/Rough-in | 5/21/2003 | 5/22/2003 | 5/22/2003 | A | PART |
Tom Arcoraci
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Annette Moore wip ok 5/22/2003 10:32:34 AM
|
BLD-Framing/Rough-in | 5/5/2003 | 5/5/2003 | 5/5/2003 | P | PART |
Dave Hannah
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Annette Moore steel trusses on roof ok to cover areas that are tobe over built 5/5/2003 2:54:13 PM
|
BLD-Footing | 3/6/2003 | 3/7/2003 | 3/7/2003 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/6/2003 at 2:44:33 PM. Contact: ###-####.
|
BLD-Foundation | 3/6/2003 | 3/6/2003 | 3/6/2003 | P | PART |
Tom Arcoraci
|
|
|
wip ok south side
|
BLD-Footing | 3/4/2003 | 3/5/2003 | 3/5/2003 | P | PASS |
Tom Arcoraci
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Foundation | 3/4/2003 | 3/5/2003 | 3/5/2003 | P | PASS |
Tom Arcoraci
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Footing | 3/3/2003 | 3/4/2003 | 3/4/2003 | P | PART |
Tom Arcoraci
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Framing/Rough-in | 3/3/2003 | 3/3/2003 | 3/3/2003 | P | CANC |
Tom Arcoraci
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Footing | 3/3/2003 | 3/3/2003 | 3/3/2003 | P | PASS |
Tom Arcoraci
|
|
|
wip ok west and south side
|
BLD-Foundation | 2/28/2003 | 2/28/2003 | 2/28/2003 | P | PART |
Tom Arcoraci
|
|
|
rebar-jan; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie sec a ok 1/3 of bld 2/28/2003 11:05:52 AM
|
BLD-Footing | 2/24/2003 | 2/25/2003 | 2/25/2003 | P | PART |
Russ Owen
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung This is a partial inspection, all concrete is required to be done by a special inspection. 2/25/2003 2:01:10 PM
|
BLD-Footing | 1/7/2003 | 1/9/2003 | 1/9/2003 | P | PART |
Russ Owen
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Work subject to special inspection. 1/9/2003 2:37:28 PM
|
(F) Reprint permit | | | 12/18/2002 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/17/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/17/2002 | | DONE |
|
|
|
|
Telephone call | | | 12/17/2002 | | DONE |
|
|
|
permit ready and fees due
|
Issue PAID IN FULL permit | | | 12/17/2002 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 9/26/2002 | | 12/16/2002 | | PASS |
Mike Otto
|
|
|
12/16/2002 14:08:42 MLO - activity updated through activity BLDA022 from case BLD02-02339.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/16/2002 | | DONE |
|
|
|
|
Routing - FIRE | 12/11/2002 | | 12/13/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 12/9/2002 | | 12/10/2002 | | PASS |
|
|
|
Approved per DRH01-196; DrH02-120; DRH02-203 and as noted on sheet A1.1.
|
Routing - PLAN CHECK | 12/6/2002 | | 12/9/2002 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 11/19/2002 | | 12/9/2002 | | PASS |
|
|
|
Contacted PDQ to take plans to outside eng. kmm
|
Plan resubmittals received | | | 12/6/2002 | | DONE |
|
|
|
Received six copies of revised sheet A1.1. Two copies of revised sheet A2.6 and A8.1. Routed to Mike O. kmm
|
Routing - PLANNING | 12/3/2002 | | 12/6/2002 | | |
|
|
|
|
Plan resubmittals received | | | 12/3/2002 | | DONE |
|
|
|
Sheet M8.0 received and forwarded to Mike Otto.
|
Routing - PLANNING | 11/29/2002 | | 12/3/2002 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 12/3/2002 | | DONE |
|
|
|
Received three copies of reivsed sheet A1.1, however they were not signed. Contacted Sam B. of this need. Steve is out of office until Monday 12/9/02. kmm
|
Routing - PLUMBING | 11/27/2002 | | 11/29/2002 | | PASS |
|
|
|
per plans , 2000 upc and nfpa 99.
|
Routing - FIRE | 11/26/2002 | | 11/27/2002 | | FAIL |
|
|
|
|
Plan Review Completed(1st rev) | | | 11/27/2002 | | FAIL |
|
|
|
|
Routing - PLANNING | 11/21/2002 | | 11/25/2002 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 11/20/2002 | | DONE |
|
|
|
Received three copies of comment response to Item no. 26. Routed to Mike Otto.
|
Routing - PUBLIC WORKS | 11/4/2002 | | 11/12/2002 | | PASS |
|
|
|
Route back to PW after intial review completed
|
Plan resubmittals received | | | 11/7/2002 | | DONE |
|
|
|
Received three sets of resubmittal sheets C1.0, C2.0, C3.0, C4.0, C5.0, A1.1, A2.2, A2.7, A3.1, A3.4, A3.5, A5.1, S1.1, S1.2, S2.1, S2.3, S3.1, S3.2, M2.1, M4.1, M6.0, M7.0, with (3) cover letter attached to structural calculations. Routed to Mike Otto.
|
Plan Review Completed(1st rev) | | | 11/4/2002 | | DONE |
|
|
|
|
Routing - FIRE | 10/30/2002 | | 11/4/2002 | | FAIL |
Bill Alexander
|
|
|
Lack access turn radius, verify required separations, medical gas quantities, generator questions.
|
Plan resubmittals requested | | | 10/30/2002 | | DONE |
|
|
|
UBC structural and non-structural corrections
|
Routing Off Site - STRUCTURAL | 9/26/2002 | | 10/29/2002 | | FAIL |
|
|
|
contacted PDQ to take plans to outside eng. kmm
|
Routing - PLAN CHECK | 10/23/2002 | | 10/29/2002 | | FAIL |
|
|
|
corrections to architect at meeting 10/20/2002
|
Routing - PLUMBING | 10/11/2002 | | 10/22/2002 | | FAIL |
|
|
|
2" waste in room 226 needs to be 3", thermol expantion tank st-5 is too small, drainage required for medical air compressor and must be located separatly from med gas cylinder storage, show compressor intake and vacuum pump exhaust locations.
|
Routing - PLANNING | 10/3/2002 | | 10/10/2002 | | FAIL |
|
|
|
Passed to DR on 10/07/02. Approved per CUO02-00081 (Mod) applicant red-lined drawings adding (3) handicape parking spaces, (1) of which is Van Accessible.
DR- This application is going to need a Committee level modification for the changes to the roof, windows, and site. Sam Burrows has been notified and we are working on the application.
|
Routing - Erosion and Sediment | 10/2/2002 | | 10/3/2002 | | PASS |
|
|
|
ESC Plan approved with conditions attached to drawings.
|
Routing - PUBLIC WORKS | 9/26/2002 | | 10/2/2002 | | FAIL |
|
|
|
Requires drainage plan revision per Brian M. kmm
|
Plan resubmittals received | | | 9/30/2002 | | DONE |
|
|
|
Received five copies of revised sheets C1.0, C2.0, C3.0 and C4.0. Had Rob of Kriezenbeck put with plans. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 9/26/2002 | | DONE |
|
|
|
Waiting for two copies of soils report. kmm
|
Routing - PLANNING Land Div | 9/26/2002 | | 9/26/2002 | | PASS |
|
|
|
Approved as per ROS 5847.
|
Plan routing begun/NEW & ADDTN | | | 9/26/2002 | | DONE |
|
|
|
|
Application received | | | 9/23/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/23/2002 | | |
|
|
|
|