BLD-Aging Inspection | 5/3/2005 | 5/3/2005 | 5/3/2005 | | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 5/3/2005 | 5/3/2005 | 5/3/2005 | P | PASS |
Jim Storey
|
|
|
|
Letter of compliance | | | 12/13/2002 | | DONE |
|
|
|
Letter of Compliance #22784 issued 12-13-02.
|
BLD-Final | 12/12/2002 | 12/12/2002 | 12/12/2002 | P | PASS |
Russ Owen
|
|
|
Mike, ###-#### - all others are finaled - call Cathy if approved ok perm oc. 12/12/2002 5:27:56 PM
|
BLD-Final | 11/6/2002 | 11/7/2002 | 11/7/2002 | A | CANC |
Carl Dependahl
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Final | 11/6/2002 | 11/7/2002 | 11/7/2002 | A | PART |
Russ Owen
|
|
|
###-#### mike. 11/6/2002 5:03:31 PM. Ok for a temp oc pending plumbing final approval. 11/7/2002 9:57:44 AM
|
Temporary occupancy | | | 11/7/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4883 issued 11-7-02 to Fuzziwig's Candy Company at Boise Towne Square.
|
FIRE-Final Inspection | 11/5/2002 | 11/6/2002 | 11/6/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled. Structural inspector to verify that the "door to remain unlocked" sticker got installed 11/6/2002 11:25:46 AM
|
BLD-Final | 11/4/2002 | 11/5/2002 | 11/5/2002 | A | NR |
Tom Arcoraci
|
|
|
next to pretzel time ; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
Plan assigned to (R_H) | 9/27/2002 | | 10/24/2002 | | PASS |
|
|
|
10/24/2002 07:55:11 RMH - activity updated through activity BLDA022 from case BLD02-02371.
|
Routing - PLAN CHECK | 10/11/2002 | | 10/24/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/24/2002 | | |
|
|
|
|
Print Occupancy Form | | | 10/24/2002 | | |
|
|
|
|
Telephone call | | | 10/24/2002 | | DONE |
|
|
|
left mess that permit is ready
|
Issue PAID IN FULL permit | | | 10/24/2002 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/21/2002 | | DONE |
|
|
|
Received three copies of resubmittal sheets A3 and A5.1 with transmittal sheet. Routed to Ron Hill.
|
Routing - FIRE | 10/10/2002 | | 10/11/2002 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 10/11/2002 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 10/1/2001 | | 10/10/2002 | | FAIL |
Ron Hill
|
|
|
Faxed and mailed requirements to the architect and routed plans to the fire department on 10/10/02, Needed more information on the proposed use of foam inside of tenant space.
|
Plan Reviewer's activity | | | 10/10/2002 | | FAIL |
|
|
|
Faxed and mailed requirements to the architect Chuck Tookey on 10/10/02, Routed plans to the fire department on the same day.
|
Plan resubmittals received | | | 10/4/2002 | | DONE |
|
|
|
Received three copies of revised sheet PE1. Routed to Ron H. kmm
|
Routing - PUBLIC WORKS | 9/27/2002 | | 10/1/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/27/2002 | | PEND |
|
|
|
Requires sheet PE1 to be stamped and signed. Have contacted Mike Salyer at ###-#### of this need. CDH approval signed by Robert Mayer on 9/25/02.
|
First Notice | 9/25/2002 | 9/25/2002 | 9/25/2002 | | DONE |
|
|
|
|
Application received | | | 9/25/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/25/2002 | | DONE |
|
|
|
|